EPDM how to
Firstly , I am a contractor and have been doing renos for the last 20 yrs so I do have a range of knowledge on houses. My situation is I have a rental cottage with a nearly flat (probably 1 / 12 pitch) roof 20 x 25 that is currently tar and gravel and seen better days. There is some soft spots that I need to fix and also tear off all the old roofing.Recently I scrounged from a commercial installation an EPDM roof that was up for 3 yrs before it was removed for an expansion of the building. I have a 1 piece no seams section big enough for the cottage roof and would only need to add one plumbing vent boot to the sheet.In its commercial instalation it was loose lay with a layer of drain rock but I have seen in residential it is glued down. Is there a reason or benefit to either system and if glued is it straight down to plywood or is there some other layer between it and the plywood.The last thing I want to do is skip an important step and have to redo all my hard work( I hate that)
|
|
|
Warning: The topics covered on this site include activities in which there exists the potential for serious injury
or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Join the #1 Contractor Forum Today - It's Totally Free!
ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!
Join ContractorTalk.com - Click Here

|
11-08-2009, 05:09 AM
|
#2
|
|
Pro
Trade:
LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,089
|
Skip, welcome to CT, please complete your profile, then go to the intro page and tell the guys a little about yourself and your proffessional exp, thanks GMOD
__________________
|
|
|
11-08-2009, 06:46 AM
|
#3
|
|
Registered User
Trade:
Roofer
Join Date: Sep 2009
Location: SW Minnesota
Posts: 15
|
Skip- Rocks are cheaper than bonding adhesive/ On the down side, if something pokes a hole in the rubber, lots a luck finding it.
Glue it if possible..... Benefits- won't shrink, easy leak repair, easy inspections,won't collect dirt,rocks are heavy...............etc.........
|
|
|
11-08-2009, 01:08 PM
|
#4
|
|
New Guy
Trade:
window and door installer
Join Date: Nov 2009
Location: Vancouver BC
Posts: 25
|
profile updated...
|
|
|
11-08-2009, 01:12 PM
|
#5
|
|
New Guy
Trade:
window and door installer
Join Date: Nov 2009
Location: Vancouver BC
Posts: 25
|
workorfish- so I don't need to worry about UV or other exposure then?
The roof is below three large pine and cedar trees and gets a good 6" of debris each year so no rocks would make it much easier to cleanup.
|
|
|
11-08-2009, 06:37 PM
|
#6
|
|
Pro
Trade:
LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 5,089
|
Quote:
Originally Posted by skipdow
profile updated...
|
Thanks
__________________
|
|
|
11-08-2009, 08:25 PM
|
#7
|
|
Registered User
Trade:
Roofer
Join Date: Sep 2009
Location: SW Minnesota
Posts: 15
|
Good to go, good luck! NO wrinkles!!
|
|
|
11-08-2009, 09:11 PM
|
#8
|
|
New Guy
Trade:
window and door installer
Join Date: Nov 2009
Location: Vancouver BC
Posts: 25
|
Well I dove rite in and started to scoop the debris off. I completely shoveled it off 3 yrs ago and now it is almost 10" deep in some spots, lots of trees around it.It resembled a thick layer of peat and was surprisingly fluffy and most of it light.
I used OSB for me to walk on as it unfortunately seems to have several soft spots
I chopped into one soft area and found ship lap running across 2" x 6" ceiling joists(not 1 1/2 x 5 1/2). the ceiling is vaulted so on the bottom of this is vapor barrier and gyproc with fiberglass insulation. Not what I thought was there. My thoughts would be that I have to strip the ship lap, strap it (for cross ventilation) then new ply. I was considering adding a layer of rigid foam insulation as well to make it more efficient and reduce the cold(condensation) on the joists.
does that seem correct, any suggestions?
Once I reach my 15 posts I'll post pics of my progress
|
|
|
11-08-2009, 10:00 PM
|
#9
|
|
Capra aegagrus
Trade:
Remodeler
Join Date: Jan 2008
Location: Central Pennsylvania
Posts: 2,468
|
Quote:
Originally Posted by skipdow
My thoughts would be that I have to strip the ship lap, strap it (for cross ventilation) then new ply. I was considering adding a layer of rigid foam insulation as well to make it more efficient and reduce the cold(condensation) on the joists.
|
If the ship lap is shot, by all means strip it out of there. I'm not sure exactly what you're up to with strapping for cross ventilation. If there's no air gap above the insulation, it probably wouldn't hurt to create one. But in my area, we fasten the sheathing directly to the joists.
Once the sheathing's down, add a layer of fiberboard, secured with screws and stress plates (3" galvanized washers). The rubber is then glued down onto that surface. Any roofing supply company in your area should be able to set you up with what you need to complete the job; normally they're very helpful.
|
|
|
11-08-2009, 10:19 PM
|
#10
|
|
Pro
Trade:
Carpenter/GC
Join Date: Mar 2008
Location: Boston, Mass
Posts: 339
|
Give the membrane a good look over before you apply it. Unless you were the one to take it off, who knows how it was handled. Holes can be patched easily as long as you can find them.
Get plenty of help when you go to set it, and if you have never done it before a 20' sheet can be tough to work. Might want to try a practice run at how to lay it down before you glue it up. Once it's down it won't want to move.
|
|
|
11-08-2009, 10:55 PM
|
#11
|
|
New Guy
Trade:
window and door installer
Join Date: Nov 2009
Location: Vancouver BC
Posts: 25
|
I've glued laminate down and its just as unforgiving about 2nd tries.
as to the strapping, I have always assumed in a vaulted area(no attic) moisture can get trapped in each joist area and have no exit which causes rot. Cross ventilation gives a way for moisture to travel to vents to the exterior and ensure it stays dry
|
|
|
11-09-2009, 01:50 PM
|
#12
|
|
stop botherin' me!
Trade:
Roofing Siding Gutters Windows
Join Date: Oct 2003
Location: Chicago
Posts: 7,666
|
Go to Versico.com there are free training videos.
My preferred method is mechanically attached for single ply. It goes down quicker and cheaper than fully adhered. We haven't done any balalsted but have bid several. Ballasted goes down ultra quick and cheap and very very economical on large buildings, however not every building can support the weight so is not a good retro-fit choice.
installation of epdm over plywood is acceptable if the plywood is fastened using screws, soemtimes stainless are required. I am not a fan of this application and have only done it once. IMO install at least a 1/2" fiberboard if you are not looking for any R value. Or else if you do desire R value look into Polyisocyanurate.
|
|
|
11-09-2009, 02:23 PM
|
#13
|
|
Pro
Trade:
siding
Join Date: Mar 2007
Location: west milford n.j.
Posts: 3,137
|
build a peak over it
__________________
Tom
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate This Thread |
Linear Mode
|
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|