Have You Ever Considered Post-dated Checks For Progress Payments????

 
Thread Tools Search this Thread Display Modes
Old 02-13-2008, 01:11 PM   #1
Contractor, v2.0
 
TigerFan's Avatar
 
Trade: General Contractor
Join Date: Apr 2006
Location: Gulf Coast
Posts: 188

Have You Ever Considered Post-dated Checks For Progress Payments????


I'm getting fed up with the voicemails, out-of-towns, working lates, thought-the-progress-payment-also-included-this, excuses and BS I'm going through almost every time I send out an invoice.

My contracts are detailed, well laid out, and spell out exactly what the customer should expect to be done when we submit for a payment.

My jobs are typically $50k - $110k renovations. I get $2500.00 at signing which takes me through permitting, dumpsters, ****ters, site prep and demolition work. Then I have 4, 5 or 6 progress payments that are "big hitter" payments. Then 3% at substantial completion, 2% at final completion.

I also lay out a timeline - 60-120 days and the progress payments are due within that timeline.

Example: Stage 1 - Due on the 10th day (or sooner) when interior demolition, plumbing demolition and exterior bushwacking are complete.

I'm now at day 15 with with those things complete and no payment yet.

2 jobs exactly like this right now.

I'm about to start making customers give me post-dated checks that land, say, 3 days after the payment would be due. IE - the "10th day" payment would be dated on the date of the 13th day of the contract.

In other words, AT SIGNING, I would get all the checks except for the substantial and final completion checks.

Any of you ever tried or done that before??

__________________

http://www.bayoucontracting.com
TigerFan is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 02-13-2008, 01:25 PM   #2
Pro
 
Tscarborough's Avatar
 
Trade: Monkey Scratching Cat Herder
Join Date: Feb 2006
Location: Austin
Posts: 4,776

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


You need to add one more clause to your contract dealing with work stoppage, remobilization costs and schedules, and make sure it lists the possible reasons for stoppage, like payments.
__________________
It ain't Rocket Science unless you are building rockets.
Tscarborough is online now  
Old 02-13-2008, 01:55 PM   #3
Contractor, v2.0
 
TigerFan's Avatar
 
Trade: General Contractor
Join Date: Apr 2006
Location: Gulf Coast
Posts: 188

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Quote:
Originally Posted by Tscarborough View Post
You need to add one more clause to your contract dealing with work stoppage, remobilization costs and schedules, and make sure it lists the possible reasons for stoppage, like payments.
Well, I kind of have that - at least as it deals with work stoppage and the schedules.

I just want people to read the paperwork they signed and do as it says without pulling teeth or writing novels about it.

I mean, they might "feel" like it's early to write the next check, but it's set up that way for a reason - to get the damn job done.
__________________

http://www.bayoucontracting.com
TigerFan is offline  
Old 02-13-2008, 02:43 PM   #4
MI Contractor
 
MIbeachbuilder's Avatar
 
Trade: General contractor
Join Date: Feb 2008
Location: Southwest Michigan
Posts: 89

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


I don't think using post dated checks is a bad idea as long as you make the client show proof of funds. (they only need to call the bank and the bank will fax it to you directly with an up to amount on the contract).

We have done that with some of our out of town clients....without any problems....
MIbeachbuilder is offline  
Old 02-13-2008, 02:56 PM   #5
Moderator
 
Double-A's Avatar
 
Trade: GC - Remodeling Specialists
Join Date: Jul 2006
Location: Arkansas
Posts: 4,618
Send a message via ICQ to Double-A

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


We make it clear that once we've reached a milestone in the contract and payment is due, we don't continue until payment is made. If a check doesn't clear for some reason, then payment has not been made.

If payment is not made, we pull off the job, and have substantial redeployment costs. We go over this part of the contract with the client carefully so they understand when the payment will be due, how much it is, what its for, and what happens and why if they don't pay.

I guess this is the same thing that Tscarborough has said in so many words, but we do put it into practice on every job. We have yet to have a real problem with it.

One other option is to use an escrow account for progress payments. Funds are deposited to pay the contract and payments made from the escrow account once both parties agree on that milestone being reached. This adds costs and you might consider telling the folks that are jacking you around that unless they start being on-time and forthright with their payments, this will be the only option left to them to continue to do business before you seek to have them declared in breech of contract and sue for monies owed and damaged incurred.
__________________
"My clients’ wishes are the center of my attention." -- David Guido, a contractor in Woodstock, N.Y.
New York Times, July 20, 2006
Double-A is offline  
Old 02-13-2008, 04:32 PM   #6
Pro
 
GSE's Avatar
 
Trade: Electrical
Join Date: Aug 2007
Posts: 180

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Quote:
Originally Posted by TigerFan View Post

I also lay out a timeline - 60-120 days and the progress payments are due within that timeline
There is your problem, your trying to be in the banking business, get back to contracting and have that money comming in every 2 weeks and the first time they miss a week back the trailer and make smoke, then get your attorney to demand third party escrow from his bank.

Please, Please, you can pay me whenever you want, I want your work so bad you don't have to respect me, do what you want and pay if you feel like it.
GSE is offline  
Old 02-13-2008, 05:39 PM   #7
Construction Marketer
 
SethHoldren's Avatar
 
Trade: Construction Dude w/ Website Skills
Join Date: Feb 2008
Location: Nashville
Posts: 288

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Quote:
have that money coming in every 2 weeks and the first time they miss a week back the trailer and make smoke
I agree with GSE.

Get the money coming in regularly. Once a week works well (especially for smaller businesses) but every two weeks is good too. Any longer than that can cause you problems.

Another key: Set it in stone. Tuesday morning at 10 a.m. is invoice time, baby. Once you set a date that works for your client, make it unavoidable. You can even implement a "missed appointment" penalty.

Enforce it. Politely but firmly.

It works. It breaks the payments into smaller chunks which are easier for the client to stomach. It gives you an authoritative presence and weekly face time.

And your cash flow will be more consistent.
SethHoldren is offline  
Old 02-13-2008, 07:21 PM   #8
Chief Toilet Mover
 
Mike Finley's Avatar
 
Trade: Bathroom Remodeling
Join Date: Apr 2004
Location: Littleton, Colorado
Posts: 14,078

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


I have to agree with all the above. We also try to give the customer a day or two advance notice of the upcoming payment. Pretty much works like:

"It's Monday, here is your invoice that will be due on Wednseday morning."

Very, very few customers fail to have the check waiting for you that morning it's due once we started doing this.

Should we have to do this type of babysitting and handholding of customers? Probably not, but it takes only a tiny bit of foresight and it seems to avoid a lot more hassles. In the past we would present the customer with the invoice due that morning on that day and then have to stand there and wait for them to find their check books or call the husband and make arrangements for him to bring it back since he accidently took it to work with him or.... etc... etc...
Mike Finley is offline  
Old 02-13-2008, 07:48 PM   #9
Pro
 
Teetorbilt's Avatar
 
Trade: Residential Contractor
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,475

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


If you're in this situation, it's usually bad and may be illegal. Ck with your attny.
__________________
You can't solve you're problems with the same level of thinking that created the problems.

Albert Einstein
Teetorbilt is offline  
Old 02-13-2008, 08:13 PM   #10
Pro
 
Steve Unkie's Avatar
 
Trade: REMODELING CONTRACTOR
Join Date: Jan 2006
Location: Port Orchard,WA
Posts: 139

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


I agree with the above posts. I usually set up weekly p-payments. One large job where the client was out of town, he wired in the payment every Fri.

The longest I'll go is 2 weeks. I learned the hard way, though.

Steve.
Steve Unkie is offline  
Old 02-13-2008, 08:17 PM   #11
Pro
 
Tom M's Avatar
 
Trade: GC/ Interior & Exterior Remodeling
Join Date: Jan 2007
Location: Bergen County, NJ
Posts: 1,886

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Its illegal to pass bad checks, so it may not be ideal but at least there is an agreement that by ------time----- this much is to be paid. Someone afraid to post date might not really have thier finances under wraps cause they already know they wont have the funds. Every customer has to be handled a little different but stopping a job in progress isnt too easy either. Thats a major hassle.
Tom M is offline  
Old 02-14-2008, 10:30 AM   #12
Contractor, v2.0
 
TigerFan's Avatar
 
Trade: General Contractor
Join Date: Apr 2006
Location: Gulf Coast
Posts: 188

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Well that's part of my issue too - stopping the job only means that we're still not paid.

I posted a typical pay schedule in another thread and got some good advice on modifications to it. I'm gonna go with "x amount due at the start of y" for my next few contracts.

For those interested here is the pay sched I had been using:

Payment Schedule:
The Owner hereby agrees to pay the Contractor, for the aforesaid materials and labor, the sum of $69,080.00 in the following manner:

$2,500.00 Earnest money at signing to Bayou Contracting

$20,724.00 on 7th day (or prior) due when:
- Electrical rough in is in progress.
- Plumbing Demolition has begun.
- Interior demolition complete

$17,270.00 on 18th day (or prior) due when:
- Plumbing rough in progress
- Electrical in progress
- Windows repaired / replaced.
- Drywall and Mud for job is onsite

$13,816.00 on 28th day (or prior) due when:
- Insulation installed.
- HVAC in progress
- Drywall hung, tape, float, finished
- Painting Begins

$11,316.00 on 40th day (or prior) due when:
- Painting complete with minor touch ups remaining.
- HVAC trim out complete
- Electrical finish work completed
- Base Trim Installed
- Flooring in progress
-
-

$2,073.00 Upon Substantial completion

$1,381.00 Upon Completion

Substantial Completion time Planned for 50 days, with final completion expected within 10 days subsequent.

IN WITNESS WHEREOF, the parties hereto set their hands and seals the day and year written above.

By: ______________________________ By: ________________________
__________________

http://www.bayoucontracting.com
TigerFan is offline  
Old 02-14-2008, 03:57 PM   #13
Pro
 
Tom M's Avatar
 
Trade: GC/ Interior & Exterior Remodeling
Join Date: Jan 2007
Location: Bergen County, NJ
Posts: 1,886

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


LOOKS GOOD TO ME. As long as you or your client isn't not to far out of pocket and your keeping current with subs after rough-ins its great. I do the split final as well its good. Sometimes you finish with-in a day or so but when it dont work out its nice to have that planned.
Tom M is offline  
Old 02-16-2008, 05:26 PM   #14
Pro
 
excellencee's Avatar
 
Trade: Electrical Contractor
Join Date: Jan 2007
Posts: 159

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Check with your attorney. Somebody told me that you can't collect on a bad post dated check because you knew there was no money when you took the check. Once again this is hearsay. I'm NOT a lawyer so go see yours.
excellencee is offline  
Old 02-16-2008, 05:54 PM   #15
Member
 
ConstSvcs's Avatar
 
Trade: New home and remodeling
Join Date: Nov 2007
Location: CT shoreline
Posts: 76

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


I hope that this doesn't come back to bite me but:

Years ago 95% of my work was by word of mouth and the client standing by their side of the disbursment plan sometimes involved lots of "handholding" the female half of the owner(s). Because, as one of my one of my past clients stated " happy wife.........happy life". This usually resulted in a perfect relationship with the client were payments went smoooooothly. Some time "tracking down" your payment was still required. You know as a GC what makes your clients happy........or not so happy.

In the recent years my work has moved to 95% work from local Architects. The advantage has been that most clients have been "screened" and have less sticker shock and a better understanding for the value of labor and quality. Usually resulting in expedited payments.

Never let them think that their payment is simply a deposit into you treasure chest. If they are business owners themselves they usually understand the importance of cash flow.

Your payment requests seem more than fair except that my retainage upon completion is usually 5% of the total.

Last edited by ConstSvcs; 02-16-2008 at 05:58 PM.
ConstSvcs is offline  
Old 02-17-2008, 11:30 AM   #16
General Contractors
 
Buckknekkid's Avatar
 
Trade: Project Managers
Join Date: Feb 2008
Location: ONTARIO
Posts: 67

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


We've been in business many years and usually our clients are referrals. STILL, its always a pain to collect.. We have deadbeat generals, dishonest salesmen, I dont like that shade of pink wife and the can you wait till we cash our savings bonds after the tax year,, want any more excuses?
Buckknekkid is offline  
Old 02-18-2008, 10:55 PM   #17
Member
 
mdcorreia's Avatar
 
Trade: Electrician - Self empl.
Join Date: May 2006
Location: Winnipeg, Canada
Posts: 86

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Quote:
Originally Posted by Double-A View Post
We make it clear that once we've reached a milestone in the contract and payment is due, we don't continue until payment is made. If a check doesn't clear for some reason, then payment has not been made.

