Concrete footings

Hey guys
quick question for you, How long should you wait to start building on new footings.

Clay soil, southern california 12"x2'

thanks for your help.

primetimeon is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 08-20-2009, 09:13 PM   #2
Chief outhouse engineer
 
dakzaag's Avatar
Trade: mason
 
Join Date: Jan 2009
Location: NW Indiana
Posts: 484
Concrete cures for about 28 days.
__________________
D K & Sons
The maintenance schedule for brick
1. Stand back and say "man that looks nice!"
2. Repeat as often as needed.
dakzaag is offline   Reply With Quote
Old 08-21-2009, 07:08 AM   #3
Pro
 
cleveman's Avatar
Trade: custom home building
 
Join Date: Dec 2007
Location: Central Iowa
Posts: 1,155
You can start right after you strip the forms.
cleveman is offline   Reply With Quote
Old 08-21-2009, 09:09 AM   #4
Thom
 
thom's Avatar
Trade: General Contractor/Homebuilder
 
Join Date: Nov 2006
Location: Albuquerque NM
Posts: 2,188
I've seen guys start within a couple hours of the pour.

It's really a function of time and stress. If you are setting block, you can start almost right away. If you need to drive a truck over it, you might want to wait a little longer.
thom is online now   Reply With Quote
Old 08-21-2009, 10:59 AM   #5
Pro
 
concretemasonry's Avatar
Trade: Masonry consultant
 
Join Date: Nov 2006
Location: Minnesota
Posts: 1,620
The 28 days is just an old wife's tale. Concrete actually cures for years. It cures the fastest in the first couple of days and slower later on. The 28 days only refers to one of the time dates (7, 14, 28 and 56 days) for cylinders to check the concrete mix under lab curing conditions.

Depending on the load, loads can be placed on it almost immediately.

I frequently see the first course or two of block for a basement laid the afternoon of the pour. This is done to make sure any rain does not swamp the basement footings and depositing dirt/mud that can take a long time (and money) to clean when the discovered the next day. Anything in an excavation can get very messy and unworkable and delay anything.

A typical basement footing or trench type footing has very little load on it until the structure is up and backfilled. If it is a trench type footing with not unbalanced soil, backfilling improves the curing conditions.
__________________
Dick

Engineer, designer and consultant recently active internationally on construction and design in about 35 countries.
concretemasonry is offline   Reply With Quote
Old 08-21-2009, 02:52 PM   #6
Twisted Cameron
Trade: Concrete, Metal buildings
 
Join Date: May 2009
Location: Yorkville Il
Posts: 172
Quote:
Originally Posted by concretemasonry View Post
The 28 days is just an old wife's tale. Concrete actually cures for years. It cures the fastest in the first couple of days and slower later on. The 28 days only refers to one of the time dates (7, 14, 28 and 56 days) for cylinders to check the concrete mix under lab curing conditions.

Depending on the load, loads can be placed on it almost immediately.

I frequently see the first course or two of block for a basement laid the afternoon of the pour. This is done to make sure any rain does not swamp the basement footings and depositing dirt/mud that can take a long time (and money) to clean when the discovered the next day. Anything in an excavation can get very messy and unworkable and delay anything.

A typical basement footing or trench type footing has very little load on it until the structure is up and backfilled. If it is a trench type footing with not unbalanced soil, backfilling improves the curing conditions.
+1
scrapecc is offline   Reply With Quote
Old 08-21-2009, 04:13 PM   #7
Chief outhouse engineer
 
dakzaag's Avatar
Trade: mason
 
Join Date: Jan 2009
Location: NW Indiana
Posts: 484
A GC who wants to know how long til he can put stress on a footer.

You might be a lot of things, but a primetime GC your not.

Sorry, but I learned that about 2 weeks into my first construction job, and I was an unskilled laborer at the time.

Still considered unskilled by some...
__________________
D K & Sons
The maintenance schedule for brick
1. Stand back and say "man that looks nice!"
2. Repeat as often as needed.
dakzaag is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Concrete Company delivered junk concrete. How best to pursue? marcomjl Concrete & Paving 39 09-19-2009 09:08 AM
4x4 posts in concrete vs. saddles Strongarm Decks & Fencing 20 08-31-2009 09:41 PM
Advice - concrete Pool Deck coping ejleonard Masonry 4 06-17-2008 04:18 PM
concrete footings ol blueeyes Framing 9 03-02-2008 09:57 PM


Top of Page | View New Posts


All times are GMT -5. The time now is 02:29 PM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC