Water Main Crew Size

5.7K views 9 replies 6 participants last post by  JonSklar  
#1 ·
Just wanted to get an idea of everyone’s thoughts on crew size for a typical water or sewer pipeline project. Our projects are in the range of pipe size 8” - 24” C900 and DIP for water and Sewer ranges 8”-15” VCP &SDR 35 & 26. Trenches are in the range of 1,000LF to 10,000LF. I understand manpower will relate to the allotted time the customer has on the contract but I am looking for input on a single crew to excavate, install & backfill.
 
#4 ·
Depends on how good the operators are. Good operators keep everybody jumping. Half arse operators drag things down. But — that’s a wide open question. Soil type, rocky, sandy, clay etc. Weather in your area the list goes on. I’ve been watching a 2 mile stretch of water line going on 3 months now. Rock & inexperienced operators have some ranchers pissed.

Mike
 
#5 ·
I agree operators make or break the project. I was just curious what everyone was seeing on average for crew size. Example for most projects we look at a 5 man crew plus a super. Running an operator, a ground guy, a pipe fitter, 2 backfill guys. I think that is ideal but wanted to see if that is realistic in the industry? With that many guys i would expect 150LF-200LF per day on a 6’ deep trench. I agree with different variable on soils and depth. But our projects generally sit in a type B soil and 6’ -7’ deep trenches.
 
#9 ·
Last time I was on a crew like that was about 15 years ago

We had I think 6 or 7 guys

One guy on the hoe.

Guy on the grade rod

Guy on the loader bringing pea gravel

2 guys pulling strings and fitting pipe

Loader backfilling

Guy on the walk-behind compactor

Super was in and out

I was either on the machine digging and trying to run the guys, or when I had a guy to dig, I was on the fitting crew.

Fitting crew got real slow with me on a machine.