Footing on Wet Clay

We started on my personal home this last week and hit water at 2ft in 40% of a 600 ft waterline dig. We moved a lot of dirt for the pad and had soft spots at one end. Now the dozer guy says wait 2 weeks for everything to dry out. March is the rain season and I need to get the foundation done. Is there any way to dig the footings and drain them let the clay dry for a couple of days (3) then poor. Will the footing crack as the clay finishes drying due to proper irrigation later. Is there a method for installing foundations in the rainy part of the year. Ground is bedrock, red clay and some grey clay all mixed. The dozer guy also thinks there is shell deeper but 12 feet revealed nothing. I think that is it. Help need to keep moving this project along.

The General is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 02-27-2005, 10:52 PM   #2
Pro
 
Teetorbilt's Avatar
Trade: Residential Contractor
 
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,464
My personal opinion is that you are building on a tenuous lot. I would not place a typical footer type foundation here. The water, current problem, will be back.
My first thought would be pilings driven or jetted to bedrock.
Teetorbilt is offline   Reply With Quote
Old 02-28-2005, 09:23 AM   #3
Pro
Trade: underground
 
Join Date: Oct 2004
Posts: 3,080
Quote:
Originally Posted by The General
We started on my personal home this last week and hit water at 2ft in 40% of a 600 ft waterline dig. We moved a lot of dirt for the pad and had soft spots at one end. Now the dozer guy says wait 2 weeks for everything to dry out. March is the rain season and I need to get the foundation done. Is there any way to dig the footings and drain them let the clay dry for a couple of days (3) then poor. Will the footing crack as the clay finishes drying due to proper irrigation later. Is there a method for installing foundations in the rainy part of the year. Ground is bedrock, red clay and some grey clay all mixed. The dozer guy also thinks there is shell deeper but 12 feet revealed nothing. I think that is it. Help need to keep moving this project along.
You REALLY should get a geotechnical consultant involved before you proceed further. Water at 2 feet deep can be indicative of a number of things and may or may not have much of an impact on your foundation design. As far as dewatering the pad area goes, you could install a sump pit at some location within the footprint, at least 4 feet deeper than your FF elevation, and run a sumbersible pump 24 x 7 to see if that impacts the water level / dries the soil. Homebuilders around here work year 'round and you can believe that if an excavator told them to wait for a pad to dry out they'd have another excavator very quickly.
As far as driving piles or drilling casings 70 some feet to bedrock...I don't see that being a cost effective alternative for your home. Three days of good weather, a good excavator and an experienced geo-tech should have you back on track.
PipeGuy is offline   Reply With Quote
Old 02-28-2005, 09:30 AM   #4
General Contractor
 
hatchet's Avatar
Trade: General Contractor
 
Join Date: Oct 2003
Location: Montana - where I belong.
Posts: 1,035
I'm with Teetor - when you start talking about clay there are all sorts of problems that need to be accounted for. With bedrock below clay the only direction it can expand is up. Drying out the soil for the pour is a temporary solution at best. I've seen clay expand 18" in 36 hours - imagine what would happen to your footing if that happens. The best way to counteract expansion is with caissons and void form. As pipeguy said - get a geotech to make recommendations on foundation design.
__________________
Rich
WIT Construction Co.
Superior MT Contractor
hatchet is offline   Reply With Quote
Old 02-28-2005, 09:40 AM   #5
Pro
Trade: underground
 
Join Date: Oct 2004
Posts: 3,080
Google search for 'Geotechnical, Arkansas, engineer' should give you a place to start
PipeGuy is offline   Reply With Quote
Old 02-28-2005, 09:46 PM   #6
Registered User
Trade:
 
Join Date: Jan 2005
Posts: 12
Thanks for all the feedback. I am going to take some pictures tomorrow. Right now it looks like piers on the east end of footprint with 2x2 footer on top of piers. Going to lay out the house and dig a little and see what we get. I think it is just too much rain. 5in in Jan. avg is 2.4 and Feb was just as bad. Pipe the actual footprint is dry but on one end (where the driveway would be)the dozer ran over the ground so much it started pumping water to the surface. Will post pics but it did rain sunday.
The General is offline   Reply With Quote
Old 02-28-2005, 10:06 PM   #7
Pro
 
Teetorbilt's Avatar
Trade: Residential Contractor
 
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,464
the dozer ran over the ground so much it started pumping water to the surface.

I'm really NOT liking the sound of this.
Teetorbilt is offline   Reply With Quote
Old 03-01-2005, 12:42 AM   #8
General Contractor
 
hatchet's Avatar
Trade: General Contractor
 
Join Date: Oct 2003
Location: Montana - where I belong.
Posts: 1,035
I've seen ground where it's hard to walk on but when any heavy equipment rolls by it "pumps" making it look like a wave of water.. that's definately going to cause problems.
__________________
Rich
WIT Construction Co.
Superior MT Contractor
hatchet is offline   Reply With Quote
Old 03-06-2005, 09:18 PM   #9
Registered User
Trade:
 
Join Date: Jan 2005
Posts: 12
Well what's done is done. We poured the footing sat. Dirt was a 7 out of 10 according to the backhoe operator as for firm ness. We ended up moving the house to fit between the bad dirt and natural spring. Also took the whole elevation down to good dirt (4ft). 15k foundation just went to 30k but it is built the way I wanted. New foundation is now 5 block high with crusher dust fill (no basement). Also ground is now sloped around footing and cost myself a pumper truck with 100ft boom. The natural spring I refer to is going to be under my driveway to the side of my house. I had the backhoe operator cut into it and at 2 ft just in that area you hit solid bedrock. Looks like the water sinks into the dirt then runs along the bedrock down hill. I will still try to post pictures, for some reason the ioio port on a lap top is not the same as a home computer so I will have to post them from work. Thanks again all and I will keep everyone posted.
The General is offline   Reply With Quote
Old 03-06-2005, 09:59 PM   #10
Pro
 
