I am bidding on site work for a future (next year) garage.
Floating concrete slab.
location is northern minnesota, deep freeze land.
The location is on the side of a hill, the back side of the garage will be five feet into the orginal elevation of the hill.
I am planning to bid the following work.
40 x 56 garage slab area
excavate area is to be 60 x 66
excavate into slope of hill zero cut infront and three feet in back.
the excess hill behind garage will be excavated to divert water around garage.
install french drain behind garage to channel water into drain tile that will also be installed on the side excavated walls of the excavated area to flow out the front of the garage area.
natural soil is all clay.
cut into clay soil resulting in a level bottom, with back cut three feet into hill, after removing 2 feet above that (3 feet) for drainage away from building.
excess clay soil behind garage above three feet deep cut will be removed for drainage.
will use pit run gravel compacted to make a three foot thick base for slab.
this is deep freeze land.
Any suggestions or comments on my plan, will take a lot of time involved here to build a base on this unique site.
Floating concrete slab.
location is northern minnesota, deep freeze land.
The location is on the side of a hill, the back side of the garage will be five feet into the orginal elevation of the hill.
I am planning to bid the following work.
40 x 56 garage slab area
excavate area is to be 60 x 66
excavate into slope of hill zero cut infront and three feet in back.
the excess hill behind garage will be excavated to divert water around garage.
install french drain behind garage to channel water into drain tile that will also be installed on the side excavated walls of the excavated area to flow out the front of the garage area.
natural soil is all clay.
cut into clay soil resulting in a level bottom, with back cut three feet into hill, after removing 2 feet above that (3 feet) for drainage away from building.
excess clay soil behind garage above three feet deep cut will be removed for drainage.
will use pit run gravel compacted to make a three foot thick base for slab.
this is deep freeze land.
Any suggestions or comments on my plan, will take a lot of time involved here to build a base on this unique site.