Contingency Amount?

 
Thread Tools Search this Thread Display Modes
Old 11-14-2009, 12:19 PM   #1
Pro
 
samccard's Avatar
 
Trade: Property Preservation and Remodeling.
Join Date: Aug 2007
Location: Ga.
Posts: 100

Contingency Amount?


I am working on an estimate and got down to the contigency line and started wondering what other use as the percentage for contigency.
If i put to small a percent I could lose money, if I put to large a percent I could overprice the job. I usually bid 3% to 5%. Any opinions?

__________________
www.destinyhomesinc.com
samccard is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 11-14-2009, 12:34 PM   #2
Thom
 
thom's Avatar
 
Trade: General Contractor/Homebuilder
Join Date: Nov 2006
Location: Albuquerque NM
Posts: 3,197

Re: Contingency Amount?


If you're selling jobs based on price, your future looks dark.

Learn to really sell. Sell your company, sell your employees, sell your work. Don't be embarrassed by a higher price.

People are willing to pay more, you need to give them a reason to pay you more.
thom is offline  
The Following 3 Users Say Thank You to thom For This Useful Post:
A W Smith (11-14-2009), bonz (11-17-2009), FlipFlap (11-18-2009)
Old 11-14-2009, 12:46 PM   #3
Pro
 
samccard's Avatar
 
Trade: Property Preservation and Remodeling.
Join Date: Aug 2007
Location: Ga.
Posts: 100

Re: Contingency Amount?


My work speaks for itself, but I still need to be competitive when bidding. Pricing is what more and more consumers are looking at no matter how good the quality. I am not cutting my profits just looking to be competitive on the contingency aspect. If that make sense.
__________________
www.destinyhomesinc.com
samccard is offline  
Old 11-14-2009, 12:56 PM   #4
Thom
 
thom's Avatar
 
Trade: General Contractor/Homebuilder
Join Date: Nov 2006
Location: Albuquerque NM
Posts: 3,197

Re: Contingency Amount?


If you are losing work over the difference between 3% and 5% you are pricing way to tight.

Assuming you are remodeling and working directly for the owner, your margins should be around 50% of sales price. On small jobs (less than a days work) your margins should be much larger. On large jobs, a month or more, your margin could be a little less.
thom is offline  
Old 11-14-2009, 01:00 PM   #5
Pro
 
samccard's Avatar
 
Trade: Property Preservation and Remodeling.
Join Date: Aug 2007
Location: Ga.
Posts: 100

Re: Contingency Amount?


Mostly custom homes, but not on your average lot.
__________________
www.destinyhomesinc.com
samccard is offline  
Old 11-14-2009, 01:07 PM   #6
Average Joe
 
Heritage's Avatar
 
Trade: D/B, Management, Consulting, Contracting.
Join Date: Mar 2007
Location: Toronto
Posts: 1,181

Re: Contingency Amount?


You build custom homes on fixed price

3-5 is small, but most of my jobs are management/cost-plus. Fixed jobs I've never bid less than 10%.

On management/cost-plus I explain the significance of the contingency to the owner/client and they are aware of when we have to dip into those funds, it's never lost me a job and if it did then it worked out for the best I guess.

10% is my standard
__________________
Toronto General Contractor-Renovation Blog-Contractor on Facebook-Renovation on twitter-Contractor Youtube
Quote:
Originally Posted by rex View Post
i get high with my left hand.....
Heritage is offline  
Old 11-14-2009, 09:43 PM   #7
Dave from Macatawa
 
macatawacab's Avatar
 
Trade: GC, cabinet maker and remodeler
Join Date: Jan 2009
Location: Austin, TX
Posts: 277

Re: Contingency Amount?


I have built custom homes for several customers on an open book basis plus stated fee. This is a construction management approach.

before hard contracts are signed w/ subs I keep a 5% contingency.

after contracts are signed, I reduce the contingency to 2.5%
macatawacab is offline  
Old 11-14-2009, 09:48 PM   #8
Lack Of All Trades
 
Darwin's Avatar
 
Trade: Professional handyman services
Join Date: Apr 2009
Location: Southeast Michigan
Posts: 1,230

Re: Contingency Amount?


Quote:
Originally Posted by samccard View Post
I am working on an estimate and got down to the contigency line and started wondering what other use as the percentage for contigency.
If i put to small a percent I could lose money, if I put to large a percent I could overprice the job. I usually bid 3% to 5%. Any opinions?

eleventy-seven%

that way you cover your costs!
Darwin is offline  
Old 11-16-2009, 11:08 PM   #9
Los Angeles Remodeler
 
brooklynite's Avatar
 
Trade: General Contracting
Join Date: Nov 2009
Location: USA
Posts: 84

Re: Contingency Amount?


Contingency is usually 10%

You can negotiate to have no contingency for certain items like separate your material and say no contingency on that. Also your overhead and profit should have no contingency. Plus on the first items you complete you should have a sunset kind-a clause to bill half or some of your contingency after the job is 70% done.
brooklynite is offline  
Old 11-18-2009, 12:48 AM   #10
Pro
 
bconley's Avatar
 
Trade: Kitchen and bath design+remodel
Join Date: Mar 2009
Posts: 710

Re: Contingency Amount?


Make sure it is clear in the contract whose contingency it is, yours or the clients. I feel it is best to "hide" your "contingency" in your overhead and to be clear to the client when and what "their" contingency will be used for.
People feel better not spending the whole contract amount, and having a realistic budget that will get the job done without having to dig unexpectedly into their pockets.
If the job runs smooth you're a hero and everyone is happy... if job has problems there is money there and everyone happy.
bconley is offline  
Old 11-18-2009, 12:57 AM   #11
Pro
 
bconley's Avatar
 
Trade: Kitchen and bath design+remodel
Join Date: Mar 2009
Posts: 710

Re: Contingency Amount?


Unforeseen site conditions should be addressed in the contract, and material price changes from time of estimate to time of signing contract should be documented and then locked in
bconley is offline  
Old 11-18-2009, 12:18 PM   #12
JimmyS
 
jimmys's Avatar
 
Trade: General contractor
Join Date: May 2009
Location: Mass
Posts: 198

Re: Contingency Amount?


Are you required to include contingency money in the contract? I've never done so, though I always recommend people budget 5-7% less than they can spend, since there's always extras.
I agree with the poster who said to be sure you say whose contingency it is. If it's part of the contract price, then do you have to prove each expenditure that is posted against the contingency amount? What a headache! If it's stated but not included in the contract figures, everyone wins. Or maybe these are contracts I'm not used to, since I wrote my own.
Jim
jimmys is offline  
Old 11-18-2009, 02:14 PM   #13
Los Angeles Remodeler
 
brooklynite's Avatar
 
Trade: General Contracting
Join Date: Nov 2009
Location: USA
Posts: 84

Re: Contingency Amount?


Entry corrected:

On most of my projects, change orders that were issued as a result of lack of clarification on the drawings came out of contingency. Change orders as a result of owner requested upgrades came out of owners pocket and were added to the price of the job. At the end, whatever is left from contingency is usually split between the owner and the general contractor.

Last edited by brooklynite; 11-19-2009 at 03:09 AM.
brooklynite is offline  
Old 11-18-2009, 08:24 PM   #14
Pro
 
bconley's Avatar
 
Trade: Kitchen and bath design+remodel
Join Date: Mar 2009
Posts: 710

Re: Contingency Amount?


I think that you are confusing contingency with retainage?
bconley is offline  
Old 11-18-2009, 08:42 PM   #15
Pro
 
bconley's Avatar
 
Trade: Kitchen and bath design+remodel
Join Date: Mar 2009
Posts: 710

Re: Contingency Amount?


This will help...
I haven't done many AIA contracts and the ones I have I was the superintendent working for the GC so my understanding is limited, and yes the projects were smaller-- high end residential and light commercial
Attached Files
File Type: pdf aiap026970.pdf (77.9 KB, 125 views)
bconley is offline  
Old 11-18-2009, 09:39 PM   #16
Dave from Macatawa
 
macatawacab's Avatar
 
Trade: GC, cabinet maker and remodeler
Join Date: Jan 2009
Location: Austin, TX
Posts: 277

Re: Contingency Amount?


let's not confuse contingency and retainage.

A contingency fund may be line itemed in an overall budget, may be required in an individual work category for a sub, or there are jobs run with no contingency set aside in the documents. Project owners are always asked to have an additional source of funds available in case of problems or hidden conditions.

On jobs using the AIA 702/703 there is a retainage line and retainage is defined by contract. Typically 10% is held back until the close out of each subcontractor's work. The retainage is a hold back on the set contract price. Retainage has nothing to do with a contingency. An additional claim against the job by a sub has nothing to do with retainage.

Many jobs have no contingency line on the AIA 702/703. There is not a line item on the AIA form for contingency but there is for retainage.

On the 702/703 there is a line for change orders that add to the contract totals. Those change orders would have a contingency as the source of funds.

Allowance contingencies are another topic but again these do not show on the 702/703 unless they are imbedded in a subs individual contract. If the allowance contingencies are imbedded, then the unused allowance dollars would be a deductive change order lowering the sub's contract and benefitting the owner.

but I digress. 5 - 10% before buying out the job. 2.5 - 5 % after buy out
macatawacab is offline  
The Following User Says Thank You to macatawacab For This Useful Post:
bconley (11-18-2009)


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Storm Chaser Acting As Adjuster AND Using Contingency Contract Found Illegal In Il Ed the Roofer Roofing 6 01-24-2011 04:55 PM
Storm Chasers Blank Price Contingency Contracts Illegal, Charges Filed, Plus More.... Ed the Roofer Roofing 15 06-29-2009 08:10 PM
contingency sum dollar figure ? guapea General Discussion 2 04-27-2009 09:39 AM
Estimating the amount of refuse generated on a job? GTConstruction Construction 5 04-26-2009 05:46 PM
What is your average Invoice dollar amount? Handymanservice General Discussion 84 03-17-2009 09:23 PM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?