When doing time and materials work, do you guys charge for small, miscellaneous supplies? I'm talking nuts, bolts, screws, anchors, etc? I don't, but I think I might try.

I had to sub out a portion of a job a short while back to a plumber. It was just a 2 day T&M thing for him. When I got his bill, I noticed that absolutely everything was itemized on the bill. Nuts, bolts, screws, anchors, and even 2 oz. of plumber's putty and 1/4 tube silicone. This didn't tick me off at all. In fact, it made me smile that he managed to keep track of that stuff.

Is this crazy? Or a worthy idea? By not charging for it presently, I don't believe that I'm giving it away for free. I havn't specifically calculated "hardware" into the overhead, but I've always considered small sundries part of the overhead.

What do you all think?

mdshunk is offline  
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!

Old 11-03-2005, 11:31 PM   #2
Priced In
 
JustaFramer's Avatar
 
Trade: Exiled For Life
Join Date: Jan 2005
Location: Lynnwood,WA
Posts: 3,292

Re: Charging For Sundries


T&M

I charge for everything and leave the item if not completely used or not charge and take the left overs. Depends how much is left and the item.

If a bid items are figured into overhead.
JustaFramer is offline  
Old 11-04-2005, 01:22 AM   #3
Pro
 
Donedat's Avatar
 
Trade: Hardwood Flooring
Join Date: Aug 2005
Location: Washington
Posts: 375
Send a message via MSN to Donedat

Re: Charging For Sundries


I do package deals. If I thing the customer is actually interested in the details I will list all the things that go into the price right on the estimate. One seasoned contractor told me to charge a lot and tell the customer all the things that go into the price. That way they will feel like they know where their money is going.
__________________
I admit...I don't know everything...but don't tell my kids I told you.
Donedat is offline  
Old 11-04-2005, 01:36 AM   #4
Pro
 
Teetorbilt's Avatar
 
Trade: Residential Contractor
Join Date: Feb 2004
Location: Jensen Beach, FL
Posts: 10,475

Re: Charging For Sundries


I've always charged a flat 10% for anything that I'm not making a greater profit on.
__________________
You can't solve you're problems with the same level of thinking that created the problems.

Albert Einstein
Teetorbilt is offline  
Old 11-04-2005, 08:26 AM   #5
Pro
 
housedocs's Avatar
 
Trade: Home Improvement
Join Date: Jan 2005
Location: Moberly, Mo.
Posts: 269

Re: Charging For Sundries


I sort of follow Teeter's example, I charge a flat 8% based upon the materials cost of the job. This I figure to cover nuts, bolts, etc and also to account for expendable items, like saw blades and drill bits. I usually word it something like this,

Expendable materials surcharge, (this covers small expendable items not line item charged on your invoice, nuts, bolts, blades, & bits) $55

I guess there are many ways to look at that, but I figure these are things that I am using and must be replaced periodically, therefore I need to recover those costs from clients.
__________________
"All you need in this life is ignorance and confidence, and then success is sure". -Mark Twain
housedocs is offline  
Old 11-04-2005, 08:34 AM   #6
Custom Builder
 
Glasshousebltr's Avatar
 
Trade: From dirt to ridge vent
Join Date: Feb 2004
Location: South Central Illinois
Posts: 4,403
Send a message via AIM to Glasshousebltr Send a message via Yahoo to Glasshousebltr

Re: Charging For Sundries


I think if I started listing nuts and bolts I might look kinda petty. I usually guess the cost and add it on to the rate. After so many years, I can guess the nuts and bolts pretty damn close.

Bob
__________________
Bob
Glasshousebltr is offline  
Old 11-04-2005, 09:04 AM   #7
Pro
 
housedocs's Avatar
 
Trade: Home Improvement
Join Date: Jan 2005
Location: Moberly, Mo.
Posts: 269

Re: Charging For Sundries


I've had clients that have freaked over the costs of some small items. Quality deck screws for example, most members of the general public probably aren't aware that decent torx head 3-1/2" screws run just over $5 a lb.

Had a perspective client for a deck job comment that they cost more than t-bone steak! Never got the job.
__________________
"All you need in this life is ignorance and confidence, and then success is sure". -Mark Twain
housedocs is offline  
Old 11-04-2005, 09:29 AM   #8
Chief Toilet Mover
 
Mike Finley's Avatar
 
Trade: Bathroom Remodeling
Join Date: Apr 2004
Location: Littleton, Colorado
Posts: 14,078

Re: Charging For Sundries


I don't do T&M jobs but it does stand for Time & Materials so if it goes into the job I don't see how you wouldn't be justified charging it.

On T&M do you work out a mark-up for the materials also or is it just cost?

I always add into my jobs a misc charge of $100.00 just to cover blue tape, plastic tarps, trash bags, gloves, etc...

It's like other companies that have an envirnomental charge say when you buy new tires to dispose of them.
Mike Finley is offline  
Old 11-04-2005, 12:45 PM   #9
Remodeler
 
MinConst's Avatar
 
Trade: Remodeler
Join Date: Oct 2004
Location: Spring Hill, Florida
Posts: 820

Re: Charging For Sundries


This reminds me of a hospital bill. $5.00 for and aspirin, 2 bucks for a band-aid.
I charge Time and Mat for most jobs and do add the Little things in as a lump sum as Materials. I don't like to break it all out. I think it looks petty. But if you don't charge you are loosing money. I don't like to loose money.
__________________
Paul
Minichillo's Construction
Website
I will never leave you hanging!
MinConst is offline  
Old 11-04-2005, 03:32 PM   #10
Bah Humbug!
 
Grumpy's Avatar
 
Trade: Roofing and Gutter Specialist
Join Date: Oct 2003
Location: Chicago
Posts: 8,574
Send a message via AIM to Grumpy

Re: Charging For Sundries


Charge for everything. I yell at my guys, not literally, when they say "Oh I had it on the truck." or "It was only a few shingles I took from storage". If you think that's cheap, at the end of the year add it all up and it will easily buy the christmas party.
Grumpy is offline  
Old 11-04-2005, 08:54 PM   #11
Suck it up, or shut up
 
rservices's Avatar
 
Trade: Flooring, wall covering, Handy-man
Join Date: Aug 2005
Location: wisc
Posts: 399

Re: Charging For Sundries


if I do a a punch list for a customer I charge 10.00 above my trip charge for misc screws and things, if it is a straight repair it's in the cost. Example feild tile cost me about 1.12 a piece I charge 5.00 a piece, that includes my mortar, grout and ,mark up. If it's a large repair tile cost +mortar+ grout+ mark-up.

I dont want to make my invoices look like I'm nickel and dimeing them, but they will usally try to nickel and dime me.
rservices is offline  
Old 11-04-2005, 09:00 PM   #12
DGR,IABD
 
mdshunk's Avatar
 
Trade: Electrical; Commercial and Residential Service
Join Date: Mar 2005
Location: Central PA
Posts: 9,680

Re: Charging For Sundries


I spent a few minutes this evening figuring what some of the items that I never charged for would retail for. For instance, a #10-14 red Rawl plug would be 8 cents and a #12 x 1-1/2" zinc plated hex washer head screw would be 14 cents. That's no small potatos when you add up a bunch of them. I never really realized that I pay about 7 bucks for a can (aerosol can) of silicone sealant. Maybe I should think about switching to tubes.
mdshunk is offline  
Old 11-04-2005, 09:05 PM   #13
Pro
 
plumguy's Avatar
 
Trade: plumbing and heating
Join Date: May 2005
Location: MA
Posts: 295

Re: Charging For Sundries


I don't usually get that specific in my billling as far as itemizing. For instance I may charge $1.50 per 1/2copper fitting and this will cover cleaning brush,sandpaper,flux,propane,solder etc.
plumguy is offline  
Old 11-04-2005, 09:18 PM   #14
Member
 
The Yaz Man's Avatar
 
Trade: Restoration/Remodeler
Join Date: Oct 2005
Location: New York
Posts: 58

Re: Charging For Sundries


If it's open ended service calls or light duty work collect your receipts and tally them up. Once tallied copy and present with a 20% mark-up for overhead and profit.

The 20% can vary based on size of job to 35%. The smaller the job the greater the mark-up to make up for time spent vs. earned monies. Less fat on the smaller ones right?

Really this should take into account the sundries plus the gas, (which really takes it's toll lately) and other things not generally accounted for in time or material.
__________________
Keep the money happy.
The Yaz Man is offline  
Old 11-04-2005, 09:37 PM   #15
DGR,IABD
 
mdshunk's Avatar
 
Trade: Electrical; Commercial and Residential Service
Join Date: Mar 2005
Location: Central PA
Posts: 9,680

Re: Charging For Sundries


Quote:
Originally Posted by The Yaz Man
... collect your receipts and tally them up. Once tallied copy and present with a 20% mark-up for overhead and profit.

The 20% can vary based on size of job to 35%...
Yaz, I appreciate your willingness to help me with my question. I must say, however, that this is profoundly bad advice that you've given. Where did those numbers come from? Out of the clear blue sky? Perhaps these numbers work for you, and they may work for others. They will not work for me, unless I intend to switch my diet to beans and weenies.
mdshunk is offline  
Old 11-04-2005, 10:34 PM   #16
Deck Designer/Builder
 
DecksEtc's Avatar
 
Trade: Construction Project Manager
Join Date: Oct 2004
Location: Whitby, Ontario
Posts: 2,426

Re: Charging For Sundries


When I started out figuring out my costs, i.e. cost per square foot for decks or cost per linear foot for fencing, I took into account ALL the material costs. This included the cement, sonotubes, lag bolts, fence clips, etc., etc. - right down to the number of screws and/or nails needed for a job. I also re-work these numbers every couple of jobs, just to make sure my pricing is still in line. Also, the type of deck can vary the pricing of some of these items. For example, the fasteners for Trex are significantly higher than the screws for Cedar or PT.

