Quote:
Originally Posted by jtcamp
Thanks for the responses so far.
The area is 70 sq ft and the finished floor will be carpet. The patio exists at the highest elevation on the property, so moisture is running away from it. Am I wrong in thinking that the two floors need to be at the same height?
I apologize, but I am new to some of this. For the last few years I have always worked along side of a professional and this most recent job is now in my hands. Thanks for all the help.
John
|
Gone to Mapei's website yet or still f'ing around?
Apply one of the Planiseal versions (you will at least have to contribute enough to the solution to figure out which one you need) - Planiseal will eliminate the moisture migration issues in the concrete.
Frame it with double bottom plates made from PT.
Look at Ultratop which will level up to 2", and level the floor to the height of the existing floor.
After that is it going to be glue down or stretched carpet?