I know wood. Framing......easy peasy.

Earthworks.........not so much.

A good friend of mine has dug some 24" deep trenches for utility expansion and once inspected, he filled them in. He then used a compacting machine (like a gas-powered pogo stick - I don't know the industry term)

Well, the soil is a mix of clay, rocks sand and top soil. it was wet when it went back in the trench.

Fat forward a week, and he called me today to ask if I knew why the ground he tamped down in the trench area was springy? He says it gives about 1".

I'm thinking that the wet earth is trapped under the dried out top layer, but what do I know.

He's willing to rent the mini ex again and dig it up and add lime or replace it with different medium. Any thoughts/suggestions?
wallmaxx is offline  

Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

   

Advertisement

 

Old 09-12-2015, 01:55 PM   #2
Want to play a game?
 
CrpntrFrk's Avatar
 
Trade: I do that too!
Join Date: Oct 2008
Location: Globe, Arizona
Posts: 4,522
Rewards Points: 4,196

Re: Spongey / Springy Earth After Filling In Trench


Yes, too wet. The soil should be damp enough to clump together. If it is too wet, it will pump. You'll have to dig it up and try again.

When you dig it up, mix all the soil together and see where you are at with moisture content. You should be able to pick up some soil in your hand and make a clump by squeezing. If you have slimy mud on your hand it is too wet.

When filling back in you should be able to do 12" lifts of soil then compact with a jumping jack. You should be able to stand on a spade shovel after compaction and the shovel only go in about an inch or so if compacted correctly.

Advertisement

__________________
My tools are always yelling at me cause the wife and kids take up too much room.

Last edited by CrpntrFrk; 09-12-2015 at 01:59 PM.
CrpntrFrk is offline  
The Following User Says Thank You to CrpntrFrk For This Useful Post:
wallmaxx (09-12-2015)
Old 09-12-2015, 06:43 PM   #3
Box Builder
 
Morning Wood's Avatar
 
Trade: Pretty much anything with wood and some metals
Join Date: Jan 2008
Location: Rockport, MA
Posts: 6,056
Rewards Points: 9,730

Re: Spongey / Springy Earth After Filling In Trench


I'd use a plate compactor instead
Morning Wood is offline  
Sponsored Links
Advertisement
 
Old 09-12-2015, 06:55 PM   #4
Pro
 
jhark123's Avatar
 
Trade: Pro Cat Herder
Join Date: Aug 2008
Location: Enumclaw, WA
Posts: 2,508
Rewards Points: 1,710

Re: Spongey / Springy Earth After Filling In Trench


If there is paving going in over this trench he should replace the fill with 5/8minus
jhark123 is offline  
Old 09-12-2015, 08:34 PM   #5
Fire up the BBQ
 
griz's Avatar
 
Trade: GC
Join Date: Nov 2009
Location: CA
Posts: 21,881
Rewards Points: 2,630

Re: Spongey / Springy Earth After Filling In Trench


We don't usually put native soils back in the ditch.

3/4- in lifts or CDF.
__________________
SOME JOBS JUST AREN'T WORTH DOING:
griz is online now  
The Following 2 Users Say Thank You to griz For This Useful Post:
JDavis21835 (11-26-2015), wallmaxx (09-13-2015)
Old 09-12-2015, 09:54 PM   #6
Pro
 
slowsol's Avatar
 
Trade: Estimator / Preconstruction Manager
Join Date: Aug 2005
Location: Toledo, OH
Posts: 2,572
Rewards Points: 2,248

Re: Spongey / Springy Earth After Filling In Trench


Agreed, it was too wet. Depending on the size of the trenches, I'd fill with premium fill. We would use 57's in this area. Essentially small, self compacting stone.
__________________
-John
slowsol is offline  
Old 09-13-2015, 11:54 AM   #7
CAD Services
 
wallmaxx's Avatar
 
Trade: So done with this place...
Join Date: Jun 2007
Posts: 3,678
Rewards Points: 144

Re: Spongey / Springy Earth After Filling In Trench


Thanks for the education.
Y'all are great.
I'll pass this along.
wallmaxx is offline  
Old 09-13-2015, 07:12 PM   #8
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 6,429
Rewards Points: 342

Re: Spongey / Springy Earth After Filling In Trench


Quote:
Originally Posted by griz View Post
We don't usually put native soils back in the ditch.

3/4- in lifts or CDF.
dissimilar soils in an area that has extreme freeze/thaw areas...like here, that does NOT work. your granular/stone backfill, stays put, native soils around it....freeze/expand...leaving a divot every freeze period until the surrounding soils thaw and contract in the spring.

best thing is go by the soils report. adhere to the optimum moisture content in the soil. if what's excavated is too wet? haul it away and go find some very similar soils that are at optimum, or a touch below moisture wise...and compact it in.
dayexco is online now  
The Following User Says Thank You to dayexco For This Useful Post:
JDavis21835 (11-26-2015)
Old 09-13-2015, 07:22 PM   #9
Pro
 
mattg2448's Avatar
 
Trade: Excavating
Join Date: Jan 2015
Location: Port Huron MI
Posts: 174
Rewards Points: 390

Re: Spongey / Springy Earth After Filling In Trench


Sand is our normal back fill material.. depending where it comes from it packs very nicely
mattg2448 is offline  
Old 09-14-2015, 04:06 PM   #10
Pro
 
rustyjames's Avatar
 
Trade: Constructioneer; LEED AP BD+C
Join Date: Aug 2008
Location: Central NJ
Posts: 1,291
Rewards Points: 1,696

Re: Spongey / Springy Earth After Filling In Trench


Here we typically use what came out of the excavation (without the topsoil) for backfilling. It's compacted in lifts, and lift depth depends on the type of compaction equipment being used. It can be quite expensive, and unnecessary filling an excavation with stone.
rustyjames is online now  
Old 11-22-2015, 09:03 PM   #11
Registered User
 
Powerjoke's Avatar
 
Trade: Excavation
Join Date: Nov 2015
Location: Kansas City
Posts: 2
Rewards Points: 4

Re: Spongey / Springy Earth After Filling In Trench


I know it's a bit of an old thread but here it goes anyways, I hate for my first post to sound like I'm arguing with everyone but the mist of it is vibration is your enemy with wet material.

If there's utilities in the trench they'll call for granular or flowable fill most of the times, if there is nothing in the trench and it's still spongy dig it out throw some gabion in it let it jaw together and most importantly if you have wet soil DO NOT VIBRATE it'll just make it worse and worse with every pass,

I've had spots like your talking about start a trench wide and before it's over have to dig it out with loader and waste several loads of 4-6" all because of trying to work wet ground and vibrating.

Pj
Powerjoke is offline  
Old 11-24-2015, 04:44 AM   #12
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,589
Rewards Points: 2,388

Re: Spongey / Springy Earth After Filling In Trench


Where is this at ? On his own property in his yard or on a customers property. If it his own in the yard that will not see any heavy traffic, then just leave it be. It eventually will dry out.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is offline  
The Following User Says Thank You to rino1494 For This Useful Post:
rustyjames (11-27-2015)
Old 11-24-2015, 07:38 AM   #13
Pro
 
Railman's Avatar
 
Trade: Railing
Join Date: Jan 2008
Location: Cincinnati
Posts: 2,371
Rewards Points: 591

Re: Spongey / Springy Earth After Filling In Trench


It's spongy because air got pumped into the wet dirt, creating a gazzillion litle air pockets in the wet dirt. Eventually, rain pounding will usually work the air out. If not, I'd try a soaker hose.
Railman is offline  
The Following User Says Thank You to Railman For This Useful Post:
Fouthgeneration (11-29-2015)
Old 11-26-2015, 01:54 PM   #14
Registered User
 
Hierr's Avatar
 
Trade: Electrical, General Engineering, General Building
Join Date: Nov 2015
Posts: 1
Rewards Points: 2

Re: Spongey / Springy Earth After Filling In Trench


Am I the only one that saw that he backfilled it with one 24" lift of wet material and then hit it with a Wacker and said all good.

Better check the Geotech report and import some engineered fill. Anybody seen my 320 with the Sheepsfoot roller.

/Sarcasm off. Sorry gonna have to dig it back up. Be careful if it's direct buried. Be careful if its in pipe/conduit. Now spread out the material and let it dry out some, then backfill it in about 6" layers (Lifts) max, compact with the wacker, another lift, compact, etc. You need to have some moisture to get compaction, but without getting a tester to come take some samples and cook em to figure out optimum you can get it better than it is now. Now I wouldn't build a structure over it without getting the compaction tested.
Hierr is offline  
Old 11-26-2015, 06:30 PM   #15
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 6,429
Rewards Points: 342

Re: Spongey / Springy Earth After Filling In Trench


Right soils, 95℅ standard density is easily attainable with ex mounted sheepsfoot or vibe plate.

Sent from my CMP749 using Tapatalk
dayexco is online now  
Old 11-28-2015, 08:29 PM   #16
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 6,429
Rewards Points: 342

Re: Spongey / Springy Earth After Filling In Trench


I should have added to post "24 inch" lifts

Sent from my CMP749 using Tapatalk
dayexco is online now  
Old 12-10-2015, 10:44 AM   #17
Registered User
 
AndyStandy's Avatar
 
Trade: Excavation & Site Work
Join Date: Dec 2015
Location: Detroit, Mi
Posts: 1
Rewards Points: 2

Re: Spongey / Springy Earth After Filling In Trench


Also worth noting - if you are backfilling with native material, don't let any organic material get mixed into your pile you are excavating - put it to the side, otherwise if it ends up back in your trench you will have issues from the start - if the material coming out is wet, spread it out and let it dry out. If you are paving over it, import an engineered fill.

Advertisement

AndyStandy is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Filling Holes in PT ? We Fix Houses Decks & Fencing 29 02-24-2013 01:59 PM
Compressed Earth Block Construction Jaws Construction 12 02-07-2013 03:33 PM
UFO found on Google Earth Leo G Off Topic (Non Trade) 19 09-19-2010 08:49 PM
Trench Drains sbcontracting Concrete & Paving 7 06-21-2010 09:21 PM
Trench permitting Upchuck Excavation & Site Work 2 04-22-2009 08:20 PM

Join Now... It's Fast and FREE!

I am a professional contractor
I am a DIY Homeowner
Drywall Talk is for
PROFESSIONAL CONTRACTORS ONLY!

At DrywallTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?