Simple enough job when you have your earth works done,get some lean mix dry concrete and bed the first course of rock on this,then either stack the next layer on these and use some 1/2"-3/4" clean chip to fill in between the rocks and the clay,when you have attained your height haunch the last row with concrete to 3/4 way up the rock so you can cover it with topsoil,then point the front face if required.
The reason chip aggregate is used is that it is self compacting and allows the irregular faces of the rip rock to bed in safely and take the load of the top layer of stones so the whole structure is self supporting.