If payment is not made, we pull off the job, and have substantial redeployment costs. We go over this part of the contract with the client carefully so they understand when the payment will be due, how much it is, what its for, and what happens and why if they don't pay.

I guess this is the same thing that Tscarborough has said in so many words, but we do put it into practice on every job. We have yet to have a real problem with it.

One other option is to use an escrow account for progress payments. Funds are deposited to pay the contract and payments made from the escrow account once both parties agree on that milestone being reached. This adds costs and you might consider telling the folks that are jacking you around that unless they start being on-time and forthright with their payments, this will be the only option left to them to continue to do business before you seek to have them declared in breech of contract and sue for monies owed and damaged incurred.
When you don't continue due to not receiving payment, who pays you to stay home (because you may not be able to start work which you did not schedule).
Also why waite 90 days? certain work completed = pay NOW!
Where did this 90 day deal come from? Are you imitating some mega co. ? are you that big?
mdcorreia is offline  
Old 02-18-2008, 11:26 PM   #18
Member
 
mdcorreia's Avatar
 
Trade: Electrician - Self empl.
Join Date: May 2006
Location: Winnipeg, Canada
Posts: 86

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Quote:
Originally Posted by ConstSvcs View Post
I hope that this doesn't come back to bite me but:

Years ago 95% of my work was by word of mouth and the client standing by their side of the disbursment plan sometimes involved lots of "handholding" the female half of the owner(s). Because, as one of my one of my past clients stated " happy wife.........happy life". This usually resulted in a perfect relationship with the client were payments went smoooooothly. Some time "tracking down" your payment was still required. You know as a GC what makes your clients happy........or not so happy.

In the recent years my work has moved to 95% work from local Architects. The advantage has been that most clients have been "screened" and have less sticker shock and a better understanding for the value of labor and quality. Usually resulting in expedited payments.


Never let them think that their payment is simply a deposit into you treasure chest. If they are business owners themselves they usually understand the importance of cash flow.

Your payment requests seem more than fair except that my retainage upon completion is usually 5% of the total.
How about HOLD BACK for 40 days etc. - in case something is wrong with the work?
mdcorreia is offline  
Old 02-19-2008, 11:16 AM   #19
Moderator
 
Double-A's Avatar
 
Trade: GC - Remodeling Specialists
Join Date: Jul 2006
Location: Arkansas
Posts: 4,618
Send a message via ICQ to Double-A

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


Quote:
Originally Posted by mdcorreia View Post
When you don't continue due to not receiving payment, who pays you to stay home (because you may not be able to start work which you did not schedule).
Also why waite 90 days? certain work completed = pay NOW!
Where did this 90 day deal come from? Are you imitating some mega co. ? are you that big?
I'm not sure where you're getting anything about "90 days" from my post, so I won't address that.

When we don't receive payment, we start proceeding as outlined in our contract. This process starts slowly and builds steam as it goes along. But, and this is important, we bill so that we're not the ones investing in the client's project, the client is. At any billing except the last one, we're collecting funds to proceed with, not to pay for what we have already completed.

As for staying at home, that is not an option, nor is it an option for our folks in the field.

We have a capital reserve account that is used to cover expenses due to not working/slow periods, so we continue to pay at our base salary rates. This account is part of the cost of doing business and is charged out as part of every billing we do. Once its fully funded, those monies are diverted to other less important accounts like capital improvements, equipment purchases, professional services, etc.

I hope that clears that up for you.
__________________
"My clients’ wishes are the center of my attention." -- David Guido, a contractor in Woodstock, N.Y.
New York Times, July 20, 2006
Double-A is offline  
Old 02-19-2008, 10:12 PM   #20
Pro
 
Carport King's Avatar
 
Trade: Aluminum Contractor
Join Date: Jan 2008
Posts: 470

Re: Have You Ever Considered Post-dated Checks For Progress Payments????


I do believe that post dating a check is Illegal and I do know it is not collectable in a court of law!

We do 10% up front and 10% on the back end and 1/3 draws x 3 in the middle. And we lien the property up front period!
Carport King is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
My first post biged04 Introductions 10 02-04-2011 01:06 PM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?