I would like to know how much painters would charge for painting 1000 SF, but specifically, what variables they consider when coming up with a quote....read on. There's a lot of discrepancy out there so maybe I am undercutting myself. I am new to painting, over the last 12 months. So here's the scenario: Straight wall of 1000 SF, you need to cut the top, one coat of latex is required, paint is about $35 / gallon. Wall is in good shape and only needs sanding. Travel time to customer is 30 min.
When I price a job like this I charge it based on Time and Materials. I would first (1) determine how much time it would take to paint the wall space of 1000 SF; (2) I would determine how much time is required for Surface preparation, and (3) how much time is required for Setup and Clean up and (4) the Cost of Materials needed for job. I then determine what I should add on for having my liability / disabilty insurance as well as the cost of using my equipment and tools (ladders, brusheds, rollers, drills, etc) as these items depreciate. Finally I determine the risk factor involved in the job by asking myself "am I placing myself at high risk by doing this job, by, for example, having to reach great heights on a ladder?"...I would then add on a fee for this risk. So here goes... let's assume that this is an easy job with no risk. My hourly rate is $40 (Canadian) 1) Paint time.....I would charge $40 / hour @ 3 hours = $120 2) Surface Preparaion... I would charge $40 (1 hour) which would involve sanding and vacuuming the floors for dust before painting. 3) Set up / Clean up...I would charge $40 (1 hour) which would involve moving the paint equipment into the room, covering the floors, and cleaning up after the job is done. 4) Cost of material...I would charge at total of $105, which includes 3 gallons of paint @ $35, sand paper, roller sleeve, tray liner, rags and garbage bag. 5) Travel Time....I would charge $20 for picking up paint (assuming one trip to paint store and delivering it to job site) 6) Use of Equipment and Depreciation. I would charge $20 (educated guess) for the use of my equipment (ladders, power tools, rollers, etc) 7) Liability Insurance / Disability Insurance. I would charge $15 (educated guess) for my these insurance. Total for job would be $360. What do you think??? What would you charge??? Am I undercutting my price?? Do you have a formula for insurances, say 25% of your fee??? Some people charge 50 cents a foot...that would be $500!!!! Help!!! Thanks, Zeebo |
|
|
|
|
|
#2 | |
|
Pro
Trade: Painting Contractor
Join Date: Dec 2004
Location: Toronto
Posts: 1,836
|
Re: Variables To Consider When Painting 1000 SF???Quote:
Try coming with yearly numbers of everything you mentioned and more and divide that by the man hours you sell a year (projected in your case). Then your hourly charge includes everything and this way you recover overhead and profit for every hour charged. As far as materials go, try marking them up by a percentage.
__________________
Toronto Painters Commercial Painting Commercial Painting Toronto Toronto Office Painters Painting Toronto Blog |
|
|
|
|
|
|
#3 | |
|
Repair/Remodeling Tech.
Trade: Repair and Remodeling Services
Join Date: Feb 2005
Location: Chester, IL
Posts: 736
|
Re: Variables To Consider When Painting 1000 SF???Quote:
That "downfall" comment shouldn't be taken too seriously
__________________
Jim P. |
|
|
|
|
|
|
#4 | |
|
Pro
Trade: Painter
Join Date: Jul 2005
Posts: 167
|
Re: Variables To Consider When Painting 1000 SF???Quote:
Thanks Jim. You're right...I miscalculated and forgot to add in the cost of these supplies. I would charge an additional $20 to cover the cost of these supplies. Quite often, sleeves are good for 2-4 jobs. I would use the old one (after washing it out well...yes, putting them in the washing machine does work!!) in 2-3 future jobs and charge the customer about $4 per sleeve. Thanks. |
|
|
|
|
|
|
#5 |
|
Pro
Trade: Painter
Join Date: Jul 2005
Posts: 167
|
Re: Variables To Consider When Painting 1000 SF???
Am I missing anything??? Did I miss a variable / expense that I did not factor in. Some painters would add in 5-10% towards the purchase of their next van / Truck / car.
