Now with a couple of pipe people around, I was wondering how you size todays machines for trenching production. Thirty years ago I worked two years for a top notch sewer and water company and the rule of thumb seemed that 1/3 to 1/2 of the machines digging depth was how a machine was sized for the job. A 14' backhoe dug 4' or 5' trenches. A 18'-20' excavator was on jobs 6' to 8' and so on for production work.
Nick |
|
|
|
|
|
#2 |
|
Pro
Trade: underground
Join Date: Oct 2004
Location: Southeast USA
Posts: 3,228
|
Re: Trenching Production
Lift specs are a big deal for me. Regularly handling precast structures that weigh as much as 9 or 10 tons a piece demands an excavator that can handle those loads safely. Even handling a 4 ton piece at any distance demands a fairly stout machine. A 33 metric ton hoe seems to be a good fit for me in that regard. It also allows me to rip rock that a 16 metric ton machine wouldn't even budge.
On the other hand, a 16-20 MT machine can usually keep up tamping the backfil that the bigger hoe produces and offers some flexibility for close quarter work. Last edited by PipeGuy; 04-17-2006 at 10:50 PM. |
|
|
|
|
|
#3 |
|
Pro
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 2,604
|
Re: Trenching Production
the bulk of our work is 16' deep or less, occasionally get a few jobs deeper. we run 200 sized excavators. and 544G deere loaders. seems like a good match for us. still big enough we can handle 48" rcp storm sewer if need be.
__________________
someday, i'll be as patient as Nick. |
|
|
|
|
|
#4 | |
|
Pro
Trade: underground
Join Date: Oct 2004
Location: Southeast USA
Posts: 3,228
|
Re: Trenching ProductionQuote:
|
|
|
|
|
|
|
#5 |
|
Vagitarian
|
Re: Trenching Production
Well, we only have 2 excavators, so we are limited to what we choose. We have a Cat 315 which I use for the underground electric, cable phone. Then I use our Kobelco 200 for the sanitary and storm. I've gone 19' deep with the 200 with no problems.
__________________
Life is hard. It is harder when you are stupid Uncle Sam wants YOU....to speak ENGLISH |
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| New Trenching and Excavating Forum | Nathan | Excavation & Site Work | 20 | 08-16-2010 01:27 AM |
| Trenching Advice - What to buy? | casey344 | Landscaping | 6 | 09-22-2007 08:52 AM |
| Production Manager | Brian | Painting & Finish Work | 5 | 07-16-2007 11:50 PM |
| Trenching in New Residential Development? | Trencher | Excavation & Site Work | 11 | 03-08-2007 06:08 PM |
| How to pay a production manager? | Grumpy | Business | 1 | 01-31-2006 10:28 PM |
| Go to Page... |