Anyone out there have a good production rate for staining cedar shakes before they're installed. these are the typical relatively smooth shakes. I have 20 squares to complete. Haven't done this in about 8 years so i really have nothing better than a guess to work off of.
|
|
|
|
|
|
#2 |
|
Pro
Trade: Painting & Pressure Cleaning
Join Date: Jan 2005
Location: Central Florida
Posts: 187
|
Re: Prestaining Cedar Shakes
Not sure how someone elses production rate is going to benefit you.
Never did understand that question. Maybe I'm missing something. If so, I need to know what I'm missing. Tom Rohland, Jr. Ranger Painting & Pressure Cleaning, Inc. Lake Mary, Florida |
|
|
|
|
|
#3 |
|
Bah Humbug!
|
Re: Prestaining Cedar Shakes
I've asked similiar questions many times Tom. What I am trying to find is a refrence point to see if my figures are in line or way outta whack. I totally understand what you are saying... An experienced crew will do something much faster and probably better than an inexperienced crew. However I think it's still a valid question if it's being used as a guideline and not a rule.
My prefinish factories would charge me about $50 a square to prefinish those shakes. That's labor and material. I doubt you could do it at this cost, but they have the facilities and equipment setup to do it fast! Have you considered hiring a prefinish factory? |
|
|
|
|
|
#4 |
|
Pro
Trade: Paint and wallpaper
Join Date: Oct 2005
Posts: 249
|
Re: Prestaining Cedar Shakes
Tom, just thought I'd check with you guys. Seeing as all I'd have to go with otherwise would be a guess. By the way thanks for your help.
Grumpy, yeah there's no way I could come close to that price. I was going to have to construct a few racks etc. I've done the work before and it goes fast, but that was ages ago and never kept track or production rates. Looks as though the customer is going to choose a different product based on a lower price. A prefinish factory was the original plan but that fell through at the last minute. I just provided the builder a price in the event the customer still wanted the cedar shakes. |
|
|
|
|
|
#5 |
|
Pro
Trade: Paint and wallpaper
Join Date: Oct 2005
Posts: 249
|
Re: Prestaining Cedar Shakes
here's what we figured out. 2 guys are able to dunk and brush 1200 shakes in an 8 hour day. At my price that's roughly 4-5 times the price of Grumpy's pre-finish contractor, but hey, I'll take what i can get.
|
|
|
|
|
|
#6 |
|
Registered User
Trade: Restoration
Join Date: May 2010
Location: Detroit, Michigan
Posts: 1
|
Re: Prestaining Cedar Shakes
Phinsher...just wondering how that Cedar Shake Dip and Brush Production rate of - 1200 shakes in an 8 hour day ultimately worked out? We are considering a 45- square CS project and I still haven't been able to get a good number on the number of shakes in a bundle. Not sure if you were able to get an answer remember approximately how many pieces you had on that 20-square project. Thanks for the help!
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| cedar shingles | wink | Roofing | 22 | 10-08-2008 07:36 AM |
| Cedar Shakes | reveivl | Roofing | 8 | 06-05-2007 09:40 PM |
| cedar shakes | newnoise | Roofing | 2 | 04-20-2007 12:42 AM |
| what is a square of cedar shakes | phinsher | Carpentry | 30 | 07-26-2006 01:35 PM |
| roofing over cedar | jkdon | Roofing | 24 | 03-16-2006 09:26 AM |
| Go to Page... |