Contractor Talk - Professional Construction and Remodeling Forum banner

Plywood Concrete Forms

33K views 33 replies 18 participants last post by  fjn  
#1 ·
Does anyone have any idea how tall of a wall you can pour with 3/4 inch plywood forms just using cams and ties? If I make the ties close enough together does it matter? Im looking at a job that has a 16 ft tall by 90 ft wall and a 20 ft tall by 50 ft wall. Worried about possibly blowing the forms and 1 inch formboard is hard to get ahold of. Thanks!
 
#5 ·
You can do it with 3/4" form ply. It will be pretty expensive though.
A wall that size.... I would use a double waler system (maybe even up the size of the lumber to 2x6) and place my tie holes at 10 to 12" o. c. at the bottom for about 4 or 5 rows.
How thick is the wall going to be?
 
#13 ·
This is a wall on a dam. Its 12 inches thick. I expect the fill rate to be fairly slow. Like I said I like ply because of the cut up nature of our jobs I can use the ply easier. And I came up a carpenter so its easier to do for me. It will run 3800 to rent symons for the first job, but I am bidding 4 seperate projects at the same time though so I figured I could buy the ply for about 7 and it would last me for a few years. But I don't want any blowouts thats for sure.
 
#9 ·
Tie spacing and whaler spacing are all dependent on the height of the pour and thr rate at which you fill the form.

ACI 347 is the standard publication that will give all of that information. I would suspect that the spacing would be fairly close unless your fill rate is very slow.

I keep a copy of the standard in my office .
 
#15 ·
To do 3/4 forms you are also going to be buying a lot of 2x4's also.

It's not like you couldn't build the gang forms with e-beams and super studs.

There is also Doka Framax system. they could be build in place then pulled out and used again in gang form. Have done that before. :laughing:

Leave the 1 1/8" panels where they belong on a residential job.
 
#16 · (Edited)
In warm enough weather and a slow enough pour rate you could probably do it with a 12' x 12" hole pattern according to ACI. that is a lot of ties. Walls like that you should have a professional design. Are you looking to use plywood because that is the system you own?

if it only the two walls, It hardly calls for a large gang system unless you already have one. they are the best in repetitive situations.
 
#17 ·
Like I said I have done 3/4" form walls that were around 30'-32' tall. We built the walls 16' for the first pour. Then jumped for the top pour. All with the standard 16" layout. To do stuff like that you need good carpenters and pour team.

I prefer a good jump deck system but you know. You build with what you got and you do it good. :thumbsup:
 
#25 ·
Worked concrete for a major construction company for 8 years. I've worked on bridges, dams, buildings and a few other challenging projects. I suggest renting symons or peri, or something similar. The cost difference between form fabrication and labour won't be much different than the rental fees. Plus with a system such as symons, they're much more versatile. Is it a small dam? Most dam jobs I have been on have a crane, which may make it a little easier to move material.
 
#26 ·
Unfortunately there won't be a crane, its very remote, we have to build a make shift road in and out. We are bidding the general contract. So you think that the savings from using Symons on labor would outweigh the plywood? Thats probably pretty close. And Symons forms are going to be stronger in the end right? It is relatively small yeah. 16FT high by 90 ft long with a 12 inch thick wall, then backfill behind it and 8ft tall by 50 foot wall at the bottom and a spillway that goes between.
 
#30 ·
BattleRidge said:
Unfortunately there won't be a crane, its very remote, we have to build a make shift road in and out. We are bidding the general contract. So you think that the savings from using Symons on labor would outweigh the plywood? Thats probably pretty close. And Symons forms are going to be stronger in the end right? It is relatively small yeah. 16FT high by 90 ft long with a 12 inch thick wall, then backfill behind it and 8ft tall by 50 foot wall at the bottom and a spillway that goes between.
I don't have much experience with form ply builds, other than building odd ball fillers or single formed walls. But I would guess the labor savings would be tremendous. Plus scaffold brackets hook right to the forms.