I am begining the foundation on my new house and I am having trouble with the layout of the in slab, (Basement) rough plumbing. Mostly due to my inexperiance in the layout process. Any help would be great.
Kyle |
|
|
|
|
|
#2 |
|
Pro
Trade: Wood working in spare time.
Join Date: Jan 2005
Location: kankakee county,Illinois
Posts: 1,539
|
Re: New Construction Rough Plumbing Layout
I think the reason no one is responding is because how can they help you out with out seeing the basement first. Just a thought. In the event I was building a new house I would go with pex water lines in stead of copper. More up front cost but less time to install. Installation is cut in half. This is what Rich on This old house always goes with when installing water lines in a new this old house project. The pex is as easy to run as electrical wire I think its awesome. This is what there using on there current project alone with radiant floor heating which is also pex. :Thumbs: :Thumbs:
|
|
|
|
|
|
#3 |
|
Pro
Join Date: Dec 2003
Location: MA
Posts: 438
|
Re: New Construction Rough Plumbing Layout
Plan ahead, look at your plans and vision where everything is going to go, then add from there for future events.
Height is a main factor whenever you are doing rough plumbing in slab work, laser and string level is a must. Measurements have to be on the mark, dead on or you will have problems on the finish. As to the materails for under ground depends on your local code, check first you do not want to have to do things twice. bjd |
|
|
|
|
|
#4 |
|
Registered User
Join Date: Mar 2005
Posts: 2
|
Re: New Construction Rough Plumbing Layout
In the plumbing in the basement slab, do I need to maintain the 1/4" per foot fall in the sewage pipes, or just have some slope. My reason for asking is so I can determine at what depth I should put a cross over pipe in my frost footing on the walkout of my basement.
Thanks |
|
|
|
|
|
#5 | |
|
Commercial construction
Trade: Commercial construction
Join Date: Dec 2004
Location: Upstate New York
Posts: 603
|
Re: New Construction Rough Plumbing LayoutQuote:
You're trying to do a professional job. Do what a professional would do; call a plumber. That's the way it's done. I really hope that you follow this advice, and I wish you the best of luck with your new home. Best regards, Mike Last edited by mikesewell; 03-29-2005 at 01:33 PM. |
|
|
|
|
|
|
#6 |
|
Pro
Join Date: Dec 2003
Location: MA
Posts: 438
|
Re: New Construction Rough Plumbing Layout
Yea that was kinda blunt, and I would have to agree with Mike.
I do not do my own taxes, you know why? because I know i would screw them up. Dont be fooled into the idea that this is a simple operation, you must be dead on or its a mess. BJD |
|
|
|
|
|
#7 | |
|
Commercial construction
Trade: Commercial construction
Join Date: Dec 2004
Location: Upstate New York
Posts: 603
|
Re: New Construction Rough Plumbing LayoutQuote:
It was really blunt, but I meant kafanslr no harm. I'd hate to see this guy have to jackhammer 4 yds of concrete out because we didn't give him a much needed wake-up call. He is in over his head, and the remedy is not very expensive. I wish that someone had wacked me in the head a couple of times when I had put myself in a similar situation. I hope to see a good ending here, and I hope he gets back to us. Best regards, Last edited by mikesewell; 04-02-2005 at 03:25 PM. |
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| I want to get in Construction and am looking for advice | chompchomp12 | Business | 21 | 12-17-2009 10:39 PM |
| plumbing codes question for new construction?? | national | Plumbing | 19 | 07-12-2007 05:54 AM |
| 22 Undeniable Construction Truths | Ed the Roofer | General Discussion | 0 | 01-26-2007 06:00 PM |
| Go to Page... |