I am wondering what I can do to speed up my process. I just did a basement room roughly 600 sq ft, includes enclosed ductwork. it was already rocked, i just had to mud, prime and texture it. they wanted smooth walls. It took me 5 days. day one, did all the joints nails and half the corners. day 2, did rest of the corners and started second coating. day 3, final coat, day four sand and prime, day five, texture (hand applied plastic bag approach for the texture, not sure what the proper name for it is.) I use 90 minute mud for first coat on seams and 45 minute mud on corners for first and second. plus three for final coat. and only sand once. all is applied by hand, no machines. the corners, i use straitflex. and I use an airless sprayer for the primer. I had to wait 3 days for the mud to dry in the corners before I could prime because it just wasn't drying, although we did have humid weather, and the house was only 3 months old. so actually, it was 8 days because of that. I even used fans! well, you can let me know how slow i am as long as you also tell me how to speed up the process! I know the inside corners are killing me on time just because it takes longer to put the mud in there. i use a corner trowel for that. any thoughts would be great.