OK. Here's what I got. A 5'x10' corner basement bath, the floor was about 6" higher than the slab in the rest of the basement. They had built it up but in doing so had simply laid 2x's on edge in the dirt, needless to say because of leaks and being in the dirt, they rotted, so we ripped it all out, and are now planning on pouring a slab in there .

So heres a pic of the cast plumbing laying in the dirt. What you're looking at is an app 2'x2' slab poured on top of the cast piping, it looks like they had cut a hole in the floor, used some vinyl flooring for a form and poured it. You can make out the vinyl flooring the little black diamonds along the top edge of the slab. If you look closely you see the 6" cast pipe coming under it from the right and going out to the left. The only thing I can think is they drilled into the cast for those two drains you see in that slab. The white pvc you see is from the first floor, the black ABS piece you see sticking up is the drain for the tub. You can also see the toilet flange in there jutting out from the lower right it has a rag sitting in it.



So I'm wondering the best way to proceed. Should I try and pour a slab around all that crap and will it adhere to that existing little slab enough to install a ceramic tile floor..
Or should I rip it all out and install new.

And how much do I need to cover the cast with concrete, because the 3/4" subfloor that was on there sat right on top of the cast, and the ceiling height was already critically low when standing in the tub.

Any ideas fellas???

denverboz is offline   Reply With Quote
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Join Contractor Talk

Join the #1 Contractor Forum Today - It's Totally Free!

ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!

Join ContractorTalk.com - Click Here JOIN FOR FREE

Old 08-16-2009, 05:32 PM   #2
Curmudgeon
 
neolitic's Avatar
Trade: carpentry/remodeling/"Yes M'am we do"
 
Join Date: Apr 2006
Location: Beech Grove, Indiana, Birthplace of the "King of Cool"
Posts: 10,151
Quote:
Originally Posted by denverboz View Post
OK. Here's what I got. A 5'x10' corner basement bath, the floor was about 6" higher than the slab in the rest of the basement. They had built it up but in doing so had simply laid 2x's on edge in the dirt, needless to say because of leaks and being in the dirt, they rotted, so we ripped it all out, and are now planning on pouring a slab in there .

So heres a pic of the cast plumbing laying in the dirt. What you're looking at is an app 2'x2' slab poured on top of the cast piping, it looks like they had cut a hole in the floor, used some vinyl flooring for a form and poured it. You can make out the vinyl flooring the little black diamonds along the top edge of the slab. If you look closely you see the 6" cast pipe coming under it from the right and going out to the left. The only thing I can think is they drilled into the cast for those two drains you see in that slab. The white pvc you see is from the first floor, the black ABS piece you see sticking up is the drain for the tub. You can also see the toilet flange in there jutting out from the lower right it has a rag sitting in it.



So I'm wondering the best way to proceed. Should I try and pour a slab around all that crap and will it adhere to that existing little slab enough to install a ceramic tile floor..
Or should I rip it all out and install new.

And how much do I need to cover the cast with concrete, because the 3/4" subfloor that was on there sat right on top of the cast, and the ceiling height was already critically low when standing in the tub.

Any ideas fellas???

Don't take this the wrong way, but
you need to get a good plumber in there.
__________________
Put your location in your profile!
(Sorry....it seems there really are dumb questions)
neolitic is online now   Reply With Quote
The Following User Says Thank You to neolitic For This Useful Post:
denverboz (08-16-2009)
Old 08-16-2009, 05:40 PM   #3
Never lost a battle.
 
ScipioAfricanus's Avatar
Trade: General contractor, designer, drafter.
 
Join Date: Sep 2008
Location: Orange County, CA.
Posts: 601
Yeah, you need somebody to evaluate that mess first hand. Give you information on about how to get an access for the shower trap, if you have enough slope on those lines, securing the piping to the wall properly, (I am assuming it is a conc. wall.

Andy.
__________________
www.draftinginoc.com
ScipioAfricanus is offline   Reply With Quote
The Following User Says Thank You to ScipioAfricanus For This Useful Post:
denverboz (08-16-2009)
Old 08-16-2009, 06:13 PM   #4
Pro
Trade: Construction
 
Join Date: Jun 2009
Location: VA
Posts: 879
Wow thats a mess. The CI will hold up no problem with just a inch of concrete above but the issue you have there is the way they have pipped into that CI soil pipe. I wouldnt build a new batroom over the top of that mess unless it was all taken up and repaired. Maybe take that concrete up and see how they have piped into the CI soil and see if they used some kind of boss or saddle adaptor. You have to be carefull as you have a couple of branches that could be a pig to replace if you damage the CI pipe or fittings. If ya gonna do it make sure ya do it right and take that mess out.
BCConstruction is offline   Reply With Quote
The Following User Says Thank You to BCConstruction For This Useful Post:
denverboz (08-16-2009)
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off





Top of Page | View New Posts


All times are GMT -5. The time now is 12:25 AM.


Contractor Talk™ © 2003 - 2009 The Building Network LLC