Need Help on New/Old/Sloped Pour
I have another crazy/unique pour. I'm GC'ing my house (2nd house) and need to connect my garage pad to my old driveway (it's over 600' of concrete, so starting over is not an option). The garage pad will connect to a new pour which terminates at a curved 3' wide cut on one corner, a curb on another corner and another 3' wide cut going down the hill. The old driveway is about 3' below the entrance to the garage, but concrete was removed from the garage going about 4' away from the garage. That's where the old concrete starts and continues.
The dirt you see piled up in the middle is on top of the old drive. My question is, what do you concrete pros recommend, short of removing all the old concrete (not affordable/option) in terms of rebar, substrate, control joints, mix, gravel, etc to give us the best chance at crack and settling mitigation, etc?