What Goes First

 
Thread Tools Search this Thread Display Modes
Old 11-19-2009, 12:23 PM   #1
Registered User
 
hotrod1148's Avatar
 
Trade: General Contractor
Join Date: Nov 2009
Posts: 3

What Goes First


How are you guys doing. I am a general contractor constructing a two story library for a public entity, it is approximatly 11,000 sq ft. the library is on the second floor and the parking garage is on the ground floor, (first floor). I am being told to build the 2nd floor (the deck) first then the ground floor. any thoughts?.

hotrod1148 is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 11-19-2009, 01:14 PM   #2
Pro
 
Framer53's Avatar
 
Trade: Framing
Join Date: Jan 2009
Location: Utica,NY
Posts: 2,052

Re: What Goes First


Quote:
Originally Posted by hotrod1148 View Post
How are you guys doing. I am a general contractor constructing a two story library for a public entity, it is approximatly 11,000 sq ft. the library is on the second floor and the parking garage is on the ground floor, (first floor). I am being told to build the 2nd floor (the deck) first then the ground floor. any thoughts?.

Welcome to the site.
Now why not just start with the roof first??
Framer53 is offline  
Old 11-19-2009, 01:18 PM   #3
Registered User
 
hotrod1148's Avatar
 
Trade: General Contractor
Join Date: Nov 2009
Posts: 3

Re: What Goes First


But thats what I am looking for. reasons why to start second floor.
hotrod1148 is offline  
Old 11-19-2009, 01:31 PM   #4
The Duke
 
KentWhitten's Avatar
 
Trade: Cabinet Maker
Join Date: Mar 2006
Location: Portland, Maine
Posts: 10,086

Re: What Goes First


Maybe you are not stating exactly what you mean since what I interpret is that either you or they need a straight jacket and a whole lot of Valium. Can you explain with a little more detail than levitating the second floor in violation of Newton's Law?

Please start a new thread about this in the Construction Forum
__________________
If you correct your mind, the rest of your life will fall into place ~Lao Tzu

Custom Cabinetry - Portland, Cape Elizabeth, Scarborough, Kennebunkport, Yarmouth, Falmouth, Cumberland, Ogunquit, Maine


Salmon Falls Cabinetry
KentWhitten is offline  
Old 11-19-2009, 01:36 PM   #5
Pro
 
Framer53's Avatar
 
Trade: Framing
Join Date: Jan 2009
Location: Utica,NY
Posts: 2,052

Re: What Goes First


Quote:
Originally Posted by framerman View Post
Maybe you are not stating exactly what you mean since what I interpret is that either you or they need a straight jacket and a whole lot of Valium. Can you explain with a little more detail than levitating the second floor in violation of Newton's Law?

Please start a new thread about this in the Construction Forum
A man with a way with words!
Framer53 is offline  
Old 11-19-2009, 01:38 PM   #6
Registered User
 
hotrod1148's Avatar
 
Trade: General Contractor
Join Date: Nov 2009
Posts: 3

Re: What Goes First


It's a concrete deck (second floor), forms shoring, rebar, they want to pour the second floor first. So we will put our shoring in place, form, set rebar, electrical, etc etc and pour. Then when that is complete and we can remove shoring we will pour ground floor.
hotrod1148 is offline  
Old 11-19-2009, 07:45 PM   #7
Pro
 
SC sawdaddy's Avatar
 
Trade: General Contractor
Join Date: Oct 2008
Location: South Carolina
Posts: 1,386

Re: What Goes First


Quote:
Originally Posted by hotrod1148 View Post
It's a concrete deck (second floor), forms shoring, rebar, they want to pour the second floor first. So we will put our shoring in place, form, set rebar, electrical, etc etc and pour. Then when that is complete and we can remove shoring we will pour ground floor.

Huh?
SC sawdaddy is offline  
Old 11-19-2009, 10:32 PM   #8
framer
 
steves's Avatar
 
Trade: framing
Join Date: Feb 2007
Location: S.E. mass
Posts: 154

Re: What Goes First


If your just talking about placing the slab they do that all the time around here.
Never made much sense to me until I asked and they said it was to protect the finished garage slabs. Some jobs have gone as far as pouring footings well below the slab for shoring posts and such.
I've seen some slabs get pretty banged up just from normal construction,this way the owner gets the nice new floor he paid for.
steves is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?