Truck Or Mixer?


Say you need just over 1 yard of concrete to fill a bunch of hellish sonotubes tucked under the structure with about 12" clearance above them (all shovel work to get the crete in the tubes) , would you get a truck in and have it sit while you wheel and shovel or just buy premix bags and get out the trusty old mixer? (there is no place to stock sand and gravel to mix your own)

__________________
shanekw1 is online now  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 09-24-2009, 10:53 AM   #2
New and Remodel Carpentry
 
cooks's Avatar
 
Trade: General Contractor/Remodelor
Join Date: Feb 2008
Location: St. Louis, MO
Posts: 93

Re: Truck Or Mixer?


On something like that you are better of with the bags. 1. You can control the time needed to pour and finish each sonotube. 2. your late charges on having that truck sit will be high(not worth it to me).
cooks is offline  
Old 09-24-2009, 11:08 AM   #3
Registered User
 
Gerry817's Avatar
 
Trade: Builder/ Remodeler
Join Date: Sep 2009
Location: Venice, FL
Posts: 3

Re: Truck Or Mixer?


I would pull out the mixer and get the bags going. Saves money and you can control the mix. With only the 12" of clearance it gives you better flexability to make sure all the mix gets into the tubes.
Gerry817 is offline  
Old 09-24-2009, 12:02 PM   #4
Chief outhouse engineer
 
dakzaag's Avatar
 
Trade: mason
Join Date: Jan 2009
Location: NW Indiana
Posts: 985

Re: Truck Or Mixer?


Just poured a footer two weeks ago, called for .8 yds. Since I was laying block on top of the footer I had sand and pea gravel delivered along with Portland and everything else I needed (except for the mortar ) We mixed and poured it in about an hour.

I used pea gravel cause any thing bigger is pretty tough on a paddle mixer. If I had a drum mixer, I could have used bigger stone. I don't think it was a problem in this particular situation.

Its still a lot of scooping.

BTW it takes about 40 bags (#80) to make a yard.
__________________
D K & Sons
The maintenance schedule for brick
1. Stand back and say "man that looks nice!"
2. Repeat as often as needed.
dakzaag is offline  
Old 09-26-2009, 05:26 PM   #5
Gumby
 
IanS's Avatar
 
Trade: Concrete
Join Date: Sep 2009
Location: NW Florida Panhandle
Posts: 112

Re: Truck Or Mixer?


Yes in this case I would probably mix bags.

However this situation comes up a lot so here is my logic.
1 cubic yard =42 80lb bags of sackrete. Each bag does 2/3 of one cubic foot. Depends on how much you waste; drop, fail to get out of mixer etc

A bag costs $4.00 in general after tax.
To rent a small mixer costs about $50.00 for me.
Cost to mix 42 bags is $168+50= $218.

My ready mix company will send 1 yard at $100.00 and a short load fee under 5 yds = 125 + environmental and fuel surcharge= $225.00

99% of the time I will get the Ready mix. In the last 3 years I have had 2-3 jobs where I just had to mix by hand.

The last possibility in my area is make your own mix. A truck of rock runs over $300.00 A load of Sand is over 300.00. Just not a possibility here. In Texas it was $6/ton back in the day. Sand was cheap too and you could get small loads delivered or you could pick them up. Similar up North in Washington State.

Site access is always the deciding factor for me.
Getting bags to site takes hours, delivery is 15-60 bucks depending on locale. It takes x minutes to load and mix bags.

If I were you, you might get some retarder added by Ready Mix Company or add it on site. Wheel barrow to a chunk of plywood by each tube; Make a large box and haul it around then get rid of truck and fill your sono tubes. How many men you have with you? You should have about 1hr or more with the retarder depending on temp, humidity wind etc. Sonotube finishing??? Bang and strike off or round top for water drain.

I have even heard some Ready mix has built in pump.
Here pump is seperate and runs $350.00 minimum. Honestly I might have tried to build that in the price.

Enough thinking out loud! Good luck!

Last edited by IanS; 09-26-2009 at 05:35 PM. Reason: More musings
IanS is offline  
Old 09-26-2009, 09:14 PM   #6
Pro
 
Jayrek's Avatar
 
Trade: GC/Transportation
Join Date: Sep 2008
Location: Southern New England
Posts: 132

Re: Truck Or Mixer?


Site mix truck, save the headache and your back.
And some of them have built in pumps.
Jayrek is offline  
Old 09-26-2009, 10:23 PM   #7
Trailer park boy
 
shanekw1's Avatar
 
Trade: Remodeling
Join Date: Mar 2008
Location: Castlegar, BC, Canada
Posts: 3,602

Re: Truck Or Mixer?


The crappy thing is sackrete comes in 55 lb bags around here (that is what is stocked anyway)

68 bags @ 5 bucks a bag = $340 (yea 5 bux a 55 lb bag)

Truck cost me $300 even with wait time and short load charge, and I got it done in 1.5 hrs versus all day mixing.
__________________
shanekw1 is online now  
Old 09-26-2009, 10:43 PM   #8
Pro
 
mics_54's Avatar
 
Trade: contractor
Join Date: Oct 2008
Location: Alaska
Posts: 1,062

Re: Truck Or Mixer?


grout pump!
mics_54 is offline  
Old 09-27-2009, 01:16 PM   #9
Pro
 
csv's Avatar
 
Trade: General
Join Date: Aug 2009
Location: Central WA
Posts: 212

Re: Truck Or Mixer?


does any rental place have a pull behind concrete trailer? I ave used them on occasion, about 155/yrd
csv is offline  
Old 10-19-2009, 12:25 AM   #10
Designer/Contractor
 
Rio's Avatar
 
Trade: General Contractor
Join Date: Oct 2009
Location: San Diego city/County, Cali
Posts: 382

Re: Truck Or Mixer?


Ready mix, pump, and factor in the price.....................
Rio is offline  
Old 10-19-2009, 01:27 AM   #11
solar guy
 
naptown CR's Avatar
 
Trade: solar contracting
Join Date: Feb 2009
Location: Annapolis Md
Posts: 1,883

Re: Truck Or Mixer?


what about a batch mix truck

for anything less than a yard I always went bags. Me and a helper can mix and pour a bag in less than 2 minutes with no spillage and no equipment other than a piece of poly. Works particularly well on a deck with hanging posts. or perhaps in this situation.
naptown CR is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Mixer Truck Question Rick Rowlands Masonry 16 08-10-2009 09:17 PM
10 Wheeler TRUCK W/ CAT C-12 99 STERLING W/8 40 YARD DUMPSTERS! Paradise Vehicles 0 07-24-2009 02:38 PM
need advice on dead truck & removing/selling Kargo Master ladder rack jordanski Vehicles 12 06-03-2009 08:29 AM
Morter Mixer Vs Cement Mixer personalt Masonry 6 07-29-2007 09:16 PM
Painted My Truck With a Roller ModernStyle Painting & Finish Work 44 07-21-2007 10:11 PM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?