Hey folks,
Started demoing my 1903 balloon framed house. As typical in balloon frame the joists run wall to wall,face nailed into the studs. I am only renovating the 2nd floor, and one thing I'm doing is adding a bathroom. Where the bathroom will be, I am going to double up the 2x8 joists with 7 1/4" LVL. The LVLs will be bolted to the existing 2x8s. I was wondering if there was a way to strengthen the connection of the joist to the stud. Not only in the bathroom but throughout the house. I'll post pictures if you guys like.
Started demoing my 1903 balloon framed house. As typical in balloon frame the joists run wall to wall,face nailed into the studs. I am only renovating the 2nd floor, and one thing I'm doing is adding a bathroom. Where the bathroom will be, I am going to double up the 2x8 joists with 7 1/4" LVL. The LVLs will be bolted to the existing 2x8s. I was wondering if there was a way to strengthen the connection of the joist to the stud. Not only in the bathroom but throughout the house. I'll post pictures if you guys like.