Estimate Question

 
Thread Tools Search this Thread Display Modes
Old 03-15-2009, 03:26 PM   #1
New Guy
 
kubotaman333's Avatar
 
Trade: excavating
Join Date: Feb 2006
Posts: 23

Estimate Question


Could any one offer me an estimate on how much 6 inch rip rap I would need to do a rip rap ditch (6 feet wide, 20 inches deep V'd from the middle up and 450 feet long). Any help is appreciated thanks.

kubotaman333 is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 03-15-2009, 06:07 PM   #2
Pro
 
dayexco's Avatar
 
Trade: entrepreneur of excavating expertise
Join Date: Mar 2006
Posts: 2,604

Re: Estimate Question


you've got your dimensions already, rest should be simple math?
__________________
someday, i'll be as patient as Nick.
dayexco is offline  
Old 03-15-2009, 09:22 PM   #3
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: Estimate Question


70 cubic yards........If I were bidding, I would up it at least one load to 80 cubic yards. Am I the winner
cexcavation is offline  
The Following User Says Thank You to cexcavation For This Useful Post:
kubotaman333 (03-15-2009)
Old 03-16-2009, 07:50 AM   #4
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276

Re: Estimate Question


You might want to check your numbers C.

6 X 1.75 X 450 = 10.5

10.5 X 450 = 4,725

4,725 / 27 = 175

Only about 100 cubic yards off. And in reality it could be more depending on the actual profile of the 6' wide ditch.

Kubotaman, it is simple volume calculation, length X width X depth.
__________________
Tom

www.gebcon.com
tgeb is offline  
Old 03-16-2009, 08:19 AM   #5
Pro
 
1mancrew's Avatar
 
Trade: Remodeling
Join Date: Nov 2008
Location: Ohio
Posts: 201

Re: Estimate Question


6' wide ditch - 20" deep
When drawn out - each side is 3.5' from top of ditch to bottem center
2 sides - 7' x .5' (6" rip rap) = 3.5'
3.5' x 450' long = 1575 cu. ft.
1575 cu. ft. = 1575/27 = 58.33 cu. yd.
Bid 70 and if it only takes 60 = take your guys out to lunch =
Of couse you can always ask the aggregate supplier and they will tell you how much you need.
__________________
www.KirbyCustomHomes.com

Last edited by 1mancrew; 03-16-2009 at 08:23 AM.
1mancrew is offline  
The Following User Says Thank You to 1mancrew For This Useful Post:
kubotaman333 (03-16-2009)
Old 03-16-2009, 08:33 AM   #6
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276

Re: Estimate Question


Ohh, Maybe I miss understand. It does not get 20" of rip rap?

Quote:
I would need to do a rip rap ditch (6 feet wide, 20 inches deep
When he said 20" deep, I took that as the depth of the stone.

Kubotaman.....can you clarify?


Somebody help me, I can't use the internet with out pictures.
__________________
Tom

www.gebcon.com
tgeb is offline  
Old 03-16-2009, 08:34 AM   #7
Professional Instigator
 
rbsremodeling's Avatar
 
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872

Re: Estimate Question


I'd just sub it to that Tgeb guy his math skills seem better than yours. Seem like that would make life easier for you.
__________________


Last edited by rbsremodeling; 03-16-2009 at 08:34 AM. Reason: take it back he seems to be waffling on his math skills
rbsremodeling is offline  
Old 03-16-2009, 08:39 AM   #8
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276

Re: Estimate Question


My math is good......it's my comprehension that is a little fuzzy.
__________________
Tom

www.gebcon.com
tgeb is offline  
Old 03-16-2009, 11:22 AM   #9
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: Estimate Question


Quote:
Originally Posted by tgeb View Post
You might want to check your numbers C.

6 X 1.75 X 450 = 10.5

10.5 X 450 = 4,725

4,725 / 27 = 175

Only about 100 cubic yards off. And in reality it could be more depending on the actual profile of the 6' wide ditch.

Kubotaman, it is simple volume calculation, length X width X depth.
I think my numbers are good....."lining" vs. "filling" as well as "V'd out"is where the discrepancy lies. Also, I always figure a 15% into my initial numbers to account for "irregularities", compaction, etc. That is where the initial "safe" number comes from. Then if it is a bid situation, I usually factor in an extra load or two depending on the size of the job. This "extra" load(s) accounts for the "extras" that people often expect in a bid situation........homeowners are good at the bait and switch maneuver when it comes to "undefined" projects......not always, but often so my advice it to plan for it and then do it even if they don't end up asking for it. This has seemed to work better for me than trying to cut everything close and be stuck doing the bare minimum work. To fill the ditch without any compaction, irregularites figured in comes out to 83yds using area of triangles(ends up being a rectangle since two triangles together eliminate the need for the divisor of 2. My equation for a fill looks something like this: [ (36" * 20")/ 144] * 450=2250cu.ft. Then 2250 cu. ft divided by 27cu. ft. gives 83.33 cu. yds. Am I still the winner!!!!

Last edited by cexcavation; 03-16-2009 at 11:30 AM.
cexcavation is offline  
The Following User Says Thank You to cexcavation For This Useful Post:
kubotaman333 (03-16-2009)
Old 03-16-2009, 11:36 AM   #10
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276

Re: Estimate Question


I would agree that your calcs were good based on 1 layer of stone rip rap with some extra for loss/waste.

I simply thought the way Kubotaman worded the question, he needed 20" thick not 6" thick stone lined channel.

We just looked at the original problem differently. No offense intended C.
__________________
Tom

www.gebcon.com
tgeb is offline  
Old 03-16-2009, 12:29 PM   #11
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: Estimate Question


Quote:
Originally Posted by tgeb View Post
I would agree that your calcs were good based on 1 layer of stone rip rap with some extra for loss/waste.

I simply thought the way Kubotaman worded the question, he needed 20" thick not 6" thick stone lined channel.

We just looked at the original problem differently. No offense intended C.

No offense taken TGEB This is a perfect example of how us contractors are at the mercy of wording and interpretation when it comes to bidding without plans. This is why homeowner bids are often so far across the board.
cexcavation is offline  
Old 03-16-2009, 06:04 PM   #12
New Guy
 
kubotaman333's Avatar
 
Trade: excavating
Join Date: Feb 2006
Posts: 23

Re: Estimate Question


sorry for the confusion and thanks for all the input. Bye the way it was just a layer not filled.
kubotaman333 is offline  
Old 03-16-2009, 09:27 PM   #13
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: Estimate Question


Quote:
Originally Posted by kubotaman333 View Post
sorry for the confusion and thanks for all the input. Bye the way it was just a layer not filled.
I say the only confusion was probably due to TGEB working too many long days in a row!!! Your description was quite clear to me, but you never know how the next guy might read something. I have bid projects where the "winner" bids a price that doesn't even cover the required materials according to what I bid. I can only assume someone misinterpreted something somewhere.........it happens.
cexcavation is offline  
Old 03-16-2009, 09:45 PM   #14
Contractor
 
tgeb's Avatar
 
Trade: Excavation, Foundation, Concrete
Join Date: Feb 2006
Location: Maryland
Posts: 3,276

Re: Estimate Question


Yep! It's all my fault.........but I did have plenty of budget for material.
__________________
Tom

www.gebcon.com
tgeb is offline  
Old 03-17-2009, 12:23 AM   #15
Pro
 
cexcavation's Avatar
 
Trade: Excavation Contractor
Join Date: Apr 2008
Posts: 374

Re: Estimate Question


Quote:
Originally Posted by tgeb View Post
Yep! It's all my fault.........but I did have plenty of budget for material.
I would love bidding against you if you pad your bids that much!!!! I would even recommend you to potential customers just to make my price look that much more appealing.....Just kiddin
cexcavation is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Question from lawyer trying to help contractor scp Business 52 02-25-2011 01:23 AM
Question for GC re: rough/final cleans britanie General Discussion 6 06-07-2009 07:42 PM
Contractor law question for california contractors saucedo80 Painting & Finish Work 7 04-18-2009 01:07 PM
Sewer Infrastructure Question ABLE1 Excavation & Site Work 20 05-28-2008 11:05 AM
Estimate question selrox Drywall 7 07-31-2006 11:45 PM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?