Markup On Customer Purchased Materials


I am good at explaining to my clients why I markup on materials and how much time is involved in answering questions, visiting suppliers, verifying fitment, communicating with subs etc. But this has always been a sticky area for me and I'm sure other contractors. I've never had it come to a major problem but I wanted to see how others deal with it.
I'm very clear to my clients about my markup on materials and subs. So that's no problem. The way I work it is whatever the HO finds that they like, I will do the ordering. That is true whether it's being bought from a store where I hold an account or anywhere else. The whole time I'm very involved in helping choose the right materials and/or fixtures and answering questions via email, text of phone.
The problem is when the HO buys their own things for the job. Most of the time I just let it slide as it's only one or two small items (tile, lights or a fixture). But what do you do when the HO wants to buy everything themselves? Do you ask them for all their receipts so you can figure the proper markup? That would seem awkward. Do you make them buy through you? What about the big ticket items such as appliances, cabinets or windows?
Again I have not had any major issues with this but I am trying to get a good plan in place in the event this comes up on a future job.
BoulderBuilder is offline  

Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

   

Advertisement

 

Old 11-09-2012, 07:36 PM  
Member
 
Jonno's Avatar
 
Trade: Carpentry
Join Date: Jan 2012
Posts: 31
Rewards Points: 27

Re: Markup On Customer Purchased Materials


Just add extra to the labour cost. It seems pretty silly trying to markup materials you didn't buy.

Advertisement

Jonno is offline  
The Following 2 Users Say Thank You to Jonno For This Useful Post:
pinwheel (11-13-2012), ryanshull (11-09-2012)
Old 11-09-2012, 08:09 PM  
Pro
 
Keeyter's Avatar
 
Trade: Home Remodels
Join Date: Sep 2010
Location: Southern Wisconsin
Posts: 435
Rewards Points: 851

Re: Markup On Customer Purchased Materials


My contract states that Markup covers the expenses, warranties, skill, experience, time, and smooth and speedy flow of the project.

I give customers 2 options when they wish to provide their own materials.

Option 1: Your responsible for warranty including installation above or below any material that is defective and any loss of production of work due to materials shortages, defects, etc that will incur my crew going home and their rate being paid for the remainder of the day.

Option 2: You spec out the type, color, product, brand, make (you get the point) of material you want in you project. I take care of picking it up, making sure its in serviceable condition, coordinating a smooth speedy schedule, and by the way I'll warranty it for 5 years if anything goes wrong.

Its my belief people hire us not because they are rich slobs with hundreds falling out of their pockets but because we can run a job like a fine ballet coordinating all the facets that the DIY Channels make look like don't exist. If a homeowner wanted the hassle of a project dealing with suppliers, subs, and vendors when things go wrong then they would do it themselves. They pay us our markup so all they have to do is sign their name and sit back watching whatever reality TV show trips their trigger.

There is a cost that goes with Warranty and Coordination in a project, you can have peace of mind by paying for it or deal with it yourself. I don't markup materials provided by homeowners, but anything goes wrong with say a tub and tile needs to be replaced its not on my dime. Warranties sell Markup
Keeyter is offline  
The Following User Says Thank You to Keeyter For This Useful Post:
ryanshull (11-09-2012)
Sponsored Links
Advertisement
 
Old 11-09-2012, 08:43 PM  
Kitchen Customizer
 
ryanshull's Avatar
 
Trade: Interior Remodeling
Join Date: Nov 2012
Location: Central Kansas
Posts: 422
Rewards Points: 310

Re: Markup On Customer Purchased Materials


Explain to them that when they order, you spend more time running around getting the things they missed, fixing the wrong materials, correcting mistakes, blah blah blah, fill in the blank.

The job just goes smoother when one person (the contractor) is held accountable for all those things working in sync.

On my current reno, owner ordered all her own cabinets, and appliances. Guess who gets to modify the cabinets.... I will not take on the headaches, since she ordered it, she can reorder and replace....... and replace....... and replace. Its been fun.
ryanshull is offline  
Old 11-11-2012, 12:15 PM  
Pro
 
AJAX's Avatar
 
Trade: General Contractor
Join Date: Sep 2009
Location: Central, MN
Posts: 238
Rewards Points: 150

Re: Markup On Customer Purchased Materials


Quote:
Originally Posted by ryanshull View Post
Explain to them that when they order, you spend more time running around getting the things they missed, fixing the wrong materials, correcting mistakes, blah blah blah, fill in the blank.

The job just goes smoother when one person (the contractor) is held accountable for all those things working in sync.

On my current reno, owner ordered all her own cabinets, and appliances. Guess who gets to modify the cabinets.... I will not take on the headaches, since she ordered it, she can reorder and replace....... and replace....... and replace. Its been fun.

I agree with this and what others have said. I personally tailor my contract to what the client wants/needs. As far as HO getting all the materials. That's fine, I warranty my labor (it's the law) and nothing else. If it's the wrong material or is short, in my contract I have a clause that specifically states that if I have to run for material it's $125/hr per man hour + $.80/mile.
__________________
Governments are instituted among men, deriving there just powers from the consent of the governed...

Declaration of Independence
AJAX is offline  
The Following User Says Thank You to AJAX For This Useful Post:
DavidC (11-12-2012)
Old 11-13-2012, 05:51 PM  
Member
 
claraclownie's Avatar
 
Trade: General Contractor
Join Date: Jun 2011
Location: St. Louis Missouri
Posts: 33
Rewards Points: 27

Re: Markup On Customer Purchased Materials


We give them allowances in the scope of work that states "All allowances are calculated at total MSRP plus tax and delivery. All materials purchased by Contractor at Contractor's vendor." Unless previously negotiated, we do not install or warranty HO purchased items.
claraclownie is offline  
Old 11-15-2012, 12:44 AM  
Pro
 
Bonzai's Avatar
 
Trade: Home Renovations & Repairs
Join Date: Dec 2009
Location: Squamish, BC
Posts: 311
Rewards Points: 252

Re: Markup On Customer Purchased Materials


Quote:
Originally Posted by AJAX

I agree with this and what others have said. I personally tailor my contract to what the client wants/needs. As far as HO getting all the materials. That's fine, I warranty my labor (it's the law) and nothing else. If it's the wrong material or is short, in my contract I have a clause that specifically states that if I have to run for material it's $125/hr per man hour + $.80/mile.
I have a similar clause but I have had clients try to say that they will go get the missing parts while my crew wait ... And then argue about me charging for downtime while we wait even though this is mentioned in the terms and conditions. Any suggestions on how to explain this without being argumentative as can be a touchy one with some clients?
__________________
Renovations & Repairs. Bathrooms, decks, tile, paint & much more.
North Vancouver to Whistler and between.
TOLL FREE 1-877-804-3326
http://www.adventhomesolutions.com
Bonzai is offline  
Old 11-15-2012, 07:46 AM  
Kitchen Cabinets NJ
 
cabinetsnj's Avatar
 
Trade: Kitchen Cabinets
Join Date: Jun 2012
Location: New Jersey
Posts: 1,099
Rewards Points: 500

Re: Markup On Customer Purchased Materials


Quote:
Originally Posted by BoulderBuilder View Post
I am good at explaining to my clients why I markup on materials and how much time is involved in answering questions, visiting suppliers, verifying fitment, communicating with subs etc. But this has always been a sticky area for me and I'm sure other contractors. I've never had it come to a major problem but I wanted to see how others deal with it.
I'm very clear to my clients about my markup on materials and subs. So that's no problem. The way I work it is whatever the HO finds that they like, I will do the ordering. That is true whether it's being bought from a store where I hold an account or anywhere else. The whole time I'm very involved in helping choose the right materials and/or fixtures and answering questions via email, text of phone.
The problem is when the HO buys their own things for the job. Most of the time I just let it slide as it's only one or two small items (tile, lights or a fixture). But what do you do when the HO wants to buy everything themselves? Do you ask them for all their receipts so you can figure the proper markup? That would seem awkward. Do you make them buy through you? What about the big ticket items such as appliances, cabinets or windows?
Again I have not had any major issues with this but I am trying to get a good plan in place in the event this comes up on a future job.
Maybe you should just structure this cost into the labor pricing so you dont have to deal with explaining this to your client, who may or may not understand.

Advertisement

__________________
NJ Cabinet Outlet
cabinetsnj is offline  
 

Thread Tools
Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Laminate flooring issue with customer beachwork Flooring 26 03-07-2013 01:56 AM
Customer from hell HandymanGenie Business 21 10-11-2012 11:43 AM
Customer owes 20k and won't pay.... Handyman33 Business 85 06-29-2012 11:53 AM
The use of markup in priced work john elliott Business 44 04-03-2011 09:44 PM
How About Materials That Fail To Meet Local Code. . . datajam General Discussion 10 10-20-2009 10:06 PM

Join Now... It's Fast and FREE!

I am a professional contractor
I am a DIY Homeowner
Drywall Talk is for
PROFESSIONAL CONTRACTORS ONLY!

At DrywallTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?