I've been doing concrete for a few years now, I'm confident with every stage of finishing (excluding certain decorative finishes) and I'm starting my own company doing flatwork. I've got one moderately skilled guy on board and I'm pretty fast. I'm thinking with just the two of us I generally won't be wanting to take on anything too big, maybe 1500 sq. ft. basement for example with good conditions and not a lot of obstacles. I understand that what we can do varies a lot on the situation but I just wanted to know some examples of what you guys would comfortable doing with one other guy?
CarsonMoffat is offline  

Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

   

Advertisement

 

Old 03-26-2014, 05:03 PM   #2
Fine Handcrafted Opinions
 
Bearded Wonder's Avatar
 
Trade: General
Join Date: Jan 2011
Location: Fort Worth Tx
Posts: 950
Rewards Points: 2,356

Re: Capabilities Of A 2 Man Crew?


Two guys is pretty small for concrete work if you're doing more than sidewalks or suchlike. If you're keeping it small, it'd be fine.

I've done a couple small additions and sidewalks with me and one helper. Had to give a $500 credit on one midsize (350 sq ft plus two steps down to a 10x20 porch) pour because it got away from us a little on the finish. It worked, but wasn't ideal. I don't do that anymore.

Can you make friends with some finishers to help you on bigger jobs? Then when you get it all formed and ready to pour, hire a few guys for the day, or even just a half day. I've hired some finishers who really know what's up, and it makes all the difference. If you can manage a few guys instead of working your ass off trying to stay ahead of the pour, you can catch a lot of the details that would probably slip thru the cracks if it was just you and a helper.

There's my 2 cents.

Advertisement

Bearded Wonder is offline  
The Following User Says Thank You to Bearded Wonder For This Useful Post:
CarsonMoffat (03-26-2014)
Old 03-26-2014, 05:48 PM   #3
Pro
 
stombaugh85's Avatar
 
Trade: Roofing
Join Date: Jul 2012
Location: USA
Posts: 318
Rewards Points: 284

Re: Capabilities Of A 2 Man Crew?


I almost lost a 10x12 patio once with 2 guys. I bull floated and let it set up for about 15 min. It was a 4" slump. The sun just broke through the clouds and breeze picked up a bit blowing leaves onto pad. By the time I got the leaves off the crete was setting fast.
The crete was probably left over from another job is my guess by the time it set up. It only took 1 hour from the time it was poured to become unworkable.
Tips I would suggest..... Order first in the morning ... Keep a retardant on hand just in case, it might buy you an extra 30 min if push comes to shove...

If you pour wet you'll have alot more time but I prefer 4" slump

Also did a 20x40 driveway with 2 guys. That is about my limit . It also was a 4" slump broom finish. 85 degree day and sunny. Fibermesh.

Last edited by stombaugh85; 03-26-2014 at 05:55 PM.
stombaugh85 is offline  
The Following User Says Thank You to stombaugh85 For This Useful Post:
CarsonMoffat (03-26-2014)
Sponsored Links
Advertisement
 
Old 03-26-2014, 09:46 PM   #4
Registered User
 
CarsonMoffat's Avatar
 
Trade: Concrete
Join Date: Mar 2014
Location: Fort St. John BC
Posts: 7
Rewards Points: 14

Re: Capabilities Of A 2 Man Crew?


Thanks a lot for your guys' input, I'll be pouring it a little wetter, I'm thinking at least a 5 slump. Where I live it's hard to find finishers, I'll probably just hire another guy who knows nothing to rake and clean tools.
CarsonMoffat is offline  
Old 03-29-2014, 09:56 AM   #5
Pro
 
Elyrain's Avatar
 
Trade: GC
Join Date: Dec 2007
Location: Oceanside, Ca
Posts: 404
Rewards Points: 442

Re: Capabilities Of A 2 Man Crew?


I always have an extra guy on hand for any concrete work, be it flatwork or walls. The chit is just to damn expensive to fix once it's set up. Having non skilled labour around is a good start, train him correctly and you can start bidding much larger work.
__________________
Ca A&B
Elyrain is offline  
Old 03-29-2014, 08:50 PM   #6
Pro
 
HUI's Avatar
 
Trade: Utility, sitework, and erosion control contractor
Join Date: Jan 2011
Location: Plymouth, IN
Posts: 219
Rewards Points: 178

Re: Capabilities Of A 2 Man Crew?


I was once in your position. I purchased a vibra strike. And I can lay a lot more mud down because it does a lot of the work and also works the cream up. Makes it much easier to finish. The way I look at it is the machine will show up everyday and in the longer term is cheaper than additional help
HUI is offline  
Old 03-31-2014, 12:06 AM   #7
Registered User
 
CarsonMoffat's Avatar
 
Trade: Concrete
Join Date: Mar 2014
Location: Fort St. John BC
Posts: 7
Rewards Points: 14

Re: Capabilities Of A 2 Man Crew?


I have used a vibrating screed a few times but I never really gave them a chance. I've always been kind of skeptical of problems with wetter concrete and/or slopes.
CarsonMoffat is offline  
Old 03-31-2014, 05:52 AM   #8
Pro
 
HUI's Avatar
 
Trade: Utility, sitework, and erosion control contractor
Join Date: Jan 2011
Location: Plymouth, IN
Posts: 219
Rewards Points: 178

Re: Capabilities Of A 2 Man Crew?


I've use one to pour a loading dock ramp. Pour the mud very dry like a 2"-3" slump then the vibrations will work up the cream and it makes it much easier on the bull float man

There was also a time that we laid mud down and we used the vibra strike and then it poured down rain. The rain washed all the cream off but the rocks were down so once the rain quite we were able to work the concrete enough to save the pour. If we didn't have the rocks vibrated down I'm pretty sure we would have lost it
HUI is offline  
Old 03-31-2014, 07:14 PM   #9
Registered User
 
CarsonMoffat's Avatar
 
Trade: Concrete
Join Date: Mar 2014
Location: Fort St. John BC
Posts: 7
Rewards Points: 14

Re: Capabilities Of A 2 Man Crew?


Quote:
Originally Posted by HUI View Post
I've use one to pour a loading dock ramp. Pour the mud very dry like a 2"-3" slump then the vibrations will work up the cream and it makes it much easier on the bull float man

There was also a time that we laid mud down and we used the vibra strike and then it poured down rain. The rain washed all the cream off but the rocks were down so once the rain quite we were able to work the concrete enough to save the pour. If we didn't have the rocks vibrated down I'm pretty sure we would have lost it
Ya I have no desire to rake around a 2-3 inch slump
CarsonMoffat is offline  
Old 04-07-2014, 07:01 PM   #10
Pro
 
jomama's Avatar
 
Trade: Concrete & masonry
Join Date: Oct 2008
Location: Wisconsin
Posts: 897
Rewards Points: 166

Re: Capabilities Of A 2 Man Crew?


Quote:
Originally Posted by CarsonMoffat View Post
I've been doing concrete for a few years now, I'm confident with every stage of finishing (excluding certain decorative finishes) and I'm starting my own company doing flatwork. I've got one moderately skilled guy on board and I'm pretty fast. I'm thinking with just the two of us I generally won't be wanting to take on anything too big, maybe 1500 sq. ft. basement for example with good conditions and not a lot of obstacles. I understand that what we can do varies a lot on the situation but I just wanted to know some examples of what you guys would comfortable doing with one other guy?
Are you talking about hand finishing 1500 sq. feet of basement, or by machine. If the latter, I don't see a problem, as long as the house is already roughed in. Generally, basements are a little colder in Summer months, and certainly damp and void of much sunshine, giving you a lot more time than a slab outside in the sun & wind. If you're wheeling it all through a man door or something, it's nice to have 3-5 guys to place it though............
jomama is offline  
Old 04-08-2014, 05:39 AM   #11
Pro
 
builditguy's Avatar
 
Trade: Carpentry
Join Date: Nov 2013
Location: Missouri
Posts: 2,117
Rewards Points: 1,316

Re: Capabilities Of A 2 Man Crew?


A 3 man crew can do alot. One guy that can finish. The second guy can finish, but is in the learning stage. The third guy just needs to pull concrete and keep tools clean.
I also use a vibra strike whenever possible. We also have a 40' Morrison screed for bigger stuff.
I have definatley scaled back my pours, as I get older. I have had too many times wehre I worked myself to death trying to finish a floor.
I do pick up some extra guys for bigger pours. I know some finishers that don't mind working on Saturdays. I also know a couple guys that are retired. So they are avaliable to work 1/2 days. I was also able to find a couple guys that work 2nd shift so they can help get it laid down.
Between all of those guys, I can usually find a couple extra on any given day.
builditguy is online now  
The Following User Says Thank You to builditguy For This Useful Post:
CarsonMoffat (04-10-2014)
Old 04-11-2014, 08:17 PM   #12
Pro
 
NYCB's Avatar
 
Trade: Concrete/Masonry
Join Date: Sep 2010
Location: Central NY
Posts: 1,668
Rewards Points: 400

Re: Capabilities Of A 2 Man Crew?


2 guys can do a lot, but you are both busting ass.

This time of year and in the fall you have all day so things go smooth, in July when it's 100 out everyone has to be in a constant state of motion.

I have done a lot of work with just two guys, but I would rather have 3.

Having just a laborer on hand to keep stuff clean while you keep working is a huge difference.
NYCB is offline  
Old 04-11-2014, 10:45 PM   #13
Pro
 
Stoneyard's Avatar
 
Trade: Journeyman Carpenter
Join Date: Mar 2014
Location: Mn.
Posts: 106
Rewards Points: 249

Re: Capabilities Of A 2 Man Crew?


Totally agree with 3 guys. That third guy can really pick up the loose end stuff. Maybe hire a hard working kid for the summer to get you over the hump...
Stoneyard is offline  
Old 04-12-2014, 07:18 AM   #14
Pro
 
HUI's Avatar
 
Trade: Utility, sitework, and erosion control contractor
Join Date: Jan 2011
Location: Plymouth, IN
Posts: 219
Rewards Points: 178

Re: Capabilities Of A 2 Man Crew?


Good luck finding a hard working kid

Advertisement

HUI is offline  
The Following User Says Thank You to HUI For This Useful Post:
peteo (04-13-2014)


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Need a quality rehab sub crew mullinsandsons Help Wanted or Looking For Work 5 05-07-2013 09:51 AM
Looking For Commercial Painting Crew for work in Highlands, NC rdr8887 Help Wanted or Looking For Work 2 03-23-2013 01:12 PM
Starting a siding crew nlgutters General Discussion 81 03-20-2013 10:15 PM
How many decks can a crew finish. klyde Decks & Fencing 40 11-03-2012 04:15 PM
Tree Removal Contract for Hurricane Irene Crew Needed. The_Game Help Wanted or Looking For Work 1 08-25-2011 07:46 AM

Join Now... It's Fast and FREE!

I am a professional contractor
I am a DIY Homeowner
Drywall Talk is for
PROFESSIONAL CONTRACTORS ONLY!

At DrywallTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?