The above may not apply exactly to your original question but my point is that I think you should take into account everything you spend on a job and make sure you're compensated for it. Maybe not itemize it line by line but definately make sure you're reimbursed for everything.
DecksEtc is offline  
Old 11-05-2005, 03:40 PM   #17
Member
 
The Yaz Man's Avatar
 
Trade: Restoration/Remodeler
Join Date: Oct 2005
Location: New York
Posts: 58

Re: Charging For Sundries


I think that it maybe profoundly misplaced advice. It does work for me. I bill by hour and that is where my real profit margin lies. Material data and costing mark-ups apply well for me and as I stated the mark-up is not profit driven it's really an o+p exchange that covers miscellany. Which I think was the foundation of your original post.

And no the 20 to 35% mark up is a benchmark not a product of gazing at clouds. And maybe as an electrician you don't deal with it or maybe I was taught wrong. I spent many years as a project manager for a very large General Contracting Firm they seemed to do well with it.

The 20 to 35%, which was pounded into my head, is based upon a 10 and 10 theory utilized in the insurance adjusting business. That theory was based upon the contractors who many years ago set terms with carriers to do work of many sizes, not just service based, without proposals. It developed out of a need to repair and restore property at an expedited rate. One takes the Labor and Material costs and adds ten percent for overhead and rolls a further cumulating ten percent for profit.

In recent years the ten and ten has creeped toward a non-cumulative 20% since, as I'm profoundly sure you know, the cumulating 10 and 10 adds an additional 1% profit to the bottom line.

When applied to standard contract actions not constricted by the insurance carriers a 20 to 35% is generally used. I have taken that standard billing procedure learned at a powerhouse here in New York and moved onto my own company where it has succeeded very nicely.

The original question of sundries is noted and I only threw my two cents in MD. I can only comment on what I know and by your post you seemed almost offended by my method and any mention of it. I am profoundly sorry.
__________________
Keep the money happy.
The Yaz Man is offline  
Old 11-05-2005, 03:47 PM   #18
Member
 
The Yaz Man's Avatar
 
Trade: Restoration/Remodeler
Join Date: Oct 2005
Location: New York
Posts: 58

Re: Charging For Sundries


I like Decks etc 's method for general and continued pricing. I can't use it because of my short attention span.

Mostly I walk a job, eyeball it and a throw a number at it. I will not state the rest of my negotiation methods concerning setting final price. I still have balck and blues from my previous thread.
__________________
Keep the money happy.
The Yaz Man is offline  
Old 11-05-2005, 03:53 PM   #19
Priced In
 
JustaFramer's Avatar
 
Trade: Exiled For Life
Join Date: Jan 2005
Location: Lynnwood,WA
Posts: 3,292

Re: Charging For Sundries


I think a 10% markup on a product you get a contractor discount on is fair. Right maybe I am wrong.
JustaFramer is offline  
Old 11-05-2005, 04:10 PM   #20
Member
 
The Yaz Man's Avatar
 
Trade: Restoration/Remodeler
Join Date: Oct 2005
Location: New York
Posts: 58

Re: Charging For Sundries


Well who gets the break Justa? I act as the General Contractor and receive no discount at all. I get a reduced rate, presumably wholesale, that is then marked up to retail on the direct contract.

There is no such thing as a discount for us.

Essentially you act as a purchasing agent at the wholesale level. Hence resail certificates. Then you boost the cost back to the retail level where you collect the sales tax and deliver it at the retail rate to the Fed.

The first 10% is the retail end or Overhead integer. The 2nd is the Profit margin. All of this is structured theory. It's going to vary from me to you to MD. We are all right if we survive and succeed.
__________________
Keep the money happy.
The Yaz Man is offline  


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Charging for quotes phillter General Discussion 4 03-06-2007 12:26 PM
Yellow Jacket Test and Charging Manifold man6_27260 Contractor Swap 0 03-04-2007 03:28 AM
What are you charging to upgrade Res. services? steve-in-kville Electrical 1 09-29-2006 01:11 AM
Charging for incidental hardware mdshunk Business 37 09-03-2006 04:03 PM
charging for repairs you couldn't make scottstef Business 3 08-24-2006 10:08 AM

Join Now... It's Fast and FREE!

Privacy Badge
I am a professional contractor
I am a DIY Homeowner
ContractorTalk.com is for
PROFESSIONAL CONTRACTORS ONLY!

At ContractorTalk.com we cater exlusivly to professional contractors who make their living as a contractor. Knowing that many homeowners and DIYers are looking for a community to call home, we've created www.DIYChatroom.com DIY Chatroom is full of helpful advices and perfect for DIY homeowners.

Redirecing in 10 seconds
No Thanks
terms of service

Already Have an Account?