#1 |
|
DGR,IABD
Trade: Electrical; Commercial and Residential Service
Join Date: Mar 2005
Location: Central PA
Posts: 9,680
|
Question For GC's
On remodeling T&M jobs where the electrician might discover something that can't be left alone, do you prefer that the electrician to do more than what you originally spoke about to get the project to pass inspection? ...or do you prefer that you talk about any of the electrician's "discoveries" on a case by case basis, even if there's really no choice?
|
|
|
|
|
|
#2 |
|
Remodeler
Trade: Remodeler
Join Date: Oct 2004
Location: Spring Hill, Florida
Posts: 820
|
Re: Question For GC's
By something that can't be left alone I take it you find something that is dangerous. It would be my responsibity to make this right. I would appreciate at least a phone call from the sub if this was going to be an expensive repair. But at the end of the day it must be made right. This all goes hand in hand with confidence in the sub.
|
|
|
|
|
|
#3 |
|
Pro
Trade: Residential Contractor
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,475
|
Re: Question For GC's
There is a clause in my contract that covers these eventualities. Everything MUST pass inspections.
Most of the time the modifications are minor and can be absorbed in the overall cost of the project. In the event that something major is discovered, the contract covers that. The owner is informed prior to initiating any work.
__________________
You can't solve you're problems with the same level of thinking that created the problems. Albert Einstein |
|
|
|
|
|
#4 |
|
Chief Toilet Mover
Trade: Bathroom Remodeling
Join Date: Apr 2004
Location: Littleton, Colorado
Posts: 14,078
|
Re: Question For GC's
I definitly want to know first, or the sub is probably risking spending his own money if it is outside of the scope of work discussed. However I wouldn't be involved with a T&M project with a sub unless it was the last resort anyways.
|
|
|
|
|
|
#5 |
|
General Contractor
Trade: General Contractor
Join Date: Oct 2003
Location: Montana - where I belong.
Posts: 1,035
|
Re: Question For GC's
Let me know first so we can at least explore options. Even if it is a no-brainer my first commitment is to the client - they should know 2 things. 1 - that something isn't right with their project and it will involve 2 - a change order in the amount of x.
|
|
|
|
|
|
#6 |
|
Pro
Trade: builder remodelor
Join Date: Apr 2005
Location: northeast
Posts: 378
|
Re: Question For GC's
I add an amount into my contracts to cover some extra work neccesary to properly complete project.A change order will be written when extras involve work excluded from or unrelated to original project.All work must pass inpections , be code compliant, and fixtures must be ul/csa listed new in box.
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Tight Space Stucco Question - Undershot between roof sections | CGofMP | Construction | 3 | 03-24-2009 09:10 AM |
| Question about bidding vinyl wallcovering | kanadaeh | Painting & Finish Work | 9 | 02-19-2009 05:29 PM |
| Basement Window Question | gregt848 | Windows, Siding and Doors | 9 | 07-26-2006 06:29 PM |
| Go to Page... |