I would be interested in hearing from other painters.....how much would you charge and what expenses do you consider for this job (or any job) Thanks Zeebo |
|
|
|
|
|
#6 |
|
Back from the dead...
Trade: Paperhanger/Painter
Join Date: Oct 2003
Location: St. Louis, MO
Posts: 6,544
|
Re: Variables To Consider When Painting 1000 SF???
I didn't see any profit added in anywhere.
|
|
|
|
|
|
#7 | |
|
Pro
Trade: Painter
Join Date: Jul 2005
Posts: 167
|
Re: Variables To Consider When Painting 1000 SF???Quote:
As a sole painter, should I be charging something above and beyond the labour time?? Please clarifiy. Thanks Zeebo |
|
|
|
|
|
|
#8 |
|
Back from the dead...
Trade: Paperhanger/Painter
Join Date: Oct 2003
Location: St. Louis, MO
Posts: 6,544
|
Re: Variables To Consider When Painting 1000 SF???
Yes, after all expenses (labor, material overhead, your salary, etc.) there should be money left over for the 'company'. This is money i utulize to pay for more marketing/advertising, new equipment, etc. I would take your total figure above, and tack on 10-15% for profit.
The extra dollars got here and there from materials and such are not enough for profit IMO. Plus, you say "the reimbursement that I received from charging for paint time, prep time, clean up set (minus materials) is the profit." All that is labor. Profit is money above and beyond all direct or indirect costs of the job. Last edited by ProWallGuy; 09-27-2005 at 08:56 AM. |
|
|
|
|
|
#9 |
|
Painting Contractor
|
Re: Variables To Consider When Painting 1000 SF???
What's the exchange rate? What is $350cd in american dollors?
__________________
Just because some of us can read and write and do a little math, that doesn't mean we deserve to conquer the Universe. Kurt Vonnegut, (1922 - 2007) from the Novel 'Hocus Pocus' The NAPP Milwaukee Painting Contractor |
|
|
|
|
|
#10 | |
|
Pro
Trade: Painter
Join Date: Jul 2005
Posts: 167
|
Re: Variables To Consider When Painting 1000 SF???Quote:
$40 Canadian converts to $34 US $35 Canadian converts to $29 US On average, what would a US painter charge per hour in your area?? Does your hourly rate factor in all expenses or is it specific to just painting time?? For example, I charge $35 - $40 / hour for painting time (which includes painting, setup, cleanup, prep). I then add on material cost and a charge for insurance and use of equipement / depreciation, and travel. I have tried to figure out an hourly rate that would encompass / factor in all of the above expenses. I have come up with about $60 - $65 Canadian (or $51 - $55 US) which includes the paint. If client provides paint, I drop my rate to $55 - $60 ($47 - $51 US). What do you think of these rates?????? Your other comments are helpful. Adding on an additional 10% - 15% for advertising, improvements, future vehicle purchase seems to make sense. Living and learning I guess!!!!!!!!!!!!!!!!!! Zeebo |
|
|
|
|
|
|
#11 | |
|
Painting Contractor
|
Re: Variables To Consider When Painting 1000 SF???Quote:
PWG is right though you need to add something in for your profit. It's always going to be different, obviously but here are some generic numbers. They are always based on dificulty. High risk 15% to 35% average risk 13% to 14% moderate risk 10% to 12% low risk 5% to 9% Those are just examples you need to figure out what's right for you, your crew, your area, and your company.
__________________
Just because some of us can read and write and do a little math, that doesn't mean we deserve to conquer the Universe. Kurt Vonnegut, (1922 - 2007) from the Novel 'Hocus Pocus' The NAPP Milwaukee Painting Contractor |
|
|
|
|
|
|
#12 | |
|
Dripless
Trade: Painting and exterior wood care
Join Date: Aug 2004
Location: N. Wis.
Posts: 169
|
Re: Variables To Consider When Painting 1000 SF???Quote:
If your man/hr. estimate is right on I think $360. is a fair price..should even account for about 10% profit. At 5.5 hrs. you've pretty much shot the whole day..but 360. is a nice round number. |
|
|
|
|
|
|
#13 | |
|
Pro
Trade: Painter
Join Date: Jul 2005
Posts: 167
|
Re: Variables To Consider When Painting 1000 SF???Quote:
Very good information. Thank you |
|
|
|
|
|
|
#14 | |
|
Pro
Trade: Painter
Join Date: Jul 2005
Posts: 167
|
Re: Variables To Consider When Painting 1000 SF???Quote:
Thanks for the information. Helpful! Do you factor in a charge for use of equipment such as brushes, ladders, power tools, rollers, vacuum cleaners, etc. These tools are used and depreciate over time and eventually require replacement. Is this taken out of your profit, as you describe above, or do you add in 5% - 10% in your charge to customer. Just curious. Thanks. Zeebo |
|
|
|
|
|
|
#15 | |
|
Painting Contractor
|
Re: Variables To Consider When Painting 1000 SF???Quote:
__________________
Just because some of us can read and write and do a little math, that doesn't mean we deserve to conquer the Universe. Kurt Vonnegut, (1922 - 2007) from the Novel 'Hocus Pocus' The NAPP Milwaukee Painting Contractor |
|
|
|
|
|
|
#16 |
|
Pro
Trade: Painting Contractor
Join Date: Dec 2004
Location: Toronto
Posts: 1,836
|
Re: Variables To Consider When Painting 1000 SF???
If you recover overhead and profit hourly (by every hour charged),
every hour worked will give you the following: Hourly payment of you and others for field work, overhead recovery including your salary for running your business, even compensation for selling jobs ( commission?) Net profit. You can collect the leftover money or give every dollar coming to you a reason for doing so.
__________________
Toronto Painters Commercial Painting Commercial Painting Toronto Toronto Office Painters Painting Toronto Blog |
|
|
|
|
|
#17 |
|
Pro
Trade: HandyWOMAN
Join Date: Sep 2005
Location: Indianapolis
Posts: 115
|
Re: Variables To Consider When Painting 1000 SF???
Sorry to drag up this new thread but I was going through the forum and had another question that pertains to this and pricing paint jobs.
Residential repaints: What if you are putting on multiple coats, like 1 of primer and 2 of finish. How would you price that out. If I used Zeebo's orginal ino # of hours of painting, setup, clean-up and etc. and I estimated it to take 12.5 hrs to paint, setup etc for this job using 1 coat primer & 2 coats of finish am I right or fair to charge out like this (assuming my labor rate is $40.00) 12.5 x 40 = $500.00 plus the other costs that Zeebo showed (for example purposes only). Is that the correct way to price it with multiple coats? Thanks in advance,
__________________
Pat Harris A HandyWOMAN Service, LLC "Why call a handyman when you can call A HandyWOMAN? |
|
|
|
|
|
#18 | |
|
Pro Painter
|
Re: Variables To Consider When Painting 1000 SF???
That sounds about right to me. You know your production rates, and what it costs per hour to do the job, then add your profit and other expenses. If that's what it costs, that's what it costs. After adding your extra expenses to that $500 you will be in the right ballpark. When a customer asks for a "ballpark" tell em "yankee stadium"!!
Honestly though, that sounds about right. 1000 sq. ft. of wall space is a BIG room! 3 coats of paint on a sucker that big is gonna cost big.
__________________
-AAPaint AA Quality Painting & Pressure Washing LLC Jacksonville Painters Jacksonville, FL. Quote:
|
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| tips on painting baseboards with carpet floor and a tip for new painters | Zeebo | Painting & Finish Work | 10 | 04-22-2011 06:42 PM |
| How profitable is your painting business? | SeanATL | Painting & Finish Work | 13 | 04-21-2007 11:16 PM |
| Painting Question | lunaassoc | Painting & Finish Work | 1 | 06-29-2006 09:34 PM |
| Painting as part of your estimate | Mike Finley | Remodeling | 20 | 05-21-2006 11:25 PM |
| Pricing for painting HELP!! | Keefer | Painting & Finish Work | 9 | 03-16-2006 11:46 AM |
| Go to Page... |