Keeping in mind the OP seems to be a new guy and is looking for help ---

From a commercial side of things, I typically tried to make the structural guy handle the crane. It doesn't matter if it's a steel frame or cast-in-place. He's on the critical path, so he gets priority on the use of the crane. In most cases, they will do lifts for other subs when the crane isn't busy. I try to put something to that affect in their contract. Maybe I get 2 hours a week as long as it's scheduled. And you get an hourly rate (including overtime) if you need more. Part of this is having some kind of relationship with various subs and suppliers.
 