Built Up Slab Question

 
Thread Tools Search this Thread Display Modes
Old 04-10-2007, 07:58 PM   #1
New Guy
 
stampcrete's Avatar
 
Trade: concrete contractor
Join Date: Mar 2007
Location: Wallingford CT
Posts: 28

Built Up Slab Question


I need some input on a slab that will be poured even with the top of the frost wall that I poured today. Originally there was going to be a crawl space with the slab down 3'. Now the guy wants me to pour the slab up to finish floor grade so he does not have to use floor joices etc. His existing house is a slab with no basement. So I plan on pouring the slab inside the frost walls to the top of the wall after backfilling, compacting etc. My question is should I put any rebar or any pegs into the wall before pouring or should wire be sufficient. This slab will be a subfloor so I dont want any settleing down the road. Any suggestions would be helpful. Thanks Kirk

stampcrete is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 04-10-2007, 08:14 PM   #2
Pro
 
POOLMANinCT's Avatar
 
Trade: Swimming Pool Contractor
Join Date: Oct 2006
Posts: 2,165

Re: Built Up Slab Question


pics?

as rule of thumb I always use #3 sitting on piece of dampened block... never mesh
__________________
......Less with the jaw & More with the paw.....
POOLMANinCT is offline  
Old 04-10-2007, 08:51 PM   #3
New Guy
 
stampcrete's Avatar
 
Trade: concrete contractor
Join Date: Mar 2007
Location: Wallingford CT
Posts: 28

Re: Built Up Slab Question


Ill have to post some pics when I get some time. I need to put a order in for some steel for another job so Ill figure in some extra for this job. I dont do many jobs that require extra reinforcement besides outside flat work that has no structural importance or a step down frost wall where I might put a rebar or two in . Thanks- Kirk
stampcrete is offline  
Old 03-24-2008, 08:09 PM   #4
Registered User
 
mainer1's Avatar
 
Trade: Foundation walls and Flat work
Join Date: Mar 2008
Posts: 3

Re: Built Up Slab Question


If you had known a head of time the best thing to is to run a 2x4 brick ledger around the inside. I would definatly bore 1/2" pegs a lest every 2' and with laterial tieing them all together.
mainer1 is offline  
Old 03-24-2008, 08:49 PM   #5
Pro
 
genecarp's Avatar
 
Trade: LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,426

Re: Built Up Slab Question


pegs wont stop settling, its all about the tamping, if the the compaction is correct, how can slab settle?
__________________
genecarp is offline  
Old 03-24-2008, 09:43 PM   #6
Pro
 
concretemasonry's Avatar
 
Trade: Masonry consultant
Join Date: Nov 2006
Location: MSP, Minnesota
Posts: 2,453

Re: Built Up Slab Question


I would not put in pegs or dowels, but just build it right as slab over compacted base. Just make sure you compact the soil with the right amount of moisture.

If you don't have the compacted soil suporting it, you have a structural slab that must be reiniforced more to span wall to wall when the undercompacted "dirt" under it settles.
__________________
Dick

Engineer, designer and consultant recently active domestically and internationally on construction and design in about 35 countries.
concretemasonry is online now  
Old 03-26-2008, 08:33 PM   #7
Registered User
 
mainer1's Avatar
 
Trade: Foundation walls and Flat work
Join Date: Mar 2008
Posts: 3
Lightbulb

Re: Built Up Slab Question


Quote:
Originally Posted by genecarp View Post
pegs wont stop settling, its all about the tamping, if the the compaction is correct, how can slab settle?
I skipped a step, yes you always want to to make sure everything is compacted to your best ablity. But all it takes is for that soil to settle 1/8" and the floor to fallow. If the Finish floor is tile what do you think is going to happen around the perimeter where the wall meets the floor, CRACK.....
mainer1 is offline  
Old 03-27-2008, 06:18 AM   #8
Pro
 
genecarp's Avatar
 
Trade: LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,426

Re: Built Up Slab Question


Quote:
Originally Posted by mainer1 View Post


I skipped a step, yes you always want to to make sure everything is compacted to your best ablity. But all it takes is for that soil to settle 1/8" and the floor to fallow. If the Finish floor is tile what do you think is going to happen around the perimeter where the wall meets the floor, CRACK.....
properly compacted soil should not settle 1/8", if it did the entire area should not settle, but only a couple of spots, the wire in the slab, in addition to a good mix, should keep the slab suspended as one piece, additionally, some cracking along the side walls is normal, just due to different materials meeting, base moulding helps with this. i have never pinned the slab to the found wall, and have never had a problem,
__________________
genecarp is offline  
Old 03-27-2008, 03:05 PM   #9
Pro
 
DBCoop's Avatar
 
Trade: Trim Carpenter-Wood/Chain Link Fence Construction-Concrete Construction
Join Date: Feb 2008
Location: Sams Valley Oregon
Posts: 159

Re: Built Up Slab Question


Kirk,you are getting some good imput and I,ll throw in my 2 cents.On an inside the wall pour I do not dowel rebar between wall and slab.As stated before;compaction is the KEY! In my area the native soil sometimes has too high of a clay content to use as base.When that is the case I compact base rock in lifts and top off with about an inch of 3/4 minus.Moisture content is crucial,now i screed off and plate compact.I then thicken any load bearing locations to appropriate size and install appropriate bar.I,m guessing this a 4 inch pour,if so I install #3 bar on 2 foot center resting on 1 inch dobies.I then attach 1/4 inch closed cell foam to the wall with the top of the foam being slab elevation.The foam isolates the wall from the slab and and allows for movement between the two.

Last edited by DBCoop; 03-27-2008 at 03:08 PM.
DBCoop is offline  
Old 03-27-2008, 05:24 PM   #10
Pro
 
genecarp's Avatar
 
Trade: LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,426

Re: Built Up Slab Question


coop, i like the foam idea
__________________
genecarp is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Demo a foundation under a radiant heat slab without disturbing the slab...? wackman Remodeling 18 04-02-2007 12:38 AM
Stupid Question about drain holes in built up walk Jacey Concrete & Paving 6 04-01-2007 04:53 PM
Mono Slab Question? TBALL Construction 3 07-26-2006 08:11 AM
Basement slab question n74tg Masonry 5 05-26-2006 04:38 PM
Slab question - Opinion on cost 20Two Masonry 6 08-19-2005 12:39 AM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?