Teetorbilt's Avatar
Trade: Residential Contractor
 
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,464
I'm staggered!
You never mentioned a natural spring!
I wish you luck on your new home.
Teetorbilt is offline   Reply With Quote
Old 03-07-2005, 08:40 AM   #11
Pro
Trade: underground
 
Join Date: Oct 2004
Posts: 3,080
Quote:
Originally Posted by The General
Dirt was a 7 out of 10 according to the backhoe operator as for firm ness. 15k foundation just went to 30k but it is built the way I wanted. New foundation is now 5 block high with crusher dust fill (no basement).
What part of that doubled the cost of your basement? The backhoe operator? The concrete pump? You said originally the block would be 3 - 4 courses tall, that's only 1 or 2 additional courses. If your foundation is 60 x 50 filled 5 block high that's less than 400 cy of fill.
7 out of 10 for firmness huh? If we were talkin' about woman I'd say you were in tall cotton. But since we're talkin' about foundations, I'm guessing you're in deep sh*t. Good luck.
PipeGuy is offline   Reply With Quote
Old 03-07-2005, 09:18 AM   #12
General Contractor
 
hatchet's Avatar
Trade: General Contractor
 
Join Date: Oct 2003
Location: Montana - where I belong.
Posts: 1,035
Whew.. clay with a natural spring nearby. I hate being negative - but I'll give it 2 years.
__________________
Rich
WIT Construction Co.
Superior MT Contractor
hatchet is offline   Reply With Quote
Old 03-03-2010, 09:02 PM   #13
Member
Trade: masonry
 
Join Date: Feb 2010
Location: russel co ,ky
Posts: 58
I wander how this guys house turned out
jshuatree is offline   Reply With Quote
Old 03-03-2010, 10:09 PM   #14
Pro
 
Tscarborough's Avatar
Trade: masonry
 
Join Date: Feb 2006
Location: Austin
Posts: 3,725
The foundation repair guys made a killing.
__________________
It ain't Rocket Science unless you are building rockets.
Tscarborough is offline   Reply With Quote
Old 03-03-2010, 11:38 PM   #15
Mason
Trade: Bricklayer
 
Join Date: Dec 2009
Location: chicago
Posts: 19
make sure u put 2 separate pumps in yr basement...yr gonna need it
brickstretcher is offline   Reply With Quote
Old 03-04-2010, 05:04 AM   #16
Pro
 
CJKarl's Avatar
Trade: Masonry
 
Join Date: Nov 2006
Location: Ivoryton CT
Posts: 968
Indoor pool
__________________
There's Always A Market For Quality
http://www.kaufmannmasonry.com/
CJKarl is offline   Reply With Quote
Old 03-04-2010, 05:42 AM   #17
General Contractor
 
greg24k's Avatar
Trade: New Home Construction-Additions-Remodeling
 
Join Date: May 2007
Location: NJ
Posts: 1,249
When building on clay soil,you have to make sure to give the load from the foundation and your house a wider area to spread over, so you will have to have a good drainage under your footings. Use a nice layer of 3/4 inch clean stone (8-10") under the footing.and the whole basement area in and out... use perforated pipe on the outside and inside of the footing tied in to the sump pump.Most likely your engineer will suggest that and to use a footing 2 maybe 3 times wider than your foundation wall with re-bar. Engineer will calculate everything based on what you have there,i.e. the weight of the house, strength of the soil,etc. Good idea to bring in fill for backfill to make sure you have a good drainage around your foundation. Don't use existing clay to backfill your foundation. Good luck
__________________
I never lost a cent on the jobs I didn't get!

Last edited by greg24k; 03-04-2010 at 07:14 AM.
greg24k is offline   Reply With Quote
Old 03-04-2010, 08:45 AM   #18
Pro
 
Tscarborough's Avatar
Trade: masonry
 
Join Date: Feb 2006
Location: Austin
Posts: 3,725
This was 5 years ago, FYI.
__________________
It ain't Rocket Science unless you are building rockets.
Tscarborough is offline   Reply With Quote
Old 03-04-2010, 09:35 AM   #19
Pro
 
stacker's Avatar
Trade: masonry
 
Join Date: Jan 2006
Location: alva,oklahoma
Posts: 1,034
i hear he has a nice trout pond in his crawl space.
__________________
life is short,do your masonry naked!!
http://ok.local.yahoo.biz/knabemasonry/index.html
stacker is offline   Reply With Quote
Old 03-04-2010, 11:35 AM   #20
Member
 
Rocha_Const's Avatar
Trade: Masonry and Stone Work
 
Join Date: Feb 2010
Location: Maryland
Posts: 46
LOL, people dont look at the year this was written. I wonder also how did everything go...
Rocha_Const is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Mass deck footing codes Mike Fish Decks & Fencing 1 07-25-2007 07:34 PM
footing depths WNYcarpenter General Discussion 18 07-14-2007 09:47 PM
Clay tile roofing Alkyd Roofing 8 11-27-2006 08:43 AM
What do I need to hire to excavate 50 acres of clay haskl33 Excavation & Site Work 11 09-11-2006 07:38 AM
Footing Drains jjtt Excavation & Site Work 27 07-17-2006 09:28 PM


Top of Page | View New Posts


All times are GMT -5. The time now is 02:25 PM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC