Advice Sought please

Good evening all,
I am in need of some advice. I am working on a small commercial project at the moment and have had a ridiculous run of bad luck with staff. I mobilized on Tuesday and started to install silt fence after a meeting, had to take wed off due to state testing. Back at it on Thursday after having a laborer go out with a blown knee, and had 2 operators quit on wed evening. I am down to me and one laborer until I rehire, this project has a 4 month completion deadline and the site super is freaking out (understandable) I am a sub. I have called in a couple of favors for tomorrow, but realistically am looking at the better part of a week until I am back to staffed if I can find some people, It is fall push. As a business owner I am wondering what to do, as a person I am a stubborn MF but that is not always a good thing. I want to try to hunker down and get it done however it is possible, but murphy is already starting to get me, just paid to haul out 25 loads of topsoil because of some trees that the state likes. As a GC would you want to hear early on that things are going to drag on, or no.
What I have to do:
Basement dig, 70x 100 5ft avg cut 1 ft of dewatering, 46 7x7 piers inside
Sink 10gal water tank
Water, sewer and lights
build a road(150ft)
some sidewalks and slabs
firetruck turnaround

Anybody need some work?

what would you do, I have 5 resumes I have called on today, have spoken to the GC about my staffing problems and have called everybody I know asking for help. I dont know what else to do.
Thanks,
John

guyute65045 is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 10-02-2009, 09:56 PM   #2
Registered User
Trade: General Engineering Contractor - CA
 
Join Date: Oct 2009
Posts: 4
I would stop giving him information that he can use against you at a later date.

Did you provide the GC with a schedule for your scope of work? Also, did the GC provide you with a schedule that incorporated your schedule? Or, did the GC provide you with a schedule that shows your scope and durations?

Two tactics I use to drive a schedule (1) I ask the sub to provide me with his durations and (2) his manpower. If I suspect that the sub is slowing down, I then have a reference point that tells me if he is lacking men or just taking alot longer to finish the job.

If you don't have a baseline schedule, I would continue business as usual while you work out your man power issues. You may want to sit down and break out a schedule for him (and yourself) to better understand how you plan to man the job and in what sequence. See if you can finish an area for him to get the next sub in and that way there are no delays to the critical path schedule.
jhlwstdnt is offline   Reply With Quote
The Following 2 Users Say Thank You to jhlwstdnt For This Useful Post:
backhoe1 (10-02-2009), guyute65045 (10-03-2009)
Old 10-04-2009, 01:44 PM   #3
Registered User
Trade: excavation , comercial residential
 
Join Date: Sep 2009
Posts: 8
my father and i have no employes, when were busy its 10-14 hour days lunch on the run and working weekends. im in good with gravel pit we get materials from and we hire there trucks from time to time and im alloud to run alone on weekends to get materails hauled on saterday n ssundays.

cant forget the all nighters and fights with the wife because i get home and am out in the garage all night wrenchn on equipment so we can work the next day.

you can get it done.
Evan03 is offline   Reply With Quote
Old 10-04-2009, 05:31 PM   #4
Vagitarian
 
rino1494's Avatar
Trade: site and utility contractor
 
Join Date: Jan 2006
Location: Dallas, PA
Posts: 2,326
Send a message via AIM to rino1494
If you were closer, I'd help you out. Things are slow and there are alot of qualified ppl out of work. Ask around and bring someone on.

You gotta look at the reason that 2 guys quit also. Don't forget, please don't cry to the GC. They do not wanna hear it.
__________________
Life is hard. It is harder when you are stupid

Uncle Sam wants YOU....to speak ENGLISH
rino1494 is offline   Reply With Quote
Old 10-04-2009, 06:17 PM   #5
Pro
 
dayexco's Avatar
Trade: entrepreneur of excavating expertise
 
Join Date: Mar 2006
Posts: 1,645
Quote:
Originally Posted by rino1494 View Post
Don't forget, please don't cry to the GC. They do not wanna hear it.
amen
__________________
When the student is ready, the teacher will appear
[b]Do you teach the best what you need to learn the most?[b]
a few pics of our operation and equipment at http://s72.photobucket.com/albums/i182/dayexco/
dayexco is offline   Reply With Quote
Old 10-04-2009, 08:16 PM   #6
Contractor
 
tgeb's Avatar
Trade: Excavation, Foundation, Concrete
 
Join Date: Feb 2006
Location: Maryland
Posts: 2,023
Concentrate on one task at a time. Don't let the full scope of the project overwhelm you.

You are not going to do it all this week anyway. Get done what you can, put the word out that your looking to hire.

Maybe you can get the dig completed and sub out the concrete work while working on the roadway, water lines, sewer pipe, what ever. There are ways to get this done.

Take a breath..... think it through, you can handle it.

Get 'er done! Make some $$.
__________________
Tom

www.gebcon.com
tgeb is offline   Reply With Quote
Old 10-04-2009, 08:21 PM   #7
Pro
 
dayexco's Avatar
Trade: entrepreneur of excavating expertise
 
Join Date: Mar 2006
Posts: 1,645
tom, i gotta say, and i truly appreciate your optimism
__________________
When the student is ready, the teacher will appear
[b]Do you teach the best what you need to learn the most?[b]
a few pics of our operation and equipment at http://s72.photobucket.com/albums/i182/dayexco/
dayexco is offline   Reply With Quote
Old 10-04-2009, 08:41 PM   #8
Contractor
 
tgeb's Avatar
Trade: Excavation, Foundation, Concrete
 
Join Date: Feb 2006
Location: Maryland
Posts: 2,023
Quote:
Originally Posted by dayexco View Post
tom, i gotta say, and i truly appreciate your optimism
Some days, Gene, I think we are our own worst enemy. We think our asses are whipped and then make it so.

I have completed plenty of tasks/projects that one man could not do. But the tasks are done, and I'm still here.

I love a challenge....
__________________
Tom

www.gebcon.com
tgeb is offline   Reply With Quote
Old 10-05-2009, 05:28 PM   #9
Member
Trade: septic installer, site work
 
Join Date: Nov 2006
Location: Vermont
Posts: 70
Quote:
Originally Posted by tgeb View Post
Concentrate on one task at a time. Don't let the full scope of the project overwhelm you.

You are not going to do it all this week anyway. Get done what you can, put the word out that your looking to hire.

Maybe you can get the dig completed and sub out the concrete work while working on the roadway, water lines, sewer pipe, what ever. There are ways to get this done.

Take a breath..... think it through, you can handle it.

Get 'er done! Make some $$.
Thanks for talking me off the edge of the roof, I needed that, in fact I needed all the advice. I had all my ducks in a row, and one by one they started to fall apart. I am getting back on track, got 3 people back, GC is still pushing the time line, but I don't mind working hard as long as I am not trying to do the work of 3 alone. Now I need to get my native to pass a sieve and I can start to see some things go right fora change.
guyute65045 is offline   Reply With Quote
Old 10-05-2009, 07:07 PM   #10
Contractor
 
tgeb's Avatar
Trade: Excavation, Foundation, Concrete
 
Join Date: Feb 2006
Location: Maryland
Posts: 2,023
You'll get it all worked out John.

Don't let the GC pushing get you too worked up.

A friend of mine once said he told the GC when asked "How soon will you be done?" He responded, "It will not take me as long to finish this, as it will for you to sign a check to pay for all this work."

Their job is to push don't let em get you stressed over it.
__________________
Tom

www.gebcon.com
tgeb is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Advice wanted for starting a construction firm P.J. Construction 34 10-09-2009 01:51 PM
Advice on a New Hire CookeCarpentry Business 69 08-03-2009 10:06 PM
Need advice on Greek Revival mikeremote Historical Restoration 3 05-12-2009 10:21 PM
Advice for starting Career as Operating Engineer TrendTherapy Excavation & Site Work 0 02-13-2009 11:07 AM
Professional Salesmen I need your advice. Grumpy Marketing & Sales 43 12-23-2008 07:31 PM




Top of Page | View New Posts


All times are GMT -5. The time now is 04:45 AM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC