Town Road Price Per Linear Foot - Eastern Connecticut

I am trying to land a job as a GC on a small sub-division project in Eastern CT. It will require 1200' of newly laid town road to the following specifications. The road must be 24' wide with a simple cape cod curb, and one hammer head turn-around at the end of the cul-de-sac.

My crew will be clearing the trees and and all other work that a landscape crew can do. Roughly, what is the cost going to be to get someone to lay the road? One GC told me to estimate $115 a linear foot. This seems low to me.

Thanks in advance.

7.3 ROAD CONSTRUCTION

7.3.1 Roadways shall be provided with a twelve (12) inch base course, a four (4) inch penetrated stone course, and a two and one half (2.5) inch wearing surface.

7.3.2 A rolled gravel base course shall be spread over the sub grade rolled and compacted in six (6) inch layers with a 10-ton roller, 15-ton in commercial and industrial subdivision, to a depth of twelve (12) inches and shall conform to the typical cross section.

7.3.3 The penetrated stone course shall be uniformly blended and shall conform to the requirements of the current edition of the Connecticut Department of Transportation, Bureau of Highways Standard Specifications for Roads, Bridges, and Incidental Construction and shall consist of clean two (2) inch course aggregate evenly applied and rolled to a depth of four (4) inches. The rolling shall be sufficient to form a uniform surface. These surfaces shall then be penetrated with penetration asphalt, applying between 1.35 and 1.75 gallons per square yard. Immediately following the applications of the penetration asphalt, sufficient one half (.5) inch keystone shall be spread to fill voids and allow a roller to pass over and not break or disturb the top of the stone course.
This shall then be rolled to a smooth true surface two and one half (2.5) inches below the proposed finished grade as shown on the profile, and having a transverse grade parallel to that shown on the applicable cross-section plan. Prior to any further construction, the roadway shall again be inspected as hereinafter provided (third inspection).

7.3.4 All road-wearing surfaces shall be paved to the full width specified herein to a compacted thickness of three (3) inches with Bituminous Concrete Pavement. The aggregate shall be composed, mixed, and laid out in two courses as specified in the Connecticut Department of Transportation, Bureau of Highways Standard Specifications for Roads, Bridges, and Incidental Construction.

7.3.5 Upon completion of the pavement, the roadway shall again be inspected, as hereinafter provided (fourth inspection).


Last edited by tlynch; 01-05-2009 at 05:25 PM.
tlynch is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 01-05-2009, 05:07 PM   #2
Pro
 
dayexco's Avatar
Trade: entrepreneur of excavating expertise
 
Join Date: Mar 2006
Posts: 1,812
we have no clue as to what your local costs are....nor your overhead. any values we throw at you will no doubt not be what it takes to make a profit, or get the job. you need to sit down yourself and figure out what this is going to cost you, and the margin of profit you wish to make...good luck
__________________
When the student is ready, the teacher will appear
[b]Do you teach the best what you need to learn the most?[b]
a few pics of our operation and equipment at http://s72.photobucket.com/albums/i182/dayexco/
dayexco is offline   Reply With Quote
Old 01-05-2009, 05:51 PM   #3
Vagitarian
 
rino1494's Avatar
Trade: site and utility contractor
 
Join Date: Jan 2006
Location: Dallas, PA
Posts: 2,446
Send a message via AIM to rino1494
Way, way, way too vague to tell you a price. Are you stripping the topsoil, doing the cuts and fills, storm drains, sanitary, erosion control, staking, etc...

For residential developments, we get anywhere from $150/ft - $300/ft. All depends on what is involved and the topography of the land.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is offline   Reply With Quote
Old 01-05-2009, 06:11 PM   #4
Registered User
Trade: Basic Landscaping
 
Join Date: Jan 2009
Posts: 6
Rino -

Thanks, although that is a large range - it actually helps. Are you located around North Stonington CT?
tlynch is offline   Reply With Quote
Old 01-05-2009, 06:13 PM   #5
Handle It!
 
