|
|
Thread Tools | Search this Thread | Display Modes |
|
|
#1 |
|
Pro
Trade: Builder
Join Date: Apr 2006
Posts: 110
|
Pay Schedule For Fixed Price Contract
What is your company's normal procedure for collecting pay on a fixed price contract? Say you are building a house from the ground up for $150,000 total. What % of the cost and at what points do you charge the homeowner?
What is your common payment schedule? |
|
|
|
|
|
#2 |
|
Pro
Trade: Builder
Join Date: Apr 2006
Posts: 110
|
Re: Pay Schedule For Fixed Price Contract
What is everyone's draw schedule?
|
|
|
|
|
|
#3 |
|
Pro
Trade: Fan of Bodger
Join Date: Mar 2009
Posts: 397
|
Re: Pay Schedule For Fixed Price Contract
Bank will let you know!!
|
|
|
|
| The Following User Says Thank You to Crock For This Useful Post: | buildpinnacle (03-19-2009) |
|
|
#4 |
|
Pro
Trade: Public Insurance Adjuster
Join Date: Sep 2008
Location: DFW
Posts: 590
|
Re: Pay Schedule For Fixed Price Contract
Kdub,
This is fairly commonplace.
__________________
Pinnacle Limited
Public Insurance Adjusters (800) 918-7840 |
|
|
|
|
|
#5 |
|
Pro
Trade: General Contracting
Join Date: Sep 2008
Location: Northwest Hills of CT
Posts: 290
|
Re: Pay Schedule For Fixed Price Contract
DRAW SCHEDULE I (Four Advances)
15% Site preparation, footer, basement walls, parged and pitched, if applicable, 1st floor joists, plate and plywood decking down. 30% Framed, sidewall sheathing, and under roof, including shingles. Interior walls studded, windows and exterior doors in place. Roughly plumbed and wired. 35% Heat plant and ductwork installed, basement floor poured, insulation, sheet-rock, plastered. Exterior walls finished, soffit and spouting. Fireplaces, if applicable, stairways roughed in, and carpet/linoleum underlayment installed. 20% Interior trim installed and finished, all cabinetry installed and finished, bath fixtures, interior doors hung, light fixtures, storms if applicable, floor covering. Graded, seeded and landscaped as per contract. DRAW SCHEDULE II (Three Advances) 35% When the foundation is in, building is rough enclosed and under finished roof. 40% When rough plumbing and electrical are completed, when exterior and interior walls are complete 25% When property is entirely completed per plans and specifications. DRAW SCHEDULE III (Four Advances) 15% When foundation is in, when sub-flooring is in. 30% When rough enclosed and under finished roof, rough plumbing and electrical are complete. 30% When house is insulated, exterior and interior walls are completed. 25% When property is entirely complete per plans and specifications. DRAW SCHEDULE IV (Four Advances) 10% Upon completion of excavation and foundation. 30% Upon completion of sub-flooring, exterior walls (enclosed), finished roof, all windows and exterior doors installed. 40% Upon completion of roughed-in wiring, roughed-in plumbing, roughed-in heating (includes delivery of central heating plant), installation of dry wall or plasterboard, sewer or septic system and drain-field installed, finished exterior walls and concrete basement floor. 20% Upon completion of dwelling per plans and specification. DRAW SCHEDULE V (Five Advances) 15% When foundation is in and 1st floor joists are set. 15% When sub-flooring is in, building rough enclosed and under roof. 20% When under finished roof, rough plumbing and electrical are complete. 25% When house is insulated, exterior and interior walls are completed. 25% When property is entirely complete per plans and specifications.
__________________
http://brianwilsonconstruction.net |
|
|
|
|
|
#6 |
|
Pro
Trade: Builder
Join Date: Apr 2006
Posts: 110
|
Re: Pay Schedule For Fixed Price Contract
Thanks all
|
|
|
|
|
|
#7 |
|
LC Australia
Trade: Building
Join Date: Dec 2006
Location: Canberra
Posts: 439
|
Re: Pay Schedule For Fixed Price Contract
We tell the bank what we are doing in regards to payment schedule! And they follow.
The usual schedule is this: 1. Deposit at signing of Contract - 5% 2. Floor level complete - 20% 3. Roof trusses installed - 20% 4. Ready for plaster linings - 25% 5. Painting complete - 25% 6. Practical completion - 5% Variations are paid by client during the job at the following progress claim after it was signed.
__________________
"It's better to die on your feet than to live on your knees" |
|
|
|
|
|
#8 |
|
Pro
Trade: Remodeling
Join Date: Jan 2009
Location: New Hampshire
Posts: 295
|
Re: Pay Schedule For Fixed Price Contract
I used to do "Start of" on my proposals, I went to a seminar by Shawn McCadden, from Remodeling Mag. He says try it this way, makes sense to me as well.
My pay schedule now says; "Ready for etc", This way I get a payment when ready, it does not mean the last phase is 100% complete, just the next is ready. It has work well no complaints. OK now I am ready to be ripped... ![]() Total Investment $24,970.00 Deposit $4,000.00 Start of Job $4,000.00 Ready for Rough Plumbing $4,000.00 Ready for Rough Electrical $4,000.00 Ready for Tile Installation $4,000.00 Ready for Painting $4,000.00 Substantial Completion $970.00
__________________
David Cookman |
|
|
|
|
|
#9 | |
|
Professional Instigator
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872
|
Re: Pay Schedule For Fixed Price ContractQuote:
|
|
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Time To Really Consider Escalation Clauses | Ed the Roofer | Business | 18 | 06-25-2008 11:42 PM |
| Go to Page... |
