Bid on 3 sewer line projects today. Missed a $27,000 job by $180. Missed a $18,000 job by $200 and got a $12,000 job by $90.
stcunlimited is offline  

Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

   

Advertisement

 

Old 04-25-2013, 10:51 AM   #2
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 6,507
Rewards Points: 66

Re: Tight Bidding Today


15 yrs ago, lost a $440k storm sewer job by $320.00

Advertisement

dayexco is online now  
Old 04-25-2013, 11:01 AM   #3
Registered User
 
stcunlimited's Avatar
 
Trade: excavation
Join Date: Aug 2012
Location: kansas
Posts: 18
Rewards Points: 10

Re: Tight Bidding Today


Quote:
Originally Posted by dayexco View Post
15 yrs ago, lost a $440k storm sewer job by $320.00
That would make you bang your head against the wall.
stcunlimited is offline  
Sponsored Links
Advertisement
 
Old 04-25-2013, 11:02 AM   #4
Registered User
 
stcunlimited's Avatar
 
Trade: excavation
Join Date: Aug 2012
Location: kansas
Posts: 18
Rewards Points: 10

Re: Tight Bidding Today


The letting before mine was a 1.5 million dollar street project and was won by $4500.
stcunlimited is offline  
Old 04-25-2013, 11:13 AM   #5
Pro
 
MarkJames's Avatar
 
Trade: Handyman Services
Join Date: Nov 2012
Location: Arlington, VA
Posts: 9,425
Rewards Points: 15,911

Re: Tight Bidding Today


I don't know anything about that, but I'll tell you a story from about 20 years ago. I was walking in front of one of the Smithsonian buildings in downtown DC late one summer day. A gritty guy was lazing on a park bench and asked me for some local guidance, etc., like places to eat. He turned out to be an excavator from upstate PA who was living out of a jobsite trailer a couple blocks down the street. He claimed it was his first time in a major city like DC, but he took a shot on a sewer contract and won it. They were doing work under I- 395 a couple blocks away. He was the proud, talkative type and said it was a 70k job that he expected to take 3 months. Said he planned to own a Nascar team one day, too. I should have kept his name to see what happened.

(Maybe it was b.s, but seemed authentic enough.)
MarkJames is offline  
Old 04-25-2013, 11:16 AM   #6
The Sheriff

 
Jaws's Avatar
 
Trade: GC
Join Date: Dec 2010
Location: Texas
Posts: 23,843
Rewards Points: 12,150

Re: Tight Bidding Today


Thats either very similar thinking people or contractors who pay attention to what the competition is doing.
__________________
"The sound of the saftey clicking off is the only warning your gonna get......., so cover your ears" Northeast Wyoming 2016

John
Jaws is online now  
Old 04-25-2013, 11:51 AM   #7
Pro
 
TLHWindows's Avatar
 
Trade: Windows Doors Siding Hurricane Shutters
Join Date: Jan 2012
Location: Tallahassee, FL
Posts: 477
Rewards Points: 734

Re: Tight Bidding Today


I lost a 20k dollar window job because my competition gave them their obscure windows for free. That cost was $75.
__________________
Cool, lets put some fabric over a window and let a hurricane throw some stuff at it. I'm sure it will protect you and your windows.

http://www.gulfbreezewindows.com
TLHWindows is offline  
Old 04-27-2013, 05:38 AM   #8
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,589
Rewards Points: 2,388

Re: Tight Bidding Today


2 years ago a buddy of mine lost a $80,000 paving contract by ...... $0.12

Talk about a kick in the nuts.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is offline  
Old 04-27-2013, 07:28 AM   #9
Pro
 
slowsol's Avatar
 
Trade: Estimator / Preconstruction Manager
Join Date: Aug 2005
Location: Toledo, OH
Posts: 2,572
Rewards Points: 2,248

Re: Tight Bidding Today


I'd rather lose jobs by $100 all day, than win a job by $20,000.
__________________
-John
slowsol is offline  
The Following User Says Thank You to slowsol For This Useful Post:
donerightwyo (04-27-2013)
Old 04-27-2013, 07:37 AM   #10
Pro
 
QCCI's Avatar
 
Trade: General Contractors/Specialty Contractors
Join Date: Jan 2013
Location: East Central Missouri
Posts: 649
Rewards Points: 952

Re: Tight Bidding Today


Bidding is extremely competitive right now, especially public projects. Everything seems to be won or lost by just a few percent. But the good thing is bidding has picked up tremendously.
QCCI is offline  
Old 04-27-2013, 08:10 AM   #11
Pro
 
backhoe1's Avatar
 
Trade: excavating contractor
Join Date: Mar 2007
Location: South Dakota
Posts: 219
Rewards Points: 182

Re: Tight Bidding Today


Last summer I won a lime removal job by $0.02/yd. About as close as you can get and still get the job!
backhoe1 is offline  
Old 04-27-2013, 08:15 AM   #12
Pro
 
BCConstruction's Avatar
 
Trade: Construction
Join Date: Jun 2009
Location: Roanoke, VA
Posts: 16,392
Rewards Points: 2,394

Re: Tight Bidding Today


So i assume there's a "going rate" in this line of work? When ever i see quotes from other contractors in this area bidding the same work as me they can be up +/- 150% difference. Crazy you guys can all be bidding so close to each other like that.
__________________
www.bcconstructionllc.com
BCConstruction is offline  
Old 04-27-2013, 09:45 AM   #13
Pro
 
slowsol's Avatar
 
Trade: Estimator / Preconstruction Manager
Join Date: Aug 2005
Location: Toledo, OH
Posts: 2,572
Rewards Points: 2,248

Re: Tight Bidding Today


Quote:
Originally Posted by BCConstruction View Post
So i assume there's a "going rate" in this line of work? When ever i see quotes from other contractors in this area bidding the same work as me they can be up +/- 150% difference. Crazy you guys can all be bidding so close to each other like that.
Whether people here want to admit it or not, there is a "going rate" for every trade. At least for those people that competitely bid projects. I always hear the talk about, "there is no going rate, just charge what you need to make money", and I agree with the fact that every contractor is different in the OH and speed. However when I bid out a building with subs and my finish carpentry numbers are $55,000, $57,000, and $65,000, you see there is a going rate.
__________________
-John
slowsol is offline  
Old 04-27-2013, 10:23 AM   #14
Contractor of the Month
 
Inner10's Avatar
 
Trade: Control Systems
Join Date: Mar 2009
Location: Ottawa, ON
Posts: 25,800
Rewards Points: 4,482

Re: Tight Bidding Today


Are these city jobs for the lowest bidder?
__________________
The Following User Says Thank You to Inner10 For This Useful Post: Leo G
Inner10 is offline  
Old 04-27-2013, 10:53 AM   #15
Registered User
 
stcunlimited's Avatar
 
Trade: excavation
Join Date: Aug 2012
Location: kansas
Posts: 18
Rewards Points: 10

Re: Tight Bidding Today


Quote:
Originally Posted by Inner10 View Post
Are these city jobs for the lowest bidder?
Yes
stcunlimited is offline  
Old 04-27-2013, 11:57 AM   #16
Pro
 
JDavis21835's Avatar
 
Trade: Excavation
Join Date: Feb 2009
Location: Saginaw Michigan
Posts: 408
Rewards Points: 386

Re: Tight Bidding Today


Quote:
Originally Posted by BCConstruction View Post
So i assume there's a "going rate" in this line of work? When ever i see quotes from other contractors in this area bidding the same work as me they can be up +/- 150% difference. Crazy you guys can all be bidding so close to each other like that.
Pretty hard to not have a going rate when everyone has specs that require a bid based on specific material. 6 contractors bidding a job that requires 12 inch C900 pvc water main are going have damn near the same material cost for the pipe. The granular material supplier, be it a sand pit, or gravel pit closest to the job is going to have those same 6 contractors calling for a price per ton of material. If the job is a Prevailing Wage job, everyone has the same labor costs.

The only way you can be more competitive is to have your own material pit, or a cheap alternative pit that the other guys dont. You can have a crew that is more productive than the competition. Also, an alternative source for pipe will help your numbers.

In the civil business, having a material source or supplier the other guys dont, is the only way you will see much of a different price. I have done this with certain items such as valves and pump equipment for lift station/water treatment plant projects. A lot of guys in this area dont know, or havent considered checking suppliers in the oilfield world. Shipping is going to be more, but if you find a good priced source, and have time to plan the shipping, it can be a big winner.

Advertisement

JDavis21835 is offline  
The Following User Says Thank You to JDavis21835 For This Useful Post:
Upchuck (04-29-2013)


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Im bidding for a commercial painting job. any advice? BaranG Painting & Finish Work 13 02-25-2014 01:54 AM
New spreadsheet for cabinetry/woodwork bidding Jason Abbott Finish Carpentry 2 12-18-2012 09:07 PM
Sono tube bidding questions! BattleRidge General Discussion 12 11-13-2011 11:38 PM
Bidding Work CConcreteEx Concrete & Paving 6 02-16-2011 11:59 AM
Cost Based Bidding Vs Spreadsheet sitegrader Excavation & Site Work 1 02-04-2009 10:44 PM

Join Now... It's Fast and FREE!

I am a professional contractor
I am a DIY Homeowner
Drywall Talk is for
PROFESSIONAL CONTRACTORS ONLY!

At DrywallTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?