#1 |
|
Registered User
Trade: Carpenter
Join Date: Aug 2008
Posts: 15
|
Estimate On Ceramic Tile
What does everyone charge for labor costs installing ceramic Tile per Sq Ft. in Philadelphia
|
|
|
|
|
|
#2 |
|
Member
Trade: Tile,Marble & Granite
Join Date: Sep 2008
Location: Trenton Michigan
Posts: 64
|
Re: Estimate On Ceramic Tile
Usually the prices are let's say a couple of dollars less than Home Depot and Lowes,so you can get the job from customers
|
|
|
|
|
|
#3 |
|
Registered User
Trade: Carpenter
Join Date: Aug 2008
Posts: 15
|
Re: Estimate On Ceramic Tile
Well what do you usually Charge?
|
|
|
|
|
|
#4 |
|
Professional Instigator
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872
|
Re: Estimate On Ceramic Tile |
|
|
|
|
|
#5 |
|
Member
Trade: Tile,Marble & Granite
Join Date: Sep 2008
Location: Trenton Michigan
Posts: 64
|
Re: Estimate On Ceramic Tile
jobs under 150 sqft I charge by job
Last edited by detroitMi; 10-06-2008 at 11:36 PM. |
|
|
|
|
|
#6 | |
|
Professional Instigator
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872
|
Re: Estimate On Ceramic TileQuote:
That is too much how do you compete with homedepot or lowe's with those prices?? |
|
|
|
|
|
|
#7 |
|
Member
Trade: Tile,Marble & Granite
Join Date: Sep 2008
Location: Trenton Michigan
Posts: 64
|
Re: Estimate On Ceramic Tile
Home Depot ,Lowes dont do mud at all , they use backerboards
|
|
|
|
|
|
#8 |
|
Member
Trade: Tile,Marble & Granite
Join Date: Sep 2008
Location: Trenton Michigan
Posts: 64
|
Re: Estimate On Ceramic Tile
none of my customers wants backerboards in their house, plus I supply the mud(here's the catch) LOWES charges over 8.50 labour only
|
|
|
|
|
|
#9 |
|
Registered User
Trade: Carpenter
Join Date: Aug 2008
Posts: 15
|
Re: Estimate On Ceramic Tile
Well i am using ceramic tile with backerboard and grouted. Its only a bathroom so 25Sq Ft. Just trying to figure out what to charge per sq Ft for labor so i can figure this out.
|
|
|
|
|
|
#10 | |
|
DavidC
Trade: Remodeler
Join Date: Feb 2008
Location: NNY
Posts: 1,917
|
Re: Estimate On Ceramic TileQuote:
Seriously, you're not trying to figure this out, you're trying to get us to tell you. Michael Stone's Markup & Profit, A Contractors Guide if you really want to figure it out. If you start there I'll be happy to pitch in where I can. Good Luck Dave
__________________
www.CookContractingLLC.com |
|
|
|
|
|
|
#11 | |
|
Professional Instigator
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872
|
Re: Estimate On Ceramic TileQuote:
I missed this one David . But to repeat BUY MICHAEL STONES MARKUP AND PROFIT book and CD
|
|
|
|
|
|
|
#12 | |
|
Registered User
Trade: Carpenter
Join Date: Aug 2008
Posts: 15
|
Re: Estimate On Ceramic Tile
Well i am trying to figure it out so i can figure out how to estimate jobs better for myself.
Quote:
|
|
|
|
|
|
|
#13 | |
|
DavidC
Trade: Remodeler
Join Date: Feb 2008
Location: NNY
Posts: 1,917
|
Re: Estimate On Ceramic TileQuote:
New construction or remodel? Good Luck Dave
__________________
www.CookContractingLLC.com |
|
|
|
|
|
|
#14 | |
|
Registered User
Trade: Carpenter
Join Date: Aug 2008
Posts: 15
|
Re: Estimate On Ceramic Tile
Its a Remodel for a bathroom
Quote:
|
|
|
|
|
|
|
#15 | |
|
Chief Toilet Mover
Trade: Bathroom Remodeling
Join Date: Apr 2004
Location: Littleton, Colorado
Posts: 14,078
|
Re: Estimate On Ceramic TileQuote:
![]() Let's name just one - Home Depot and Lowes are now considered the standard of the industry? They now set the bar as the best there is and everyone else should be lower because why??? Last time I checked both of them have about 10,000 consumer complaints of homeowners crying over the sh*tty jobs their 'contractors' deliver. So that means the freak'n worst now sets the bar for the most you can charge?? What the hell? Why aren't you doubling what Home Depot and Lowes charge as a starting point? Just another example of contractors great at racing to the bottom. Somehow a lot of us seem to believe the prizes are only awarded to whomever can do it the cheapest. |
|
|
|
|
|
|
#16 |
|
DavidC
Trade: Remodeler
Join Date: Feb 2008
Location: NNY
Posts: 1,917
|
Re: Estimate On Ceramic Tile
With remodeling no two jobs are alike. Variations will skew your sq. ft. figures and most likely bite you.
Can you reasonably calculate how many hours this will take to complete? Start with a fresh peice of paper and list each portion of the job in the order you will perform them. (Unload and setup, demo work, repairs, etc.) Visualize your way through the job from start to finish and assign a time for each task. After the job is done you can go down this same list and record how long each step really took. This will help improve accuracy with future estimates. Will you be working alone or with help? Good Luck Dave
__________________
www.CookContractingLLC.com |
|
|
|
|
|
#17 | ||
|
Builder/Remodeler
|
Re: Estimate On Ceramic TileQuote:
![]() As this obviously is... ![]() Quote:
__________________
![]() Christopher Wright, CR: President @ WrightWorks, LLC/President @ Central Indiana NARI, Named to the 2010 REMODELING Big50 www.WrightWorks.net - Facebook - Twitter - Carmel Remodeling Indianapolis Kitchen Remodeling Contractor - You Can Get There From Here |
||
|
|
|
|
|
#18 |
|
Mod / ArchiBuilder
Trade: Design/Build Outdoor Living
Join Date: Aug 2004
Location: ArkLaTexOma
Posts: 6,611
|
Re: Estimate On Ceramic Tile
I am going to stay out of this one.
__________________
Tulsa's Leader in Outdoor Living Construction | Facebook | Tulsa Pergola Builder | Tulsa Outdoor Kitchens |
|
|
|
|
|
#19 | |
|
Registered User
Trade: Carpenter
Join Date: Aug 2008
Posts: 15
|
Re: Estimate On Ceramic Tile
To complete properly 5 days with one guy. So after i know the amount of days to do the job now how do i go about quoting it.
Quote:
|
|
|
|
|
|
|
#20 |
|
DavidC
Trade: Remodeler
Join Date: Feb 2008
Location: NNY
Posts: 1,917
|
Re: Estimate On Ceramic Tile
Broken down into days or hours you can now apply your daily or hourly rate. To find that you need to know how much you require to get paid after all expenses, hourly or daily. Now add the state & federal taxes. Add up all of the holidays and vacation time, any other bennies you deserve. This is your labor cost. (assuming you work alone for now)
You also need to know your overhead costs so you can break that down to daily or hourly. Include your insurance, truck, office, phone, etc. (any expense that you cannot tie directly to a job) Add your daily labor cost to your daily overhead and there is your daily labor rate. I really really really recommend Michael Stone's Markup & Profit, A Contractors Guide. It's only $32 and comes with a CD. Read it through once then start again and apply it 1 chapter at a time to your business. That way you won't forget the profit. Hope that helps. Good Luck Dave
__________________
www.CookContractingLLC.com |
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Laying new ceramic tile on wall | faromic80 | Ceramic & Stone Tile | 4 | 09-17-2008 08:01 AM |
| Ceramic tile floor tile over control joint ? | master mason | Ceramic & Stone Tile | 18 | 05-10-2008 02:14 AM |
| flooded ceramic tile floor on concrete | bmorrisey | Ceramic & Stone Tile | 2 | 12-06-2007 09:35 PM |
| ceramic tile vs quarry tile labor | t336 | Flooring | 2 | 07-18-2007 08:00 PM |
| ceramic tile | pre-reno | Flooring | 10 | 02-04-2007 04:15 PM |