Will this be faster or slower than two layer asphalt? It's over plywood, not skip sheathing.
 

·
Been around
Joined
·
1,151 Posts
On average it will be more labor. However I figure my rate for the tear off, I would allow 25-50% more effort for that portion of the job.

Two asphalt will have less fasteners and a more predictable nailing pattern.



The condition of the shingles, asphalt or cedar, will make the difference.
 

·
diplomat
Joined
·
5,292 Posts
Discussion Starter · #9 ·
Thanks for all the replies. That zoom boom video is horrifying and awesome.
 