Warmboard Installation
We will be framing an addition soon and the plans have changed to include Warmboard as the subfloor instead of traditional methods.
The company says the framing contractor should be the one who installs this, and it does not seem too technical. Although it is quite a bit more technical than throwing down some OSB.
My questions are: Does anyone have experience with this product? Any tips, hints, etc.? And most importantly, since I have already been awarded the contract...are there justifiable reasons why I should increase the cost of installing this (takes longer, need a PHD) ?
More info is available at http://www.warmboard.com/technical-i...install-guide/
|
|
|
Warning: The topics covered on this site include activities in which there exists the potential for serious injury
or death. ContractorTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Join the #1 Contractor Forum Today - It's Totally Free!
ContractorTalk.com - Are you a Professional Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for contractors to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your trade is you'll find that ContractorTalk.com is a great community to join. Best of all it's totally free!
Join ContractorTalk.com - Click Here

|
10-08-2009, 04:46 PM
|
#2
|
|
Internet Creep
Trade:
Kitchen/Bath Remodeling, Tile
Join Date: Oct 2007
Location: Will County, Illinois
Posts: 1,183
|
Quote:
Originally Posted by innovous
are there justifiable reasons why I should increase the cost of installing this (takes longer, need a PHD) ?
|
Hell yes there is!!! Keeping the channels aligned is imperative. That will surely add time to your installation. Also, not sure if you have a typical method to your installs but you will most likely have to follow a schematic from either Warmboard or the designer/engineer that laid out the system in the first place. Finally, you will probably also end up hand routing some of the channels.
I cannot tell you how much time, but definitely add something. Don't lose your ass!
__________________
"If you're good at something, never do it for free."
|
|
|
10-08-2009, 04:53 PM
|
#3
|
|
Pro
Trade:
LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 4,153
|
It is a project, i have installed similar systems by stadler, they supply me with full floorplans showing zone locations, feeds and returns. G
__________________
|
|
|
10-08-2009, 05:02 PM
|
#4
|
|
Member
Trade:
Residential & Commercial Remodeling / Roofing
Join Date: May 2007
Location: Denver
Posts: 40
|
Thanks guys.
Gene -- do you recall your production output for the stadler systems?
After accounting for time to sort the panels, additional time for cutting (thicker, cuts need to be perfect, and requires carbide blade), adding time to line up, check, line up, check, and line up the channels I see this adding 2 days to my overall schedule at the bare minimum.
Not to mention I am sure someone would like me to warranty this
|
|
|
10-08-2009, 08:14 PM
|
#5
|
|
Member
Trade:
Design/Build Remodeler
Join Date: Oct 2009
Location: Denver
Posts: 96
|
Quote:
Originally Posted by innovous
Thanks guys.
...........I see this adding 2 days to my overall schedule at the bare minimum.
Not to mention I am sure someone would like me to warranty this 
|
How big is the addition?
__________________
"Time stays long enough for those who use it"
Leonardo da Vinci (1452-1519)
|
|
|
10-08-2009, 08:30 PM
|
#6
|
|
Member
Trade:
Design/Build Remodeler
Join Date: Oct 2009
Location: Denver
Posts: 96
|
You'll also need their router templates. Warmboard sells them - but ours have been sitting in storage for a few years collecting dust - let me know.
__________________
"Time stays long enough for those who use it"
Leonardo da Vinci (1452-1519)
|
|
|
10-08-2009, 10:50 PM
|
#7
|
|
Member
Trade:
Residential & Commercial Remodeling / Roofing
Join Date: May 2007
Location: Denver
Posts: 40
|
Quote:
Originally Posted by DaVinciRemodel
How big is the addition?
|
When I first posted it was about 1,050sf that was getting the Warmboard. Now it has scaled back to just over 280sf. Right now I am planning to add an extra day.
As far as the router templates...I will talk with Warmboard and see if they are automatically included with the install pack, I will send you a pm.
Thanks.
|
|
|
10-08-2009, 11:00 PM
|
#8
|
|
Pro
Trade:
LI,NY designer, new homes, renovation work, concre
Join Date: Mar 2008
Location: Long Island, NY
Posts: 4,153
|
Quote:
Originally Posted by innovous
Thanks guys.
Gene -- do you recall your production output for the stadler systems?
After accounting for time to sort the panels, additional time for cutting (thicker, cuts need to be perfect, and requires carbide blade), adding time to line up, check, line up, check, and line up the channels I see this adding 2 days to my overall schedule at the bare minimum.
Not to mention I am sure someone would like me to warranty this 
|
Fiest time, 2 days, play it safe. G
__________________
|
|
|
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Rate This Thread |
Linear Mode
|
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|