Hi Iam trying to find info on monlithic footers, where the footer and the floor are poured at the same time.How much wieght they will support ? Also info on how freeze and thaw affect them. Thank's Dave.
|
|
|
|
|
|
#2 |
|
Custom Builder
|
Re: Monolithic Footers ???
1.Use fiber mesh.
2.No less than 3500PSI. 3.Tie your wire floor mesh to verical rebar down the foundation wall. 4.Remove "ALL" organic and loose material. 5.If fill is needed, only fill with 1" rock and keep it out of the footing. 6.Slope the inside edge of the slab to foundation wall bank a little. 7.Get ready to use a lot of crete 8.Drink beer when your done. These steps are very important with monolithic foundation pours. Hope this helps. Bob
__________________
Bob |
|
|
|
|
|
#3 |
|
Pro
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452
|
Re: Monolithic Footers ???
Dave,
A monolithic pour of footings, frost wall and slab wood have the same strength as a regular foundation when sized appropriately. Your depth would be the required footing depth as any foundation in your area. All the things Bob listed. And whatever the local building code and official require. It can be harder to pour if you have no experience with it. There are cracking concerns when not done properly. Nick |
|
|
|
|
|
#4 |
|
Valley Springs,ca
Trade: Landscaping/Spec building
Join Date: Dec 2005
Location: Valley Springs,Ca
Posts: 100
|
Re: Monolithic Footers ???
Glass you got it all wrong. Here in Cali. all my concrete guys start #8 after #3,4 and 5
|
|
|
|
|
|
#5 |
|
Custom Builder
|
Re: Monolithic Footers ???
LOL
Glad I'm not framing over them.Bob
__________________
Bob |
|
|
|
|
|
#6 |
|
Member
Trade: carpentry/ self employed master craftsman
Join Date: Mar 2005
Location: massena ny
Posts: 81
|
Re: Monolithic Footers ???
how about some drawings???
http://www.slcc.edu/tech/techsp/arch...os_lecture.htm I hope this helps... Dan
__________________
"what ever it takes" |
|
|
|
|
|
#7 | |
|
Contractor
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276
|
Re: Monolithic Footers ???Quote:
![]() What exactly are you trying to do Dave? We do our monolithic pours a couple of ways depending upon conditions. The link Sawdusted put up may help you, though we do ours differently than what is shown there. A little more info please. Tom |
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| monolithic slab vs Block Slab | The General | Construction | 12 | 09-03-2009 09:38 PM |
| Monolithic Slab foundation drain tile placement | J Hague | Construction | 32 | 02-08-2008 11:12 PM |
| Deck footers & freezing temps | Woodcrafter74 | Decks & Fencing | 1 | 01-31-2007 08:51 AM |
| Decking footers | Teetorbilt | Decks & Fencing | 10 | 08-19-2006 02:44 PM |
| Basement slab question | n74tg | Masonry | 5 | 05-26-2006 04:38 PM |
| Go to Page... |