"Anticipated Start Date:#####
Anticipated Completion Date:#####
Contractor will apply for permits on acceptance of this agreement. Actual start date will be within X days of permit being issued.
Contractor not resonsible for delays caused by.... "
Your agreement needs to include language to account for delays beyond your control example: weather, permitting, material shortages etc.