Thread Tools | Search this Thread | Display Modes |
|
|
#1 |
|
Registered User
Trade: General Contractor
Join Date: Jun 2008
Posts: 1
|
Newbie With Question On Partial Lien Release Clauses
Hi All,
New member here with a question on "typical" partial lien release clauses in construction contracts between GC and Owner. Specifically, is it most common to require the GC to furnish partial lien releases from Subcontractors and Vendors prior to receiving the first draw (any payment), or, is it typical to require partial lien releases for the prior month's payment before receiving the next draw? I understand it is usual to provide final releases before getting paid the last draw including retainage. The first way requires the GC to finance the work until reimbursed. Trying to avoid that. Maybe I've been lucky on other work to bring in releases for the previous month before getting the next check (again, until the last draw) but don't remember it being the norm to front the payments. Thanks for any insight/suggestions |
|
|
|
|
|
#2 |
|
Pro
Trade: LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,426
|
Re: Newbie With Question On Partial Lien Release Clauses
i will not sign a partial lien release untill i recieve the check for that amount, you could also sign the release, with a signed note at the bottom that states (release becomes effective after check has been recieved)
__________________
|
|
|
|
|
|
#3 |
|
Remodeling GC
Trade: Remodeling General Contractor
Join Date: Aug 2006
Location: Denver Colorado
Posts: 2,033
|
Re: Newbie With Question On Partial Lien Release Clauses
after the check is cleared would be a better way to state it on the release.
__________________
Kevin Basement Finishing Highlands Ranch Colorado Littleton Colorado, Basement Remodeling Kitchen Remodeling Denver |
|
|
|
|
|
#4 |
|
Registered User
Trade: Masonry
Join Date: Apr 2008
Location: Southwest Florida
Posts: 18
|
Re: Newbie With Question On Partial Lien Release Clauses
It is customary to provide partial lien waivers for every pay application after the first draw. Then, a final waiver is provided before final payment is released.
Regards Kevin |
|
|
|
![]() |
| Thread Tools | Search this Thread |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| I-joist newbie question | 737Pilot | Framing | 2 | 03-10-2008 10:10 PM |
| 120/240 Service & Phases: newbie question | Mark Twenhafel | Electrical | 3 | 11-04-2007 01:04 PM |
| Question about a lien?? | AHS | Business | 10 | 07-28-2007 11:47 AM |
| Progressive Lien Release | ncurls | Business | 2 | 07-23-2007 02:56 PM |
| Newbie Question | DAK | General Discussion | 21 | 07-26-2006 07:30 PM |
| Go to Page... |