MALCO.New.York's Avatar
Trade: Everything The Union Guys Do Not Want To Do
 
Join Date: Feb 2008
Location: Brooklyn, NY ~ Haverford, PA
Posts: 8,057
There are a Buncha Heavy Metal Operators in CT. Best you listen to and possibly Co-Work with these PROFESSIONALS.

And I do Mean PROFESSIONALS. Denick can teach you VOLUMES.
__________________
Something to One may be Nothing to another!

Ultimate Wisdom---------
http://www.youtube.com/watch?v=_k1Ug...ture=rec-HM-r2
MALCO.New.York is online now   Reply With Quote
Old 01-05-2009, 06:46 PM   #6
Registered User
Trade: Basic Landscaping
 
Join Date: Jan 2009
Posts: 6
Thanks, I simply do landscaping, I have no intention of constructing a road, it is well beyond my area of expertise.

I have been hired to manage the construction process for a local developer that I have a relationship with. I will be hiring a contractor to build the road, we just want as much information as possible before we start talking to contractors. I will not be looking to make a direct profit on the road construction.

I will be the one clearing a 40' wide level dirt path through the lot.

We just discovered that we may be able to get enough road frontage with a single 600' cul-de-sac if we can get the proper variance.

Any information is appreciated.
tlynch is offline   Reply With Quote
Old 01-05-2009, 07:12 PM   #7
Pro
 
jmic's Avatar
Trade: manager of excavation division
 
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660
The last town road I built was around 13 yrs. ago and it came in around $150 / lin. ft. with the same width / specs. that you mentioned. This was in lower Litchfield Cty.

This included a 10K gal. fire tank and approx. 150' of drainage off site connecting into C.B. on state rd.
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline   Reply With Quote
Old 01-05-2009, 08:03 PM   #8
Captain of the Titanic
 
Vinny's Avatar
Trade: Asphalt Paving,Excavating, Masonry
 
Join Date: Jul 2007
Location: Westport, Connecticut
Posts: 604
I have a guy in wallinford that may be able to help. They do chip / seal and paving

I would help but I was just wondering, If i provide a budget number, can I get a real shot to bid it?? I dont think I need practice coming up with prices to projects that may never happen
__________________
Roccies Asphalt Paving
The Right Way Driveway Company
If you say you cant, your a loser. If you say you wont, your a quiter. Which one do you want to be?
Vinny is offline   Reply With Quote
Old 01-05-2009, 10:36 PM   #9
Registered User
Trade: Basic Landscaping
 
Join Date: Jan 2009
Posts: 6
Vinny - sorry, I can't promise anyone a chance to bid, as we are still calculating the feasibility of this project in these economic conditions.

But a high-end ballpark estimate based on a couple recent projects in the area would be a great help.

Send me your contact info and I will keep it in my Rolodex.
tlynch is offline   Reply With Quote
Old 01-05-2009, 10:53 PM   #10
Midnight
 
Blas's Avatar
Trade: Excavating, Grading, Demolition, Underground Utilities
 
Join Date: Jan 2008
Location: Minnesota
Posts: 154
Quote:
Originally Posted by Vinny View Post
I have a guy in wallinford that may be able to help. They do chip / seal and paving

I would help but I was just wondering, If i provide a budget number, can I get a real shot to bid it?? I dont think I need practice coming up with prices to projects that may never happen

Practice makes perfect.
__________________
"It is what it is"
Blas is offline   Reply With Quote
Old 01-06-2009, 10:04 AM   #11
Registered User
Trade: Basic Landscaping
 
Join Date: Jan 2009
Posts: 6
No, no, no, I am not looking for anyone to spend a bunch of time on this. Just looking for quick feedback.

Thanks everyone.
tlynch is offline   Reply With Quote
Old 01-11-2009, 01:13 AM   #12
Member
 
ConstSvcs's Avatar
Trade: New home and remodeling
 
Join Date: Nov 2007
Location: CT shoreline
Posts: 56
The correct thing to do woul be to call Tilcon or someone like Sullivan or B&L for an accurate price.
ConstSvcs is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off



Top of Page | View New Posts


All times are GMT -5. The time now is 08:13 PM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC