A somewhat typical job for me.
I did a few items for the Homeseller prior to close of sale a few months ago.
New owners are getting new flooring installed this week and discovered this:
The underlayment had been previously replaced. I was curious about why there was fixall plaster at the joint to the existing. Ding dingdongs had installed 5/8” instead of 3/4 MDF.
The plate was gone, so I built a PT pony wall on the foundation wall. South side gets hammered by weather here and it’s a second story wall on that side. Wind pushes two stories of water in. PT for prudence.
Vycor wrapped sections of subfloor got banged in under the bottom plates.
I put some Vycor on the subfloor sheet when I laid it down.
Letting the dehumidifier work for a day or two, there is a wet plywood edge under the threshold. Underlayment in a day or two.
5x the standard rate, I’m in it a total of 5 hours + two boards and two studs.
Flooring can go in on Thursday as planned, making me the hero.
Sent from my iPhone using Tapatalk