Thread Tools | Search this Thread | Display Modes |
|
|
#1 |
|
Member
Trade: design / build defense contractor
Join Date: Feb 2009
Location: Hamden, CT
Posts: 90
|
Penetration At 2-hour Separation
we're building a 5b rated building, nursery school under offices. the nursery school has a 2-hour separation top / bottom and on all load bearing members. my electrician is telling me that its BX inside the 2-hour rated area. Does anyone know if these are BX home runs to the main panel or are we allowed to terminate at sub-panels just outside the 2-hour rated envelope and go with Romex from these sub-panels to the main? We're IBC.
|
|
|
|
|
|
#2 |
|
Service & Repairs
Trade: Electrician
Join Date: Dec 2006
Location: Rahway, New Jersey
Posts: 3,998
|
Re: Penetration At 2-hour Separation
BX to sub panels and romex back to the mains? What in God's green earth are you talking about?
Btw, what state is this in? |
|
|
|
|
|
#3 | |
|
Member
Trade: design / build defense contractor
Join Date: Feb 2009
Location: Hamden, CT
Posts: 90
|
Re: Penetration At 2-hour SeparationQuote:
my electrician has me running bx inside the 2-hour envelope. i don't want to run it to the main if we don't have to, its a large building. |
|
|
|
|
|
|
#4 |
|
DGR,IABD
Trade: Electrical; Commercial and Residential Service
Join Date: Mar 2005
Location: Central PA
Posts: 9,680
|
Re: Penetration At 2-hour Separation |
|
|
|
|
|
#5 |
|
Service & Repairs
Trade: Electrician
Join Date: Dec 2006
Location: Rahway, New Jersey
Posts: 3,998
|
Re: Penetration At 2-hour Separation
I guess you're going to have install some conduit from the MDP to a sub panel and tie your armored cables in there.
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| High Speed Cable & P.O.T. Separation? | redzthredz | Low Voltage | 11 | 12-01-2009 05:09 PM |
| Do you charge more per Hour if Homeowner is "helping"? | guyute65045 | Excavation & Site Work | 13 | 10-21-2008 09:24 PM |
| One hour fire rating for a truss | AlLockrem | Drywall | 2 | 09-18-2008 10:31 PM |
| Plywood w/one hour fire rating | fireguy | Commercial Construction | 8 | 09-18-2008 06:44 PM |
| Question about man hour rates | Dorman Painting | Painting & Finish Work | 9 | 05-03-2006 07:35 PM |
| Go to Page... |