Contractor Talk - Construction and Remodeling Site
CLICK HERE AND JOIN OUR COMMUNITY TODAY...IT'S FREE!
Go Back   Contractor Talk - Professional Construction and Remodeling Forum > Trade Talk > Drywall

Reply
 
Thread Tools Search this Thread Rate Thread Display Modes
Old 01-30-2009, 11:18 AM   #1
Profit is not dirty.
 
AARC Drywall's Avatar
Trade: Residential Drywall and Taping
 
Join Date: May 2008
Location: Prince George BC Canada
Posts: 306
Contracts...have a read.

Hey guys,

I have never used a contract..and now i will have to.. times are tight, and people seem to think that we as conrtactors have screw me writen on our forheads..
Would you have a look, and see if we missed something, or areas of adjustment.

Thanks, feel free to use if needed. I dont want to see anyone else get screwed, and if this helps, go for it.

http://www.aarcdrywall.com/AARCContract.html
J

__________________
Profit is NOT a dirty word....Cheap is....
AARC Drywall is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 01-30-2009, 12:07 PM   #2
Custom Stuff
 
Mike(VA)'s Avatar
Trade: General Contractor - Custom Renovations
 
Join Date: Jan 2008
Location: Manassas, VA
Posts: 846
Just a few comments: You should have a different contract for GC's and HO's.
Time and Completion:The work to be preformed by the Contractor pursuant to this agreement shall be commenced within ( ) days from this date or approximately on (dd/mm/yyyy) provided that the terms and conditions have been met. (see page 2)
You just need an estimated start and completion date, GT%C's spell out what could change the time.
Payment: Owner or Contractor agrees to pay AARC Drywall a total (cash/ Certified cheque) price of $ Down payment of $ (if required) Payment Schedule as follows (also see page 2)
Total amount of_____________ to be paid as follows:
x% deposit, x% at board install, (if needed for long install jobs), x% when complete, 7 days to pay.
Payment of 50% of above total amount may to be required once boarding is complete, if taping is required, contractor reserves the right to lien the property to secure funds, then commence with taping. Remainder of monies to be paid net 7 days from final invoice date. AARC Drywall reserves the right to ask for monies to cover materials, before boarding will commence.
Forget all this. Lien info goes in GT&C's, your deposit should at least get your materials covered.
Allowances:All Materials needed are included in the contract price. The contract price shall be adjusted upwards /downward based upon actual amounts needed rather than estimated amounts herein.
BIG RED FLAG! You estimate properly, there is no need to adjust up or down. You goof up, you eat it. That's how you learn. Allowances are amounts allocated to items of customer's choice. They spend more or less, but you have given them an idea of costs for those items. I don't think you need allowances for rocking.
At least its better than no contract at all. Last point, get Michael Stone's book on contracts called The Contractor's Legal Kit. About 90 bucks and you can use the material anyway you want.
__________________
__________________________________________________ ___________
You are not making progress unless someone is trying to get in your way. I will never give up!
Clifton, Great Falls, McLean, Fairfax Station, Manassas, Virginia Renovation Contractor
Mike(VA) is offline   Reply With Quote
Old 01-30-2009, 04:04 PM   #3
Drywall & Painting Pro
 
Sir Mixalot's Avatar
Trade: Hang, Finish, Texture, Repair, and Paint.
 
Join Date: Jan 2008
Location: East Central Florida
Posts: 720
I would never consider starting a job without a contract w/ a HO's or GC's signature. No matter how big or small the job is. Here's portion of one of my contracts.

[quote] All material is guaranteed to be as specified, and the above work to be completed in accordance with the drawings and specifications submitted. Payment terms to be negotiated and agreed upon by all parties prior to contract signing. Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. Workers Compensation and General Liability insurance policies will remain in effect on above work.
All work to be completed in a substantial workmanlike manner for the sum of: $3200.00
Payment to be made as follows: (30% after demo--40% after drywall has been installed---30% upon completion) [quote]
Sir Mixalot is offline   Reply With Quote
Old 01-31-2009, 02:00 AM   #4
Profit is not dirty.
 
AARC Drywall's Avatar
Trade: Residential Drywall and Taping
 
Join Date: May 2008
Location: Prince George BC Canada
Posts: 306
Thanks guys, really appriciate the input, and will make changes.
__________________
Profit is NOT a dirty word....Cheap is....
AARC Drywall is offline   Reply With Quote
Old 01-31-2009, 08:10 AM   #5
Contractor
Trade: Remodeling & Home Additions
 
Join Date: Sep 2006
Location: Delaware
Posts: 1,714
regarding the allowance portion-your steps in estimating should include an additional amount of slack-say 5-10% extra more material waste. the way it was worded sounds more like T&M with a fixed 'time'. I use allowances; for instance a HO choosing their own fixtures for a bathroom remodel may have an allowance of $500 for choosing a vanity top and faucet (materials only). If not used they get a credit, if cost is more than $500, the additional cost is added.
72chevy4x4 is offline   Reply With Quote
Old 02-04-2009, 12:14 PM   #6
Registered User
Trade: General
 
Join Date: Feb 2009
Posts: 6
Here is a couple of sample documents on the subject, you might want to consider:
Go to truebluecontractors.com website
Go to Articles
Go to Templates and forms

Sorry guys, I can't post links so far, so those who are interested might still want to check the sample documents at the specified location.
barack is offline   Reply With Quote
Old 02-04-2009, 07:10 PM   #7
Drywall & Painting Pro
 
Sir Mixalot's Avatar
Trade: Hang, Finish, Texture, Repair, and Paint.
 
Join Date: Jan 2008
Location: East Central Florida
Posts: 720
Welcome barack! Here's that link Templates & forms
Sir Mixalot is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Small towns & contracts furstclass General Discussion 16 01-30-2009 12:28 PM
Marked as Read? neolitic Site Help and Suggestions 5 01-15-2009 04:52 PM
How do I read the articles? Mike(VA) Site Help and Suggestions 6 01-14-2009 01:13 AM
Titles staying in boldface even after subject is read. Leo G Site Help and Suggestions 11 10-31-2008 11:17 PM
Importance of doing things by email and using contracts HellisLikeNewrk General Discussion 9 09-27-2008 05:37 PM


Top of Page | View New Posts


All times are GMT -5. The time now is 11:46 PM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC