Old 04-26-2009, 06:40 PM   #1
Pro
 
Ed the Roofer's Avatar
 
Trade: Roofing Contractor
Join Date: Dec 2006
Location: NW Suburbs of Chicago
Posts: 7,135

Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Does anyone assess a fee charged in their change orders just for the discontinuity of the anticipated work flow?

I don't mean for the actual work scoped to be done as an extra, but just for the job scheduling upheaval?

Yes, adding more Materials And Labor to the project should be profitable, but many times, just getting to the point of getting the Signed Extra Work Authorized, it creates a Slow Down on the other production until it is agreed to.

Even if there is no slow down, there is unexpected downtime, even if it is only the fact of going over the new work authorized with the crew or foreman.

Comments?

Ed

Ed the Roofer is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 04-26-2009, 08:10 PM   #2
Chief outhouse engineer
 
dakzaag's Avatar
 
Trade: mason
Join Date: Jan 2009
Location: NW Indiana
Posts: 988

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Ed,
I am getting a new contract written up by a lawyer at this time and I had him add a statment "$150 dollar fee to generate a change order" due at the time a request is made. Total cost of change order is due at time of signing to offset the expense of changing schedule, putting off next customer etc. I might add lingo that the $150 will be applied to the CO if it is signed.

Looking to control all the what if's I get. Don't get me wrong, I will add on to any project gladly, but usually with a change order, you have gotten prices and done the figuring and then they respond with " I had no idea it would be that much, lets just leave it the way we planned."

This hopefully will cut down on requests, and at least pay the phone bill checking on prices and wasted down time, esp. if it delay's ongoing production.
__________________
D K & Sons
The maintenance schedule for brick
1. Stand back and say "man that looks nice!"
2. Repeat as often as needed.
dakzaag is offline  
Old 04-26-2009, 08:10 PM   #3
Sean
 
SLSTech's Avatar
 
Trade: General Contractor
Join Date: Sep 2008
Location: Cullman, AL
Posts: 4,515
Send a message via Skype™ to SLSTech

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


I don't do it, but I have heard of people charging a handling fee which is listed in the contract.
SLSTech is offline  
Old 04-26-2009, 08:24 PM   #4
LRG WoodCrafting
 
Leo G's Avatar
 
Trade: Master Sawdust Producer
Join Date: May 2005
Location: Windsor Locks, Connecticut
Posts: 13,231

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


$75 dollars for the change order request. And whatever the change of price upgrade/downgrade is. But the $75 is for writing the change order and that is all.
__________________
Sawdust Follows Me Everywhere

Quote:
Originally Posted by HusqyPro View Post
Carpenter by day.
Mad scientist by night.
http://lrgwood.com
Custom Cabinets in Hartford County Connecticut
Leo G is online now  
Old 04-26-2009, 09:11 PM   #5
Pro
 
Patrick's Avatar
 
Trade: Siding, Windows, Seamless Gutters, Metal Roofing
Join Date: Apr 2006
Posts: 2,761

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


We dont have a specific line item for change order cost, but what we gennerally do is mark up items a little more when they are part of a change order, especially if its something that is a PIA that we would rather not do.
__________________
Originally Posted by Celtic
Like I said...I'm sure you are very good at what you do ~ whatever that is and where ever it happens.
Patrick is offline  
Old 04-26-2009, 09:13 PM   #6
Professional Instigator
 
rbsremodeling's Avatar
 
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


$450

it is also in my original contract that the fee will be charged. It usually takes 4-8 hours to get all the info and documentation for a change order to be put together by me our the office. My change orders are usually for larger amounts and require some form of research and technical info.

How many hours do you think goes into one of your change orders?
__________________


Last edited by rbsremodeling; 04-26-2009 at 09:16 PM.
rbsremodeling is offline  
Old 04-26-2009, 11:11 PM   #7
General Contractor
 
nadonailer's Avatar
 
Trade: General Contractor
Join Date: Nov 2005
Location: Coronado, CA (Just outside San Diego)
Posts: 548

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


I don't - if you add enough slush to your original bid and enough to your change order to make it super profitable, then you're fine and it's just going to be looked upon as cheesy (at least in my area). I think a Contractor should have enough in their O&P to cover the pain of doing a simple CO
__________________
"History does not long entrust the care of freedom to the weak or the timid”.
Dwight D. Eisenhower
nadonailer is offline  
Old 04-26-2009, 11:15 PM   #8
Professional Instigator
 
rbsremodeling's Avatar
 
Trade: Design Build Remodeling Contractor DC MD
Join Date: Nov 2007
Location: Washington, DC/ Maryland
Posts: 6,872

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Quote:
Originally Posted by nadonailer View Post
I don't - if you add enough slush to your original bid and enough to your change order to make it super profitable, then you're fine and it's just going to be looked upon as cheesy (at least in my area). I think a Contractor should have enough in their O&P to cover the pain of doing a simple CO
Agreed. Sometimes as bad as this sounds you want to stop random change orders. A few fees attached and they become less random
__________________

rbsremodeling is offline  
Old 04-27-2009, 07:35 AM   #9
Pro
 
Pearce Services's Avatar
 
Trade: Commercial Loading Dock and Door Contractor
Join Date: Nov 2005
Location: Southeastern Massachusetts
Posts: 651

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


My contract specifies a $100 admin fee for any changes. The idea of charging is to stop the changes from destroying the productivity.

I will usually allow one "Mulligan" from which I show them how much disruption, and replanning is caused by changes. Following the signing of the Freebie change order, I tell them to now come clean with any and all idea that they may have for other changes. If we resolve any changes at that time, I will generally waive the admin fee, with a firm understanding that there will be no more freebies. All subsequent changes, additional work, or even discussions that cause a delay to the project will be billed, and due immediately.

The real killer for me has been when more that one decision maker is involved, and the conversations regarding any change could consume a day or more. I try to limit the number of people recognized on my contract as having the authority to make changes.
__________________
Kevin

www.BadcoDoors.com
Pearce Services is offline  
Old 04-27-2009, 11:30 AM   #10
Pro
 
Ed the Roofer's Avatar
 
Trade: Roofing Contractor
Join Date: Dec 2006
Location: NW Suburbs of Chicago
Posts: 7,135

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


It always makes my final invoicing of the project a sheer PITA.

For some items added on, I don't have the invoice from my supplier yet, so I am guessing from the most current price lists.

Then, when I am compiling them at the end, and double and triple checking to make sure I didn't miss anything, or double bill for anything, my concentration waivers too much, at least for me personally.

The extras could be charged at a higher premium too, but then the line item amounts can be questioned more than at the initial proposal stage, because they are broken out.

Ed
Ed the Roofer is offline  
Old 04-27-2009, 05:26 PM   #11
Pro
 
buildpinnacle's Avatar
 
Trade: Public Insurance Adjuster
Join Date: Sep 2008
Location: DFW
Posts: 590

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Ed,

It amazes me how much different roofing in Texas differs from rest of the country. I guess I can throw in OK to boot as I have roofed up there since I was a younger buck. Most subcontractors around here are charging anywhere from $40-$45/sq for a walkable 1 off and they eat the dumps. As none of them have insurance, we have to carry them as uninsured subs on our yearly premium counts. I've been using the same roofing crew for over 3 years now and they do a great job. Every roof we put on down here, we put on like it was recieving a manufacturer's warranty with all the extras. You'd be surprised how many are torn off, some 15# thrown on and new 3tabs thrown up with all the existing flashings, vents, turbines, etc left in place. Noone calculates attic ventilation. I read a post from Douger a few days back where he mentioned the square rate they were getting and I was amazed. I am sure labor, ice damming, and local municipalities come into play much more in your area. I guess that thwarts the 'everything is bigger in TX' addage.

Sorry for the Hijack.

