alittle intro to my question hammer work

My father and i run very small only two man operation excavation company, weve a t-800 12yd truck, 580 superm, 763 bobcat and jcb mini x. we also rent a hire bigger equipment and trucks ass needed

we used to do residiential houseing clearance this includes digging the clearance along with all utilities and concrete prepp. this market is now falln flat on its face, weve gone from 10-20 houses a months to 6 in the last year.

but weve picked up few custom hom builders who do big homes weve done couple 10000 square foot clearances this year and a few dailight basements on hill sides. these are good jobs

to my question. weve been doing more and more and larger comercial jobs. we do all the trenching for plumbing company. were all the digging on the planned to be biggest idaho highschool. weve so far loogged over 2000ft of trench on this job.

ok dang it to the question. weve run into rock on this job and have rented a super m hoe with hammer. weve hammerd about 500 ft of trench in the last week.

what im wondering is how much the price goes up for backhoe with ahmmer or if just standerd hourly raters apply. normaly our backhoe makes 75-90 an hour, or 5 dollars a foot of trench. this included backfill and material haul off. bedding sand isnt included

i guess ther you have it, how much to hammer?

thanks for your time

Evan

Evan03 is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 09-05-2009, 11:37 PM   #2
Pro
 
dayexco's Avatar
Trade: entrepreneur of excavating expertise
 
Join Date: Mar 2006
Posts: 1,645
tree fiddy
__________________
When the student is ready, the teacher will appear
[b]Do you teach the best what you need to learn the most?[b]
a few pics of our operation and equipment at http://s72.photobucket.com/albums/i182/dayexco/
dayexco is offline   Reply With Quote
Old 09-06-2009, 08:30 AM   #3
Registered User
Trade: excavation , comercial residential
 
Join Date: Sep 2009
Posts: 8
350 an hour, you gota be kidding, what area is that in? southdakota

thanks for the reply
Evan03 is offline   Reply With Quote
Old 09-06-2009, 11:11 AM   #4
Contractor
 
tgeb's Avatar
Trade: Excavation, Foundation, Concrete
 
Join Date: Feb 2006
Location: Maryland
Posts: 2,023
Evan, I would add the additional cost of the daily hammer rental rate plus some $ for overhead and profit.

Divide by 8, add that to your hourly rate. I might even add more $ for having to listen to that thing all day.
__________________
Tom

www.gebcon.com
tgeb is offline   Reply With Quote
Old 09-06-2009, 11:50 AM   #5
New Guy
Trade: site work/paving
 
Join Date: Jan 2009
Location: New Jersey
Posts: 24
We have a 1996 ford 575D with a 1000lb hammer on it (a little big for the machine). We only do full day rentals with our operator for $1250.00 per day. We move the machine our selves and the day is from 7:30 till 4:00.
Gnella is offline   Reply With Quote
Old 09-06-2009, 07:06 PM   #6
Dig with BIG TOYS
Trade: Landscape, Masonry, Site Prep... the grunt work
 
Join Date: Jun 2009
Posts: 78
Quote:
Originally Posted by tgeb View Post
Evan, I would add the additional cost of the daily hammer rental rate plus some $ for overhead and profit.

Divide by 8, add that to your hourly rate. I might even add more $ for having to listen to that thing all day.
yeah hammering sucks... but its stupid for you to have to eat the rental of the hammer... that cost deffinitley needs to be passed on. Plus for a little extra for having to abuse your machine with that beast... and for your slight loss of sanity...
digdeep516 is offline   Reply With Quote
Old 09-06-2009, 11:23 PM   #7
Registered User
Trade: excavation , comercial residential
 
Join Date: Sep 2009
Posts: 8
we rented backhoe with hammer on it we had both hoes running the rental hammering and ours had rock bucket dragn rock out of the trenches.


rental is 300 a day.

thanks for the replys

ohhhhh we set our case up with wobble sticks and the rental has case controls. i danged near cant run the case controls they drive me crazy specialy the foot pedals
Evan03 is offline   Reply With Quote
Old 09-07-2009, 08:55 AM   #8
Registered User
Trade: site contractor
 
Join Date: Jan 2009
Posts: 4
I charge 285.00hr for a 3500lb hammer on a JD 590 and 365hr for a 5000lb hammer on a JD 892 there not cheap to rebuild.
Heimy is offline   Reply With Quote
Old 09-07-2009, 09:14 AM   #9
Pro
Trade: excavating / concrete / masonry
 
Join Date: Feb 2006
Location: NW, CT
Posts: 2,359
Most company's I know get 2X's to 2.5X's the normal machine hourly rate for a machine with a hammer on it. Some charge a point wear charge on top of that.
__________________
Nick

"Every day I remind myself that my inner and outer life are based on the labors of other men, living and dead, and that I must exert myself in order to give in the same measure as I have received and am still receiving" Albert Einstein
denick is offline   Reply With Quote
Old 09-07-2009, 09:46 AM   #10
Registered User
Trade: excavation , comercial residential
 
Join Date: Sep 2009
Posts: 8
thanks guys for the replies.

i think im gona figure on the 2 times normal rates with the 300 dollar rental tacked on top of that
Evan03 is offline   Reply With Quote
Old 09-07-2009, 05:50 PM   #11
Pro
 
Vinny's Avatar
Trade: Asphalt Paving, Masonry
 
Join Date: Jul 2007
Location: Fairfield County Connecticut
Posts: 573
Quote:
Originally Posted by Heimy View Post
I charge 285.00hr for a 3500lb hammer on a JD 590 and 365hr for a 5000lb hammer on a JD 892 there not cheap to rebuild.
You got that right
__________________
Roccies Asphalt Paving
The Right Way Driveway Company
If you say you cant, your a loser. If you say you wont, your a quiter. Which one do you want to be?
Vinny is offline   Reply With Quote
Old 09-07-2009, 09:31 PM   #12
Pro
Trade: underground
 
Join Date: Oct 2004
Posts: 3,045
Exclamation

Quote:
Originally Posted by Evan03 View Post
weve hammerd about 500 ft of trench in the last week....how much for backhoe with ahmmer...normaly our backhoe makes 75-90 an hour, or 5 dollars a foot of trench...this included backfill and material haul off....how much to hammer?
40 hours x $75-$90 = weekly rate

weekly rate divided by 500 ft of hammered trench = feetly rate for hammered trench

feetly rate x feet divided by hours spent hammering = hourly rate

FYI - at $5 a foot of trench including backfill and haul off you should have no shortage of work.
__________________
Quote:
That's the way that the world goes 'round, you're up one day and the next you're down.
It's a half an inch of water and you think you're gonna drown, that's the way that the world goes 'round.
PipeGuy is offline   Reply With Quote
Old 10-04-2009, 01:37 PM   #13
Registered User
Trade: excavation , comercial residential
 
Join Date: Sep 2009
Posts: 8
weve been busy and lucky to be working at all last winter almost put us under all we did from november till spring was plow pking lots. work is already slowing so ive been chasen bigger lots and started working on on 4 ft plow wing for the backoe. well then be out plowing loaders that run around town. i fabbed wing for the skidsteer last years and can out plw the backhoe and skidsteers that are running around town with 6k plow blades those guys are nuts foor spendn that much on a peice of seasonal equipment.
its going to be scary if the snow doesnt fly atleast enough to make equipment payments i dont know if well make it

5- 6.50 is the going rate inside jobs are charged by the hour

we are wrapping up a trenching job on school being built job has been about 2.5 months long and will run past 3000 ft of trench
Evan03 is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
High Horses and "Ironing Boards" for Detail Work basswood Finish Carpentry 24 07-25-2009 01:00 PM
PITA customer telling me what to charge knothead Business 11 07-16-2009 05:57 PM
Help me chose a new hammer! CJ21 Tools & Equipment 17 05-06-2009 12:28 PM
Question - Requirements For Contractor To Work In Canada firemike Contractor Licensing 2 01-19-2009 08:01 PM




Top of Page | View New Posts


All times are GMT -5. The time now is 12:38 AM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC