Discussion Starter · #1 ·
On my current project, we just had the hardwood floors refinished – Three coats of “commercial, oil based, satin, polyurethane”. The final coat went on yesterday about noon.

When is it safe to:

• Walk on it?
• Put the furniture and area rugs back on it?
• Put Ram Board down so I can finish the kitchen? Can I tape it down?

Over the years I’ve gotten way too many different answers to these questions and I’m hoping to get definitive answers to these questions.
 

· Registered
Design/Build Remodeling
Joined
·
6,878 Posts
Discussion Starter · #5 ·
Oil modified urethane takes 30 days to fully cure. I wouldn't put rugs down less than a week after. The best "definitive" answer is to not use oil modified finish in any situation where time is a concern. Water is better in every way, and now it's pretty easy to get the look of oil if you know what you're doing. Water is fully cured in 7 days and pretty close to done in 36 hours.
Now you tell me :censored:
 