I'm estimating a little dirt project and I need to know how much shrinkage I can expect with 98% compaction. For easy math, let's say I have 10cy on a truck what will I have when it's compacted?

__________________
"The beatings will continue until morale improves."
cdub is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 12-11-2008, 08:17 PM   #2
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: How Much Shrink Will You Get With Compaction


I always figure at least 20% with soil. If I have a bad feeling about it, I bump it up......it all depends since soils vary so much. 10 yards would compact to 8yds or less depending. That is how I do it, but that may not be correct. I'd love to hear what other guys use for a compaction factor.
cexcavation is offline  
Old 12-11-2008, 08:33 PM   #3
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 2,605

Re: How Much Shrink Will You Get With Compaction


take a sample of the soil to a soils engineering firm...have them determine your maximum dry density...go from there. anything you hear form us will be bogus, we have no clue as to what soil types, moisture contents you're dealing with....and, i'm not a soils engineer!

fwiw.....when i'm dealing with a cohesive soil...i estimate a min. of a 33-35% shrink....granulars, min. of 25%
__________________
someday, i'll be as patient as Nick.
dayexco is offline  
Old 12-11-2008, 08:35 PM   #4
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,278

Re: How Much Shrink Will You Get With Compaction


It really depends on the material you have.

Can you get more specific cdub?

For the most part I think C's method would work well, as would Dayexco's guidelines.
__________________
Tom

www.gebcon.com

Last edited by tgeb; 12-11-2008 at 08:38 PM.
tgeb is offline  
Old 12-11-2008, 09:13 PM   #5
Member
 
cdub's Avatar
 
Trade: excavating
Join Date: Feb 2008
Location: KS
Posts: 65

Re: How Much Shrink Will You Get With Compaction


I would call the material a silty clay. The material will be excavated from bank but the pay item is compacted fill. I'm trying to calculate production knowing the loose volume of my trucks but not the compacted volume. I've searched a little and found information to support both of you. I realize its a soil specific factor. I was just curious what rules of thumb you guys use. I would normally call a 15 yard truck 10 compacted, but I can't remember where I came up with that.
__________________
"The beatings will continue until morale improves."
cdub is offline  
Old 12-12-2008, 06:38 AM   #6
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,096
Send a message via AIM to rino1494

Re: How Much Shrink Will You Get With Compaction


Obviously it depends on the soil and the moisture content, but I usually figure 25%.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is online now  
Old 12-12-2008, 08:17 AM   #7
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: How Much Shrink Will You Get With Compaction


As day and rino said 25% for granular soils. 33% to 40% in clay soils.
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 12-12-2008, 03:25 PM   #8
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,096
Send a message via AIM to rino1494

Re: How Much Shrink Will You Get With Compaction


What are you building and what is your method of compaction ?? 98% seems like a pretty high standard. We recently completed a building pad for a 53,000 sq. ft. building and it called for 95% compaction. 12" lifts, we were getting about 102 with our Cat CS553 roller.

How much material are we talking about here. I wouldn't be too picky about percentage unless you are talking alot of material. As long as you are in the ballpark, you will be ok.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is online now  
Old 12-12-2008, 06:34 PM   #9
Midnight
 
Blas's Avatar
 
Trade: Excavating, Grading, Demolition, Underground Utilities
Join Date: Jan 2008
Location: Minnesota
Posts: 177

Re: How Much Shrink Will You Get With Compaction


25 percent will get you really close in any soil. When I bid projects 25,000CY or less that is what I use. If I am going to move more than 25,000CY then I will take a sample to the nerds.
__________________
"It is what it is"
Blas is offline  
Old 12-12-2008, 07:53 PM   #10
Member
 
cdub's Avatar
 
Trade: excavating
Join Date: Feb 2008
Location: KS
Posts: 65

Re: How Much Shrink Will You Get With Compaction


It's an auxillary spillway repair on a lake. There is about 20,000 of compacted fill. The farthest haul is about 1000 feet and averages about 300-400 ft. I was planning on getting some sort of vibratory roller for compaction. I've got along real well with them compacting sewer trench backfill (100+%) if the guys will slow down and let it do its work.
__________________
"The beatings will continue until morale improves."
cdub is offline  
Old 12-12-2008, 08:09 PM   #11
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 2,605

Re: How Much Shrink Will You Get With Compaction


Quote:
Originally Posted by Blas View Post
25 percent will get you really close in any soil. When I bid projects 25,000CY or less that is what I use. If I am going to move more than 25,000CY then I will take a sample to the nerds.
i'm going to bid every "clay" job i can get my hands on...and sub it to you!!!
__________________
someday, i'll be as patient as Nick.
dayexco is offline  
Old 12-12-2008, 09:04 PM   #12
Midnight
 
Blas's Avatar
 
Trade: Excavating, Grading, Demolition, Underground Utilities
Join Date: Jan 2008
Location: Minnesota
Posts: 177

Re: How Much Shrink Will You Get With Compaction


I guess I should have clarified a little more. Day hit the nail on the head with knowing the material you are moving. 25% would be a very crude example and would work for sand to sandy lean clay. If you are in a real plastic clay 35% - 40% wouldn't be out of the question. I wouldn't bid a plastic clay site with a 25% shrink factor, lucky for me this area is usually sand - sandy lean clay.
__________________
"It is what it is"
Blas is offline  
Old 12-12-2008, 10:08 PM   #13
Member
 
cdub's Avatar
 
Trade: excavating
Join Date: Feb 2008
Location: KS
Posts: 65

Re: How Much Shrink Will You Get With Compaction


Quote:
Originally Posted by Blas View Post
I guess I should have clarified a little more. Day hit the nail on the head with knowing the material you are moving. 25% would be a very crude example and would work for sand to sandy lean clay. If you are in a real plastic clay 35% - 40% wouldn't be out of the question. I wouldn't bid a plastic clay site with a 25% shrink factor, lucky for me this area is usually sand - sandy lean clay.
The 35-40% shrink is from loose form, correct? I figured 30% but I think my cycle times are slow. I figured it from the longer end of the haul to allow for down time and other work interruptions. 5% volume change could easily get absorbed.
I appreciate the advice guys. Thanks.
__________________
"The beatings will continue until morale improves."
cdub is offline  
Old 12-12-2008, 10:12 PM   #14
Member
 
cdub's Avatar
 
Trade: excavating
Join Date: Feb 2008
Location: KS
Posts: 65

Re: How Much Shrink Will You Get With Compaction


Quote:
Originally Posted by cdub View Post
The 35-40% shrink is from loose form, correct? I figured 30% but I think my cycle times are slow. I figured it from the longer end of the haul to allow for down time and other work interruptions. 5% volume change could easily get absorbed.
I appreciate the advice guys. Thanks.
10% may tickle a little.
__________________
"The beatings will continue until morale improves."
cdub is offline  
Old 12-12-2008, 10:39 PM   #15
Pro
 
denick's Avatar
 
Trade: excavating / concrete / masonry
Join Date: Feb 2006
Location: NW, CT
Posts: 2,452

Re: How Much Shrink Will You Get With Compaction


cdub,

If you need 200 cy to fill a hole of measured size. you need to dig 200 cy of dirt out of a bank. When you excavate it and dump it in the truck it swells to 270 cy at the 35% swell factor. You need to transport 270 cy. If you dump that 270 cy on the ground and compact it 100% it has a shrinkage factor of .74

All this depends on the material your digging is at a 100% compacted density. for that particular soil. if it was disturbed already and loosened it might already be in a swelled state. If the material that has been packed like iron for the length of a project and you start digging it it may swell at a factor X's 2.
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline  
Old 12-13-2008, 05:52 AM   #16
Vagitarian
 
rino1494's Avatar
 
Trade: site and utility contractor
Join Date: Jan 2006
Location: Dallas, PA
Posts: 3,096
Send a message via AIM to rino1494

Re: How Much Shrink Will You Get With Compaction


Quote:
Originally Posted by cdub View Post
The 35-40% shrink is from loose form, correct? I figured 30% but I think my cycle times are slow. I figured it from the longer end of the haul to allow for down time and other work interruptions. 5% volume change could easily get absorbed.
I appreciate the advice guys. Thanks.

Obvisously we don't work 100% for a full day. On avg. I figure that we work 50 min out of every hr. So, when figuring jobs, I figure how much material can be moved per hr and multiply that my .83 to get actual.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is online now  
Old 12-13-2008, 04:16 PM   #17
Midnight
 
Blas's Avatar
 
Trade: Excavating, Grading, Demolition, Underground Utilities
Join Date: Jan 2008
Location: Minnesota
Posts: 177

Re: How Much Shrink Will You Get With Compaction


I will post up a chart and some literature on the subject when I get around to scanning it. Probably tonight sometime.
__________________
"It is what it is"
Blas is offline  
Old 12-13-2008, 05:20 PM   #18
Member
 
cdub's Avatar
 
Trade: excavating
Join Date: Feb 2008
Location: KS
Posts: 65

Re: How Much Shrink Will You Get With Compaction


For my cycle times I figured the number per hour at maximum production then reduced that number by estimated dowmtime. I think that its a round about way to the same end.
__________________
"The beatings will continue until morale improves."
cdub is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Stranger than fiction (do houses shrink?) HANDM Remodeling 17 01-19-2009 02:40 PM
Compaction Factor for "Reference" Road Base Palisade Mike Concrete & Paving 2 05-22-2008 08:34 PM
Soil compaction joasis Commercial Construction 1 05-06-2008 09:30 AM
Excavator Mounted Compaction: Static roller vs vibratory roller or plate artherd Excavation & Site Work 5 07-02-2007 10:36 PM
Compaction Quiz denick Excavation & Site Work 8 04-17-2006 11:33 PM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?