Rippable Rock...


I, like many of you at some point or another, am not being paid for a rock job I'm on. I hit rock in the middle of december on a mass grading job I'm working on. There are NO geotech engineering reports to my knowledge so the job certainly isn't classified. The owner's engineer is the 3rd party representative throughout the process and has been quantifying the rock. I've taken a number of pictures of the dozer ripping the material and the smoke flying off behind the dozer. However, the GC on the project claims I only experienced 'delayed excavation' and will not be paid for any rock. This seems like a fancy way of getting around a rock clause. Is this typical and I'm just missing the boat here? I've completed a number of jobs in which I charged for rippable rock. The engineer's field reports even classify it as rippable rock. The GC is denying the change order with a claim that rippable rock is, as a standard practice, not beyond the project scope. Am I missing something here? Please advise.

ElIngeniero is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 02-07-2008, 07:37 PM   #2
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Rippable Rock...


E,

It sounds like there was not a clear understanding somewhere. We always stop work when rock is encountered and get it in writing as to how to proceed and how we are getting paid. If that wasn't done before hand.

Do you have a contract? Does it have a rock clause? What does it define as rock? It's hard to argue these things after the fact.
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 02-07-2008, 08:59 PM   #3
Midnight
 
Blas's Avatar
 
Trade: Excavating, Grading, Demolition, Underground Utilities
Join Date: Jan 2008
Location: Minnesota
Posts: 177

Re: Rippable Rock...


Typical...... Delayed excavation...... Rock is rock, I would shut her down, that usually seems to get the ball rolling. If anything the guy will learn not to mess with you in the future depending how much you already have into the project and how often you work with this GC. If there is nothing in the specs or your contract about rock I would say you at least have an argument. Besides delayed excavation, and ripping should be just as expensive.
__________________
"It is what it is"
Blas is offline  
Old 02-07-2008, 09:10 PM   #4
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Rippable Rock...


E,

I should say our only rpping of rock is with excavators. We would be excavating with a bucket and hit rock. Then we would stop and change to a ripper tooth. Our excavations are not wide open areas.

If you were dozing earth and encountered rock. Then just lowered the ripper and kept producing it seems harder to plead the case.
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein

Last edited by denick; 02-07-2008 at 09:25 PM.
denick is offline  
Old 02-07-2008, 09:45 PM   #5
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,092
Send a message via AIM to rino1494

Re: Rippable Rock...


It really depends on what your rock clause states. It should mention rippable and non-rippable rock. Either way, I would fight it tooth and nail. How many yds of material are we talking about ?? You say a mass-grading job, I am assuming a large commerical project.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is offline  
Old 02-07-2008, 10:36 PM   #6
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 2,604

Re: Rippable Rock...


if this goes head to head, i'm sure owner is going to open the spec book and point you to the page where it says..."contractor shall familiarize himself with the site before bidding" or.........."such costs shall be considered incidental unless otherwise noted by the engineer"...i wish you well, but i think you're screwed like a housecat.
__________________
someday, i'll be as patient as Nick.
dayexco is offline  
Old 02-08-2008, 08:04 AM   #7
Member
 
ElIngeniero's Avatar
 
Trade: Sitework
Join Date: Feb 2008
Posts: 93

Re: Rippable Rock...


There are no borings or specifications on the project (the owner is a church and is trying to save as much money as possible I suppose). We have a clause in our contract that spells out "If rock, mud, dewatering...etc is encountered, it will be at cost+price". We also have a mass rock and trench rock price in our contract. They are saying, however, that since we didn't do any blasting and we (& the engineer) are classifying it as 'rippable rock', we can't get paid for said rippable rock as it is not an unsuitable material.

We were digging with 2 330 Excavators and getting it out s-l-o-w-l-y so we brought in a D-8 with a ripper. We actually cut a significant amount of rock thinking we'd get through it and not have to change order it.

We're talking about 12,000 CY's of rock. I spoke with the GC yesterday and he claims that we can get paid for 'delayed excavation' but he didn't think we were delayed very much so he wants us to bill him at an hourly rate. I think he's doing this because the amount of time we were delayed is a bit more open to discussion whereas the amount of rock is not (the owner's engineer has been quantifying the rock from the start and is in complete agreement with us).

I've been looking for a site like this for ages--you've all been a wonderful help!
ElIngeniero is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Drilling river rock kevbo Masonry 5 01-17-2008 07:12 PM
Rock Clause In Contract Driftwood Excavation & Site Work 9 03-15-2007 09:42 PM
Rock / No Rock denick Excavation & Site Work 11 02-13-2007 09:59 PM
dug footer for deck, monster rock in one. ramblemn Construction 7 06-06-2006 12:18 AM
Rock splitting denick Excavation & Site Work 7 04-30-2006 07:21 PM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?