I'm getting ready to build some store and lock buildings. I got a bid for the excavation that seems really high. I'm hoping the bid is overkill and I can cut it back from what the bidder is proposing. Does anyone have an idea of pricing for the following. I have approx 240,000 sq feet of basically flat level land I'm going to build these storage buildings on. So I need an idea of what the costs would be for excavating, gravel ,and drainage systems installation if it's even neccessary. Do I have to dig down or can I just build up? Do I need a drainage system or can I just do drywells? How much and what type of gravel base do I need?
Thanks, I'll tell you what the bid is after I hear some comments.

smitty58 is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 03-17-2006, 10:03 PM   #2
Pro
 
jmic's Avatar
Trade: manager of excavation division
 
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660
You need to price something like this off of a site plan , way to much specific information needed to even come close.
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline   Reply With Quote
Old 03-18-2006, 06:26 AM   #3
Pro
 
jmic's Avatar
Trade: manager of excavation division
 
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660
Smitty,
So you have 5+ acres, how many sq. of buildings, and what are their configuration on the property? I'd imagine you have to do frost walls for all these buildings, anything special called out for the slab preps? How about drainage, any involved? Does it go into detention on site or into town / city system ( doutfull ) You must have all the other utilities going to an office somewhere on the grounds. What are the ground conditions there ( soil types )? There must be a enormus amount of process / gravel to be imported for driveways / parking in between the buildings. Unfortunatly earthwork pricing always seems high to anyone not in the field, mostly just because it's sub surface and not something you can really touch and see on a day to day basis. Sounds like a interesting project, please keep us informed of your progress as you move along with it. Good- Luck with it.
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline   Reply With Quote
Old 03-18-2006, 06:43 AM   #4
Custom Builder
 
Glasshousebltr's Avatar
Trade: From dirt to ridge vent
 
Join Date: Feb 2004
Location: South Central Illinois
Posts: 4,405
Send a message via AIM to Glasshousebltr Send a message via Yahoo to Glasshousebltr
Yes indeed jmic, that sounds like an interesting project. Going to need a lot more input for sure.

Bob
__________________
Bob
Glasshousebltr is offline   Reply With Quote
Old 03-18-2006, 11:45 PM   #5
Member
Trade: carpenter
 
Join Date: Nov 2005
Location: SW Ohio
Posts: 66
The plans call for a retention area on site at the back of the property. There will be 7 buildings (30 x 300 each) ,blacktop everywhere. The property is not rectangular but rather triangular ,so it isn't exactly 5 acres. There is a house on the property we are converting into office space. We are planning on the mechanicals being in one unit of the store and locks. The plans have a 12" drain pipe with collection basins at each end of the buildings. Is this really neccessary? Can we just do drywells? I don't know what the soil type is ,but it used to be a farm and it is flat as a pancake. The bidder figured taking 12" off and then building it back up with 8" of slag and then concrete/asphalt. Do we really need to take 12" off the top? Can't we just level it out and build it up from there? I'm sure you have figured out I know very little about excavation ,so any advice is much appreciated. I'm building the buildings and installing the fencing. It is a large project ,but will be done in 3 phases over a couple of years. The bid we got for excavation in including installing the drainage system is $244,000 which to me seems very high ,but again I have know idea about excavation.
smitty58 is offline   Reply With Quote
Old 03-19-2006, 12:58 AM   #6
Custom Builder
 
Glasshousebltr's Avatar
Trade: From dirt to ridge vent
 
Join Date: Feb 2004
Location: South Central Illinois
Posts: 4,405
Send a message via AIM to Glasshousebltr Send a message via Yahoo to Glasshousebltr
Was it the engineer that called for the cut?

If it used to be farmland, there's a good chance it has a hell of build up of organic topsoil. If so, and you deside to build up without the cut, your in for a hell of a ride. You'll get more movement out of your paved passage than 10 Iraqi insurgents with an incomming cruise missile.

Bob
__________________
Bob

Last edited by Glasshousebltr; 03-19-2006 at 01:05 AM.
Glasshousebltr is offline   Reply With Quote
Old 03-19-2006, 09:01 AM   #7
Pro
 
jmic's Avatar
Trade: manager of excavation division
 
Join Date: Dec 2005
Location: danbury,ct.
Posts: 3,660
Quote:
Originally Posted by smitty58
The plans call for a retention area on site at the back of the property. There will be 7 buildings (30 x 300 each) ,blacktop everywhere. The property is not rectangular but rather triangular ,so it isn't exactly 5 acres. There is a house on the property we are converting into office space. We are planning on the mechanicals being in one unit of the store and locks. The plans have a 12" drain pipe with collection basins at each end of the buildings. Is this really neccessary? Can we just do drywells? I don't know what the soil type is ,but it used to be a farm and it is flat as a pancake. The bidder figured taking 12" off and then building it back up with 8" of slag and then concrete/asphalt. Do we really need to take 12" off the top? Can't we just level it out and build it up from there? I'm sure you have figured out I know very little about excavation ,so any advice is much appreciated. I'm building the buildings and installing the fencing. It is a large project ,but will be done in 3 phases over a couple of years. The bid we got for excavation in including installing the drainage system is $244,000 which to me seems very high ,but again I have know idea about excavation.
Smitty,
Bob is right, you must have topsoil up the wazoo. Around here that would be a goldmine in itself, are you letting the Ex. contractor to take this material? Is he charging you to haul it away, or giving you a credit for it, all things to consider. If it was me I'de push it up in a corner, get a screener and sell it off the property, but again not sure of the market there for it. As far as the drainage IMO the best way is with c.b.'s and the 12" pipe, you're going to have a tremendous amount of water from all the roofs and blacktop surface's, it just makes sense to collect it and get it away into the detention area away from the building areas. I've seen C.b.'s set over drywells once the crushed stone see's any amount of silt they will start failing, then you have real problems on your hands, again you have way to much water shed to consider that kind of system IMO. I'm not familiar with slag.....must be what we would call a process, ( machine made material ) Someone please inform me if I'm incorrect. Well I have to get a few things done around the house, later!
__________________
___"Remember You Never Get A Second Chance To Make A First Impression"______________________
Joe
jmic is offline   Reply With Quote
Old 03-19-2006, 09:37 AM   #8
Pro
 
ruskent's Avatar
Trade: Outdoor D/B
 
Join Date: Jun 2005
Posts: 1,846
Seems like someone didn't do a good business plan with estimates of construction cost.
ruskent is offline   Reply With Quote
Old 03-19-2006, 03:54 PM   #9
Pro
 
jojo's Avatar
Trade: excavating
 
Join Date: Jan 2006
Location: lancaster co. Pa.
Posts: 101
Why not get a couple more estimates,,that just might tell you if the first guy is in the ball park,,,,
jojo is offline   Reply With Quote
Old 03-19-2006, 04:02 PM   #10
Pro
Trade: excavating / concrete / masonry
 
Join Date: Feb 2006
Location: NW, CT
Posts: 2,376
I second JoJo's thoughts.

Nick
denick is offline   Reply With Quote
Old 03-19-2006, 07:22 PM   #11
Vagitarian
 
rino1494's Avatar
Trade: site and utility contractor
 
Join Date: Jan 2006
Location: Dallas, PA
Posts: 2,437
Send a message via AIM to rino1494
Seems pretty cheap to me. I just bid a 12,000 sq ft building with 6,000 yds of dirt to move, detention basin, curbs, catch basins and storm drains, 6" downspout drains, dig footers, stone sub base under pad and modified stone sub base for under asphalt for $225,000.

Oh, also there was a 6" sewer lateral with a ductile iron creek crossing.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH

Last edited by rino1494; 03-19-2006 at 07:25 PM.
rino1494 is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Wilsonart Tap N Lock KITKAT Flooring 1 03-22-2004 08:40 PM


Top of Page | View New Posts


All times are GMT -5. The time now is 03:21 AM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC