Discussion Starter · #1 ·
Does anyone know how long you have to wait between the pouring of the base slab, pouring of the sand cushion and pouring of the final 1/2" terrazzo topping? Can you do the whole process in three consecutive days? Or would you have to wait a month for each layer to cure?
Thanks
 

·
Registered
Joined
·
79 Posts
Discussion Starter · #3 ·
Thanks pipeguy. Do you think when they say cure the underbed, they mean it to be cured the same amount of time as the base slab? The underbed is a one part cement to four part sand mixture.
 

·
Registered
Joined
·
3,265 Posts
Calypso, I hope the link could be some help to you. I figured maybe a little info would get you over the hump. If you need expertise you'll need answers from a FLOORguy or TERRAZZOguy - not a PIPEguy. :Thumbs: Good luck.
 

·
Registered
Joined
·
79 Posts
Discussion Starter · #7 ·
Thanks Bill. From what I have read on terrazzo sites, I need to wait the usual 28 days for the slab cure. They mentioned that the sand/cement cushion came next but not how long to wait before pouring the terrazzo topping. Thanks for the seven days information.
 