Moisture Conditioned Pads

 
Thread Tools Search this Thread Display Modes
Old 01-08-2007, 01:02 AM   #1
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Moisture Conditioned Pads


Is this done on a regular basis anywhere else in the country?

We are lucky here in San Antonio to have a large limestone formation (Edwards escarpment) at the foothills of the Texas hill county that gravel is quarried from to produce concrete and asphalt aggregates, road base and many other stone and associated byproducts here locally. We have been spoiled over the years by the cheap cost of crushed limestone. Much of the materials manufactured here are shipped by rail to Houston, Dallas and other areas in the south. However, here recently we have been experience a construction boom and material prices have increased substantially due to supply and demand. This has created a need for other means and techniques for constructing building pads which have most always been constructed of crushed or naturally occurring (pit-run) gravels.

Method:
Rather than installing a gravel pad in compacted lifts, the Geo-technical Engineers are having us preswell the existing soils with water to some predetermined depth to a achieve a potential for vertical rise of less than 1". The existing soil is removed, for example, 5 feet below bottom of slab and then reinstalled to +5% to +10% of optimum moisture and compacted to +90% density in 6" compacted lifts. This can be a pretty muddy situation considering the optimum moisture of many of these clayey materials is about 17% to 20% and we have to achieve at least 5% above that (approaching snot). One of the Engineers insists we mix the mud with a pulverizer/mixer to insure complete amalgamation of soil and solution. I can't even begin to tell you what a quagmire that is, the mixer won't even pull itself through the mud under it's own power, we have to pull it with a D6.

Anyway, just wondering if any others are doing this procedure.

Dirtguy is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 01-08-2007, 08:36 AM   #2
Pro
 
jmic's Avatar
 
Trade: manager of excavation division
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660

Re: Moisture Conditioned Pads


Quote:
Originally Posted by Dirtguy View Post
Is this done on a regular basis anywhere else in the country?

We are lucky here in San Antonio to have a large limestone formation (Edwards escarpment) at the foothills of the Texas hill county that gravel is quarried from to produce concrete and asphalt aggregates, road base and many other stone and associated byproducts here locally. We have been spoiled over the years by the cheap cost of crushed limestone. Much of the materials manufactured here are shipped by rail to Houston, Dallas and other areas in the south. However, here recently we have been experience a construction boom and material prices have increased substantially due to supply and demand. This has created a need for other means and techniques for constructing building pads which have most always been constructed of crushed or naturally occurring (pit-run) gravels.

Method:
Rather than installing a gravel pad in compacted lifts, the Geo-technical Engineers are having us preswell the existing soils with water to some predetermined depth to a achieve a potential for vertical rise of less than 1". The existing soil is removed, for example, 5 feet below bottom of slab and then reinstalled to +5% to +10% of optimum moisture and compacted to +90% density in 6" compacted lifts. This can be a pretty muddy situation considering the optimum moisture of many of these clayey materials is about 17% to 20% and we have to achieve at least 5% above that (approaching snot). One of the Engineers insists we mix the mud with a pulverizer/mixer to insure complete amalgamation of soil and solution. I can't even begin to tell you what a quagmire that is, the mixer won't even pull itself through the mud under it's own power, we have to pull it with a D6.

Anyway, just wondering if any others are doing this procedure.
Thank the Lord No!
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline  
Old 01-08-2007, 04:53 PM   #3
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Moisture Conditioned Pads


Gee Joe's never been so right with so few words!
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 01-08-2007, 05:23 PM   #4
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


To add to the problem the pads are typically warehouses around 200,000 to 150,000 square feet.
Dirtguy is offline  
Old 01-08-2007, 05:25 PM   #5
Pro
 
concretemasonry's Avatar
 
Trade: Masonry consultant
Join Date: Nov 2006
Location: MSP, Minnesota
Posts: 2,451

Re: Moisture Conditioned Pads


I guess we can scratch Texas off as one of the possible locations for the Garden of Eden.

Dick
concretemasonry is offline  
Old 01-08-2007, 05:50 PM   #6
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Moisture Conditioned Pads


Gee, When will the video be out?
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 01-08-2007, 06:02 PM   #7
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


It's a horror flick, we're editing right now.
Dirtguy is offline  
Old 01-08-2007, 07:17 PM   #8
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,092
Send a message via AIM to rino1494

Re: Moisture Conditioned Pads


So, are you telling me that you are not using crushed stone for under slabs ??

I don't see the benefit to saturating the soil above it's optmium moisture content and then compacting.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is offline  
Old 01-08-2007, 07:38 PM   #9
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


The "theory" by the Engineer is the that we are preswelling the soil by saturating it to the point that it will not swell anymore. For constructability purposes a 12" layer of gravel is used to cap the moisture conditioned soil. This allows the concrete contractor to have a workable surface to pour the slab. Here's a pic of a pad about 40% complete.
Attached Images
 
Dirtguy is offline  
Old 01-08-2007, 07:44 PM   #10
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Moisture Conditioned Pads


I don't want to sound ignorant but what happens when it shrinks?
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 01-08-2007, 07:48 PM   #11
Pro
 
jmic's Avatar
 
Trade: manager of excavation division
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660

Re: Moisture Conditioned Pads


Quote:
Originally Posted by Dirtguy View Post
The "theory" by the Engineer is the that we are preswelling the soil by saturating it to the point that it will not swell anymore. For constructability purposes a 12" layer of gravel is used to cap the moisture conditioned soil. This allows the concrete contractor to have a workable surface to pour the slab. Here's a pic of a pad about 40% complete.
Gee I thought that was an airport.
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline  
Old 01-08-2007, 08:04 PM   #12
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


Well I asked that same question. There is a +/- 8' deep trench that is dug around the perimeter of the pad and poly is installed along the inside wall of the trench and over the pad. The trench is then backfilled before concrete is installed. This creates a moisture barrier around and over the pad that is suppose to keep the moisture trapped in the pad and keep it from drying.

The whole process is a real pain in the a%#, but it is still cheaper than importing 30,000 in place yards of select fill and hauling off 20,000 of fat clay. Given my preference, I would much rather install the select fill. I can set up 20 trailers and have the pad installed in about 60% of the time it takes us to perform this process. But to import the select fill would cost about $12/CY and to export is about $7/CY (all in place CY). That's about $500,000 worth of import and export that is not needed, and man I can move alot of dirt with just labor and equipment for that kind of money.
Dirtguy is offline  
Old 01-08-2007, 08:18 PM   #13
Pro
 
jmic's Avatar
 
Trade: manager of excavation division
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660

Re: Moisture Conditioned Pads


Nick,
I guess it true what they say about Texas. Everything is bigger out there!
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline  
Old 01-08-2007, 08:30 PM   #14
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Moisture Conditioned Pads


The Headaches Too?
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 01-08-2007, 08:30 PM   #15
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


10-4
Dirtguy is offline  
Old 01-08-2007, 08:57 PM   #16
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: Moisture Conditioned Pads


Dirt,

How long have they been using this type of soil preperation?


You didn't just make it up did you. We really can't see much in that picture?
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 01-08-2007, 09:27 PM   #17
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276

Re: Moisture Conditioned Pads


WOW...

I am glad we don't have too much expansive clay around here!

I see some know and then, but very rarely.

Maybe you should have stopped by sooner, there was guy selling clay, or trying to, to the Corp. of Engineers, to import down to the levees in New Orleans, back in the spring I think.

Do you all remember that guy, he was gonna dig up the family farm or something, wanted to know how much to charge for the clay?

But Back on topic, DirtGuy you have a heck of a project on your hands, good luck in that mess. It must drive ya nuts to get to work in the AM to a nice dry site then turn the water on and make a huge muddy mess!
__________________
Tom

www.gebcon.com
tgeb is offline  
Old 01-08-2007, 10:40 PM   #18
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


No, I'm a contractor not and engineer. Tell me what to build and I will find a way to bid it, build it and bill it.... and hopefully collect it.

The moisture conditioning is a fairly new process in these parts. Howe er, we are starting to see it more often.

We have a 600,000 SF pad that bids in a couple of weeks and it's specified to recieve 60" of select fill. Due to the cost of importing 120,000 CY I would not be suprised to see the owner's engineer request an alternate price to provide a moisture conditioned pad.

Last edited by Dirtguy; 01-08-2007 at 10:43 PM.
Dirtguy is offline  
Old 01-09-2007, 08:38 AM   #19
Pro
 
PipeGuy's Avatar
 
Trade: underground
Join Date: Oct 2004
Location: Southeast USA
Posts: 3,228

Re: Moisture Conditioned Pads


Quote:
Originally Posted by Dirtguy View Post
...This creates a moisture barrier around and over the pad that is suppose to keep the moisture trapped in the pad and keep it from drying.
Why can't a moisture barrier be used to stabilze the expansive soil in its in-situ state; that is by precluding both absorption and evaporation instead of just evaporation (after the soil's been moisture conditioned)? At first glance I'd think it much more practical to protect the soil from 'wetting' over time than to preclude it from drying.
__________________
Fortunately I keep my feathers numbered for...for just such an emergency. -Foghorn Leghorn

Last edited by PipeGuy; 01-09-2007 at 08:41 AM.
PipeGuy is offline  
Old 01-09-2007, 09:28 AM   #20
Member
 
Dirtguy's Avatar
 
Trade: Sitework
Join Date: Dec 2006
Location: San Antonio, Texas
Posts: 56

Re: Moisture Conditioned Pads


That is a good point. Like I said I'm the contractor, not the engineer. I guess the reason is that they (the engineer) know that by performing this process there is good consistency of moisture and compacting through out the entire pad of a predetermined thickness.

There are also contractors that do a process of injection that is suppose to achieve the same result, but they have had problems with consistency. If while injecting and the water finds a sand seam it will follow the path of least resistance leaving a large portion of the clay untreated.

The injection method was specified for the stabilization of the ground under the SBC Center (where the Spurs play). After we excavated the hole a contractor from Dallas came down and started injecting using a "snake-oil" concoction of potassium and lignite. Don't ask me why they chose to use that, I can't tell you. Anyway, they got about 50% complete and we had some serious rain that left about 3 to 4 feet of water in the excavated hole, and that was a big f*%&$# hole! Well, the engineer decided that the water had diluted the solution to a point that the process would not work so they had to redesign the basement floor. Rather than use a slab-on-grade configuration they changed the entire floor to be suspended on carton forms. We got a change order to excavate and additional 14" in the bottom.
Dirtguy is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Moisture Barrier BKA Concrete & Paving 3 05-16-2007 04:53 PM
Acceptable moisture content of unfinished hardwood Grainywood Flooring 2 09-24-2006 08:46 PM
conditioned area stangit92 General Discussion 8 09-22-2006 09:59 PM
Unfinished home with too much moisture? Steve Unkie Carpentry 20 03-22-2006 11:07 PM
Landscape solution to basement moisture problem RJC Construction 3 11-21-2005 01:34 AM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?