Question Painting fresh concrete surfaces

We have to paint below ground concrete surfaces with Epoxy PAINT or Bituminous paint. The engineers says we can paint only after 30 days. What is the actual time gap required to paint on new concrete surfaces.
Any reference to international codes? We tell him only 7days are sufficient.

What is the international practice for such painting?

Thanks.

Gnanchandra is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 11-16-2008, 01:26 PM   #2
Member
Trade: painting contractor(semi retired)
 
Join Date: Aug 2008
Location: S. Central Florida
Posts: 41
there is no way the moisture will be out of contrete walls below grade in 7 days. The way to check moisture on concrete is to put plastic on the walls and seal the edges tightly(maybe several times) with tape. If there is any condensation on the plastic....it's still wet. Thats just the old fashioned way. I'm sure there are meters today that will measure moisture content. pd
painterdude is offline   Reply With Quote
Old 11-16-2008, 09:42 PM   #3
Pro
 
painter213's Avatar
Trade: Coatings consultant and Inspector
 
Join Date: Nov 2008
Location: Southeast
Posts: 218
Send a message via AIM to painter213
It is prefered to let the concrete cure for at least 28 days. If there are curing agents used, you can get on sooner. You can check out the Society for Protective Coatings SSPC-PA 7 Specification for Applying Thin Film Coatings to Concrete for further information. Also check out the ACI International Standards for more standards available. Also, as far as test methods go, you can check out ASTM D4263. This the Plastic Sheet Test Method. This test only tells you the presence of moisture in the concrete. Pretty much ALL concrete has some moisture. For a detailed test, you will need a Quanative test to get the amount present. If the concrete is exposed on one side, then your not going to be trapping any moisture in place. It will have a way out, anyway. One thing is to make sure that you do the required surface prep. If you do not, then you can apply the best coating out there and it will not last. You can also check with the ICRI "International Concrete Repair Institute" for more information as well. There is a lot of information out there. Also, I would recommed to check with your coating supplier, to see what there requirements are for concrete application. Get a specification and follow it.
__________________
Benny Abbott
Abbott Consulting and Coating Inspections
E-Mail: babbott@abbottcoatinginspections.com
Phone: (205-717-0292)
painter213 is offline   Reply With Quote
Old 11-16-2008, 09:45 PM   #4
Handle It!
 
MALCO.New.York's Avatar
Trade: Everything The Union Guys Do Not Want To Do
 
Join Date: Feb 2008
Location: Brooklyn, NY ~ Haverford, PA
Posts: 7,901
Quote:
Originally Posted by Gnanchandra View Post
We have to paint below ground concrete surfaces with Epoxy PAINT or Bituminous paint. The engineers says we can paint only after 30 days. What is the actual time gap required to paint on new concrete surfaces.
Any reference to international codes? We tell him only 7days are sufficient.

What is the international practice for such painting?

Thanks.
WRONG. PERIOD. 30 days is the accepted allotment of cure time. Actually it takes a couplea years for a slab to TRULY "Cure".

Especially with a "Below Grade" pour.

I know bunk about the Science of Crete, but I do know that which I share.
__________________
Something to One may be Nothing to another!

Ultimate Wisdom---------
http://www.youtube.com/watch?v=_k1Ug...ture=rec-HM-r2

Last edited by MALCO.New.York; 11-16-2008 at 09:48 PM.
MALCO.New.York is offline   Reply With Quote
Old 11-16-2008, 10:08 PM   #5
Bunny by Malco - NY
 
Chris Johnson's Avatar
Trade: ICF Construction
 
Join Date: Apr 2007
Location: North of 49
Posts: 2,221
First off concrete cure is a loose term. In the concrete business we base what strength we can reach in 28 days, this is the industry standard since Christ was a cowboy. Concrete takes longer to cure than a couple years is dependant on several factors, exposed concrete continually cures till it starts deteriorating, that time frame varies by all sorts of factors none of which can be answered quickly or properly without science getting involved and exposure and placement and location and weather factors, etc.

For a below grade application using a bituthane type product application after 7 days is generally acceptable, depending on weather conditions the wall has received since the initial pour. It's one of those things that requires an experience concrete guy to look at the wall and say either yes or no you can apply the product now. I have applied bituthane the following day in certain climates without issue and have also done projects where I had to wait over 2 weeks.
__________________
Chris
Chris Johnson is offline   Reply With Quote
Old 11-19-2008, 10:18 PM   #6
Pro
Trade: painting
 
Join Date: Mar 2008
Location: Frankfort, KY
Posts: 107
All you have to do is go to the paint store and pick up a gallon of paint that u plan to use. It will tell you how long you need to wait or all warranties are void. Plus you have the engineers right there telling you the facts just open your ears.
capital city is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Painting Concrete Patio kcel Specialty Coatings 20 11-27-2008 12:49 PM
Advice - concrete Pool Deck coping ejleonard Masonry 4 06-17-2008 04:18 PM
Painting a concrete block building Vinny Painting & Finish Work 3 12-06-2007 11:15 AM
Painting Concrete Block Flikka Painting & Finish Work 1 11-28-2007 04:52 PM