Insofar as the C/O fee. It's kind of like charging for estimate. We all need to be doing it. It's on my long list. This forum has been very helpful for one thing, to say the least. It lets us all know just how inadequately we run our businesses from time to time.
__________________
Pinnacle Limited
Public Insurance Adjusters
(800) 918-7840
buildpinnacle is offline  
Old 05-03-2009, 02:03 AM   #12
Registered User
 
thinking4ward's Avatar
 
Trade: Remodeling Contractor Residential & Commercial
Join Date: Apr 2009
Location: Tallahassee Florida
Posts: 6

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


In the remodeling arena ( at least for me ) I usually have 3 to 4 change orders per job and each change order sheet will have anywhere from two to six items on it. In my contract I have it stated something like this: Any additional work performed that is not stated on the plans, job cost or spec sheet ( at the Owners request or out of neccecity for the project i.e. termite damage, unforseen wood rot etc.) will constitute a change order and will be paid on or before the next scheduled draw. I don't have a specific cost for the change order it self per say however when I do the write up on my job cost sheet it automatically adds in the extra I need to get for supervision, administrative, overhead and profit. This seems to work well, it is stated clearly up front that any extra work will be an extra cost.
thinking4ward is offline  
Old 05-03-2009, 02:27 AM   #13
Pro
 
Ed the Roofer's Avatar
 
Trade: Roofing Contractor
Join Date: Dec 2006
Location: NW Suburbs of Chicago
Posts: 7,135

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Quote:
Originally Posted by thinking4ward View Post
In the remodeling arena ( at least for me ) I usually have 3 to 4 change orders per job and each change order sheet will have anywhere from two to six items on it. In my contract I have it stated something like this: Any additional work performed that is not stated on the plans, job cost or spec sheet ( at the Owners request or out of neccecity for the project i.e. termite damage, unforseen wood rot etc.) will constitute a change order and will be paid on or before the next scheduled draw. I don't have a specific cost for the change order it self per say however when I do the write up on my job cost sheet it automatically adds in the extra I need to get for supervision, administrative, overhead and profit. This seems to work well, it is stated clearly up front that any extra work will be an extra cost.
What method do you use to come up with your supervision and administrative costs to be added on?

A percentage or a fixed fee?

If a fixed fee, how do you work up to that figure?

One more thing, have you found SiteBuildIt easy to use and create your alternative website?

Ed
Ed the Roofer is offline  
Old 05-03-2009, 10:24 AM   #14
Pro
 
buildpinnacle's Avatar
 
Trade: Public Insurance Adjuster
Join Date: Sep 2008
Location: DFW
Posts: 590

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Quote:
Originally Posted by Ed the Roofer View Post

One more thing, have you found SiteBuildIt easy to use and create your alternative website?

Ed

I don't know what 'IT' is, but now I want it.
__________________
Pinnacle Limited
Public Insurance Adjusters
(800) 918-7840
buildpinnacle is offline  
Old 05-03-2009, 10:36 AM   #15
Lack Of All Trades
 
Darwin's Avatar
 
Trade: Professional handyman services
Join Date: Apr 2009
Location: Southeast Michigan
Posts: 1,230

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


No fees for change orders. It seems to penalize the H/O if I brought this up to them. But you could figure in a little somethin' extra when the change order is written...?
Darwin is offline  
Old 05-03-2009, 02:35 PM   #16
LRG WoodCrafting
 
Leo G's Avatar
 
Trade: Master Sawdust Producer
Join Date: May 2005
Location: Windsor Locks, Connecticut
Posts: 13,231

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Why no charge? It will cost you time to figure out what you need to do for the change. Why shouldn't you get paid for your time?
__________________
Sawdust Follows Me Everywhere

Quote:
Originally Posted by HusqyPro View Post
Carpenter by day.
Mad scientist by night.
http://lrgwood.com
Custom Cabinets in Hartford County Connecticut
Leo G is online now  
Old 05-03-2009, 03:14 PM   #17
Pro
 
Mitch M's Avatar
 
Trade: General Contractor
Join Date: Dec 2006
Location: NC
Posts: 473

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


This is what I have in my contracts. I have not had anyone to argue with it yet.

ARTICLE 8. CHANGE ORDERS
8.1 A Change Order is any change to the original plans and/or specifications. All change orders need to be agreed
upon in writing, including cost, additional time considerations, approximate dates when the work will begin and be
completed, and signed by both parties. 10% of the cost of each change order up to a maximum of $1000.00 will be paid
prior to the change, with the remaining amount paid upon completion of the change order. A 20% fee shall be added to all
change orders and overages in excess of initial allowances. Additional time needed to complete change orders shall be
taken into consideration in the project completion date. Only one (1) signature from each respective party to this
agreement shall be necessary to execute the change order.
Owner understands that an estimating and coordination fee of $50 per hour will be incurred on the design, drafting, and
pricing of the change or additional work, whether the change is elected or not by the Owner.
Mitch M is offline  
The Following User Says Thank You to Mitch M For This Useful Post:
Ed the Roofer (05-03-2009)
Old 05-03-2009, 03:17 PM   #18
Custom Stuff
 
Mike(VA)'s Avatar
 
Trade: General Contractor - Custom Renovations
Join Date: Jan 2008
Location: Manassas, VA
Posts: 859

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


This is in our contract:

21. ADDITIONAL WORK AND CHANGE ORDERS: Without invalidating this agreement, Owner(s) and/or Contractor may order extra work or change the existing Contract work by the use of a CHANGE OR ADDITIONAL WORK ORDER. A change may consist of additions, deletions, or modifications to the original Contract work; the Contract sum and Contract time being adjusted accordingly. Any additional sums incurred for such additional work as defined in this section, shall be paid in full (100%), at the next progress payment due or the final payment due, whichever comes first. The change may occur providing the document is mutually agreed to and signed by both the Owner(s) and Contractor. Only one (1) signature from each respective party to this agreement shall be necessary to execute the change order. Such modifications to the original Contract, or subsequent Contracts or CHANGE OR ADDITIONAL WORK ORDERS, will only occur with a signed CHANGE OR ADDITIONAL WORK ORDER.
Owner(s) understand(s) a design/estimating and coordination fee may be incurred on the design, drafting, research, and pricing of the change or additional work, whether the change is elected or not by the Owner(s), and this fee is to be paid in full (100%) prior to the start of any design, drafting, research, or pricing.

This last part leaves the door open to charging a fee, if any, appropriate to the amount of work (and costs) related to preparing the specific change order.
__________________
__________________________________________________ ___________
I EXPECT THAT SOMEDAY I WILL SEE THE FRUITS OF MY LABOR. IS IT SOMEDAY YET?
Clifton, Great Falls, McLean, Fairfax Station, Manassas, Virginia Renovation Contractor
Mike(VA) is offline  
The Following User Says Thank You to Mike(VA) For This Useful Post:
Ed the Roofer (05-03-2009)
Old 05-03-2009, 04:53 PM   #19
Pro
 
Ed the Roofer's Avatar
 
Trade: Roofing Contractor
Join Date: Dec 2006
Location: NW Suburbs of Chicago
Posts: 7,135

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


Thank you both.

I now have some clause revisions to consider and run past my attorney for approval.

Ed
Ed the Roofer is offline  
Old 05-03-2009, 05:23 PM   #20
JimmyS
 
jimmys's Avatar
 
Trade: General contractor
Join Date: May 2009
Location: Mass
Posts: 199

Re: Fees For Change Orders, Not For The Work, Just For Providing The Change Order


We don't charge for change orders, except for not having to shave the way you might for a bid you really want. We handle Allowances and some other to-be-decided line items through change orders. If we charged an admin fee (that showed up on a CO line) that would penalize the customer for, say, a certain tile choice. We do only custom work, and ymmv in a spec or commercial environment of course. My homemade CO form (Excel) shows date updates, dollar updates, etc., and my contract refers to (and includes an attached sample CO) COs, so everyone knows what to expect. I know some guys use COs to bill at a higher rate, but we don't.
Jim
jimmys is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Hiring office work/paper work people? J-Peffer Roofing 3 06-22-2008 11:22 AM
Estimate for Change Order lavoneb Plumbing 2 10-29-2006 03:57 PM
Contract and terms. AFI Painting & Finish Work 28 09-29-2006 07:57 PM
In answer to a closed thread. AAPaint donb1959 Painting & Finish Work 42 08-27-2006 01:36 AM
Work Order Terms and conditions jmejio Business 5 03-18-2006 05:34 AM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?